Lindon City v. Engineers Construction Co.

636 P.2d 1070, 1981 Utah LEXIS 891
CourtUtah Supreme Court
DecidedSeptember 21, 1981
Docket17141
StatusPublished
Cited by35 cases

This text of 636 P.2d 1070 (Lindon City v. Engineers Construction Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lindon City v. Engineers Construction Co., 636 P.2d 1070, 1981 Utah LEXIS 891 (Utah 1981).

Opinion

HALL, Chief Justice:

This is an appeal from the dismissal of a complaint seeking a declaratory judgment as to rights and obligations of the litigants under a contract that included provisions calling for arbitration of any disputes that might arise out of the contract. The contract was for construction of a facility for the plaintiff, Lindon City, and resulted after the defendant, Engineers Construction, was the low bidder on an advertised invitation for bids. Both parties agreed to the arbitration by the designated American Arbitration Association. The entire contract was prepared by the City and the arbitration provision was a condition necessary to bind the parties to its terms.

Two disputes did arise: one as to the rate of interest on delinquent contract payments, and the other as to whether there had been a “final payment” by check that did not include the disputed interest.

Engineers claimed that payment had not been made, and requested and gave notice for arbitration according to the contract’s terms. Before the date of hearing, the City refused to arbitrate and filed this suit for declaratory judgment.

The contract provisions that are of vital concern in resolving this litigation are reproduced as follows:

Section 30.1. All claims, disputes and other matters in question arising out of, or relating to, the CONTRACT DOCUMENTS or the breach thereof, except for claims which have been waived by the making and acceptance of final payment as provided by Section 20, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. *1072 This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in any court having jurisdiction thereof.
Section 19.6 If the OWNER fails to make payment 30 days after approval by the ENGINEER, in addition to other remedies available to the CONTRACTOR, there shall be added to each such payment interest at the maximum legal .rate commencing on the first day after said payment is due and continuing until the payment is received by the CONTRACTOR.
Section 20.1 The acceptance by the CONTRACTOR of final payment shall be and shall operate as a release to the OWNER of all claims and all liability to the CONTRACTOR ....

It would appear that the “disputes” mentioned above are particularly suited and designed for determination by arbitration by the very provisions insisted upon by the City for inclusion in the very contract it drafted and required as a condition for acceptance of bids. If not so intended to be arbitrable, it is suggested that few, if any, situations or “disputes” would survive for arbitration under such a superficial conclusion. We are of the opinion that a claim, followed by denial of the interest agreed upon and whether final payment under the contract had been made, are “disputes” under the plain, clear wording of the contract provisions set out above, and we so hold.

The only question, therefore, is whether the plaintiff City was premature in filing for declaratory judgment — not whether such a suit is impermissible under any circumstances because of the arbitration agreement. We are convinced that before the plaintiff filed this suit, it was bound by its promise, first, to seek arbitration, then to litigate, if it could under its contract, or under either the Arbitration Act 1 or the Declaratory Judgment Act. 2

The plaintiff asserts that the trial court held that it had no “standing” in court, while defendant contends the trial court held the suit to be “premature.” The statements of the court indicate that it adjudged that the suit was premature. Whatever term is or was used, it connotes the conclusion that in any event the parties covenanted to arbitrate first; otherwise, the provisions therefor would make no sense. There is no question before this Court as to filing suit after arbitration failed, and therefore we need not discuss it except to say that, in fact, the Arbitration Act itself provides for such litigation in U.C.A., 1953, 78-31-13:

The arbitrators may on their own motion, and shall by request of a party to the arbitration:
(1) At any stage of the proceedings submit any question of law arising in the course of the hearing for the opinion of the court, stating the facts upon which the question arises, and such opinion when given shall bind the arbitrators in the making of their award.
(2) State their final award, in the form of findings of fact, for the opinion of the court on the questions of law arising on the hearing.

The trial court decided the suit was premature, as do we. Resort to the arbitration process has not been had, as agreed, and the arguments as to what the declaratory judgment says or does, are not germane here. Neither are those touching the jurisdiction of the arbitrator or issues determinable by the arbitrator in the first instance, such as “future” versus “present” disputes, whether the contract complies with the Arbitration Act, and whether the 1977 amendment to the Act or its predecessor prevailed. The decision of the trial court cannot be interpreted other than to say that none of the above matters can properly be heard by the court prior to arbitration.

As to whether the content of a contract is arbitrable, doubts should be resolved in favor of the parties’ freedom to *1073 contract. 3 As was stated in King County v. Boeing Company: 4

Arbitration is a contractual remedy for the settlement of disputes by extrajudicial means. It is a remedy freely bargained for by the parties, and “provides a means of giving effect to the intention of the parties, easing court congestion, and providing a method more expeditious and less expensive for the resolution of disputes.” There is a strong public policy in favor of such a remedy, but it should not be invoked to resolve disputes that the parties have not agreed to arbitrate.
* * * * * *
Arbitration clauses should be liberally interpreted when the issue contested is the scope of the clause. If the scope of an arbitration clause is debatable or reasonably in doubt, the clause should be construed in favor of arbitration unless it can be said that it is not susceptible to an interpretation that covers the asserted dispute.... If an arbitrable issue exists, the parties should not be deprived of the benefits of the agreement for which they bargained. [Citations omitted.] 5

There is nothing in the contract here that is unclear, ambiguous or vague, and even if there were, the parties have agreed to arbitrate such things first. There is nothing in the contract that an average, literate person would not be able to read and interpret such as to demand a judge’s decision rather than a competent arbitrator.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marzano v. Proficio Mortgage Ventures, LLC
942 F. Supp. 2d 781 (N.D. Illinois, 2013)
Lamkin v. Morinda Properties Weight Parcel, LLC
440 F. App'x 604 (Tenth Circuit, 2011)
Peterson & Simpson v. IHC Health Services, Inc.
2009 UT 54 (Utah Supreme Court, 2009)
Duke v. Graham
2007 UT 31 (Utah Supreme Court, 2007)
Wood v. University of Utah Medical Center
2002 UT 134 (Utah Supreme Court, 2002)
Laney v. Fairview City
2002 UT 79 (Utah Supreme Court, 2002)
McCoy v. Blue Cross and Blue Shield of Utah
2001 UT 31 (Utah Supreme Court, 2001)
Dairy Product Services, Inc. v. City of Wellsville
2000 UT 81 (Utah Supreme Court, 2000)
Jenkins v. Percival
962 P.2d 796 (Utah Supreme Court, 1998)
Rollings v. Thermodyne Industries, Inc.
1996 OK 6 (Supreme Court of Oklahoma, 1996)
Allred v. Educators Mutual Insurance Ass'n of Utah
909 P.2d 1263 (Utah Supreme Court, 1996)
Park City Education Ass'n v. Board of Education
879 P.2d 267 (Court of Appeals of Utah, 1994)
Chandler v. Blue Cross Blue Shield of Utah
833 P.2d 356 (Utah Supreme Court, 1992)
Cady v. Allstate Insurance
747 P.2d 76 (Idaho Court of Appeals, 1987)
Docutel Olivetti Corp. v. Dick Brady Systems Inc.
731 P.2d 475 (Utah Supreme Court, 1986)
Utah Restaurant Ass'n v. Davis County Board of Health
709 P.2d 1159 (Utah Supreme Court, 1985)
Berrett v. Stevens
690 P.2d 553 (Utah Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
636 P.2d 1070, 1981 Utah LEXIS 891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lindon-city-v-engineers-construction-co-utah-1981.