Little v. District of Columbia

19 Ct. Cl. 323, 1884 U.S. Ct. Cl. LEXIS 79, 1800 WL 1132
CourtUnited States Court of Claims
DecidedMarch 24, 1884
DocketNo. 352
StatusPublished
Cited by6 cases

This text of 19 Ct. Cl. 323 (Little v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Little v. District of Columbia, 19 Ct. Cl. 323, 1884 U.S. Ct. Cl. LEXIS 79, 1800 WL 1132 (cc 1884).

Opinion

Drake, Ch. J.,

delivered the opinion of the court:

Michael Shiner, the claimant’s intestate, had two contracts in writing, entered into in September, 1871, with the Board of Public Works of the District of Columbia, for the grading of Eleventh street east, between Pennsylvania avenue and H street; one numbered 109 and the other 110.

The price stipulated in the contracts to be paid for the grading was 20 cénts per cubic yard.

Under those contracts Shiner, prior to the 29th of August, 1872, graded 19,591 cubic yards; which was but a small portion of the whole grading required by the contracts. Of the quantity graded, 6,833 yards were done before January 8,1872, and the other 12,758 yards between that day and August 29, 1872.

For the former quantity the claimant asks only 20 cents per cubic yard; for the latter 30 cents per yard. The grounds upon which he rests the latter claim are as follows :

January 22,1872, the Board of Public Works adopted the following order:

Ordered, That the prices of grading be fixed at 30 cents per cubic yard, including the hauling, not to exceed 200 feet; for each additional 200 feet one cent additional per cubic yard will be allowed.”

September 6,1872, the Board ordered that contracts 109 and 110 should be canceled, and a new one prepared, dated after [325]*325the establishment of present rates, that is, 30 cents per cubic yard, for such work, and allowing Shiner that rate for the same.

In pursuance of this order, there was drawn up a contract-r-No. 2l6¿ — dated January 25,1872, stipulating for the payment to Shiner of 30 cents per cubic yard for grading, which should include the first 200 feet of hauling, and one cent per cubic yard for every additional 200 feet of hauling.

This paper was signed by Shiner, but not by any member or officer of the Board of Public Worlcs; and on the 22d of October, 1872, it was by that Board ordered to be canceled, and the work to be given to another contractor, Shiner having failed to go on with the work on Eleventh street, though he was notified by the Board, on the 21st of September, that unless he immediately proceeded with the execution of contract 216 J, the same would be taken from him and given to another.

In connection with this statement we would say, in advance, that we use the words “canceled” and “cancellation” not in the strict legal acceptation of those terms, but because they are used in the proceedings of the Board. As will presently appear, the fifth article of each contract provided that the Board of Public Works, in certain contingencies, might discontinue all of the worlc under it,; and beyond doubt this was what was meant and understood by both parties by the words “canceled” and 0 cancellation.” Therefore, for convenience sake, we continue to use those words, but in the sense in which the parties regarded them.

So far as the first two contracts are concerned, the claimant, by not suing on them, or either of them, and by suing on the third alone, and claiming the rate of compensation stipulated for in it, waives all objection .to their being taken from him, or “ canceled.”

Now, upon these facts, what is the claimant’s case as presented in his petition? The petition sets out contract 216¿- as the basis of the action, and alleges that the grading of the 19,591 cubic yards was done under that contract, and ought to be paid for at 30 cents per cubic yard and hauling, instead of 20 cents per yard and no hauling.

We are not able to discover any foundation for such a claim. Every fact in the case is against it.

[326]*3261. The grading of 19,'591 cubic yards was all done before contracts 109 and 110 were canceled, and at a time when there was not the least ground for claiming it to have been done under any other contract.

2. The order of January 22, 1872, increasing the rates for grading was not retrospective in its operation; did not refer to contracts previously entered into on other rates; did not mention Shiner or his contracts; and if it had specifically named him and directed him to be paid the higher rates, would not have legally bound the defendant to pay those rates. This was so held by this court in Roche v. The District of Columbia, (18 C. Cls. R. 217), which was just such a case as this.

3. The paper set out in the petition as “ a contract in writing duly made and entered into,” by the Board of Public Works and Shiner, never was so made and entered into. As before stated, it was signed by him, but not by any member or officer of the Board. In section 37 of the act of February 21,1871, “ to provide a Government for the District of Columbia” (16 Stat. L., 119, 127), it was provided that—

“All contracts made by the said Board of Public Works shall be in writing, and shall be signed by the parties making the same, and a copy thereof shall be filed in the office of the secretary of the District.”

In the face of this absolute requirement we are at a loss to comprehend how it could be averred that the paper set forth in the petition was “ a contract in writing duly made and entered into ” by the Board of Public Works.

The only answer to this, attempted by the claimant’s counsel, was, that “it cannot be disputed that contract 216£ contains the intention of said Board and its agreements with the claimant, as disclosed by the official correspondence given in the record.” It needs but a word to show the fallacy of such a position. The Board’s “intention” as to any contract could be lawfully indicated only by what the members of the Board signed. There might be circumstances in which the “official correspondence” of the Board could be resorted to to discover or interpret the intention of its acts; but it is impossible, in view of that statutory provision, to charge the Board as a contracting party by any such resort.

In no view can the paper numbered 216J be held to be a contract, or to form a basis for any recovery by the claimant in this action.

[327]*327There remains another matter to be disposed of, — the set-off which the defendant claims, based on the increased expense to which the District was subjected by having the grading of Eleventh street completed by others, over and above what it would have had to pay Shiner if he had completed it at 20 cents per cubic yard. It is found that that increased expense was $6,428.10. Was Shiner liable under contracts 109 and 110 to repay than amount to the Board of Public Works'?

In each of these contracts was an article in the following words:

u Fifth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oberndorfer v. United States
65 Ct. Cl. 376 (Court of Claims, 1928)
Denver & Rio Grande Railroad v. United States
53 Ct. Cl. 155 (Court of Claims, 1918)
Gonzales y Garcia v. United States
37 Ct. Cl. 243 (Court of Claims, 1902)
Barnes v. District of Columbia
22 Ct. Cl. 366 (Court of Claims, 1887)
Henry v. United States
22 Ct. Cl. 75 (Court of Claims, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
19 Ct. Cl. 323, 1884 U.S. Ct. Cl. LEXIS 79, 1800 WL 1132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/little-v-district-of-columbia-cc-1884.