Linbeck Construction Corporation v. National Labor Relations Board

550 F.2d 311, 94 L.R.R.M. (BNA) 3230, 1977 U.S. App. LEXIS 13888
Court of Appeals for the Fifth Circuit·Decided April 11, 1977·No. 75-3555·Published·Cited by 20 cases

Opinion

LEWIS R. MORGAN, Circuit Judge:

Linbeck Construction Company [Linbeck] petitions for review of an order of the National Labor Relations Board issued on August 5, 1975, 219 N.L.R.B. No. 133. That order concerns two segments of picketing during the summer of 1974 that Linbeck alleges to have violated Section 8(b)(4)(i)(ii)(B) of the National Labor Relations Act. 1

I. Facts.

Linbeck was the general contractor for the construction of a shopping mall in Austin, Texas. The excavation, paving, sani *314 tary, and storm sewer work was subcontracted to Luckie Construction Company [Luckie], a non-union employer. Shortly after construction began in June of 1973, Linbeck barricaded all entrances to the project except an entrance on Northcross Drive designated for the use of Luckie’s employees and suppliers [Luckie gate] and an entrance on Anderson Lane [Linbeck gate] reserved for the employees and suppliers of Linbeck and the other subcontractors. 2 Despite the restrictions indicated on the gate signs, Luckie’s employees and suppliers continued to enter the job site through the Linbeck gate.

On June 20, 1974, upon hearing rumors that the International Union of Operating Engineers, Local Union No. 450, AFL-CIO [Union] intended to picket the job site to protest Luckie’s non-union hiring practices, Linbeck’s project manager sent the Union a telegram stating that Linbeck had designated the Northcross gate for the use of Luckie, its employees, materials and equipment; other employers, their suppliers, and employees would use the Linbeck gate. On June 24, the Union set up two pickets: one at the Luckie gate and one who walked 100-150 feet on Anderson Lane, but who never came closer than 100 feet to the Linbeck gate. Picketing continued in this fashion through June 26. While Luckie employees used only the Luckie gate to enter the site during this period, materials to be used by Luckie, such as cement, steel, and crushed stone, were delivered through the Linbeck gate and were signed for by Lin-beck employees. Prior to the picketing, such materials had been received by Luckie employees.

On June 26, Linbeck’s project manager sent the Union a telegram indicating that henceforth Luckie would cease working on the job site between 7:30 a. m. and 4:30 p. m. on weekdays, instead working between 5:00 p. m. and 7:00 a. m. on weekdays and twenty-four hours a day on weekends; upon receipt of the telegram, the Union removed its pickets. Linbeck subsequently sent the Union a letter informing it that Luckie would not resume work until July 19. Thereafter, Luckie did not return to the site until July 20 and the Union did not resume picketing until July 24. 3 Upon resuming work on July 20, Luckie’s employees, who entered the job site each evening through the Luckie gate, adhered to their announced schedule and were not on the job site during the weekdays. Materials that Luckie worked on in the evenings, however, were delivered during the day at the Lin-beck gate and received by the general contractor’s employees. In addition, Luckie and his foreman, Joe Jackson, visited the job site on two occasions during the day to examine the materials that had been delivered and to make preparations for their crew’s work that evening.

On the evening of July 24, when Luckie employees were working on the job site, the Union, displaying the same picket signs as those used in June, resumed its picket of the Luckie gate. 4 The pickets returned during the day on July 25 and July 26 to the Luckie gate and, in response to the barricaded gate and covered gate sign, 5 covered their own sign, which indicated the object of their grievance. On July 29, 30, and 31, 6 picketing again occurred at the Luckie gate, this time with the picket sign *315 uncovered, but on August 1 the picket again covered his sign. On August 2, he picketed for a couple of hours with an uncovered sign before leaving. No picketing, with a covered or uncovered sign, has occurred since that time.

II. Findings by Administrative Law Judge and Board.

The Administrative Law Judge concluded that the June 24-26 picketing at Anderson Lane, 7 100 feet from the Linbeck gate, did not constitute a violation of § 8(b)(4)(i)(ii)B, but that the July 25-26 and July 29-August 2 picketing did violate the National Labor Relations Act’s prohibitions against secondary activity. Upon review of the judge's findings, the Board held that neither segment of picketing violated the Act. The Administrative Law Judge concluded that the June picketing was legal primarily on the ground that a telegram, alone, could not convert a previously integrated job into a job separated by reserve gates and that, therefore, the Union could, pursuant to Sailors Union of the Pacific [Moore Dry Dock], 92 N.L.R.B. 547 (1950), validly picket anywhere on the site. The Board agreed with the judge’s conclusion, but disagreed with his reasoning. Arguing that a telegram would be sufficient to establish a valid reserve gate situation if the gates themselves were legitimately maintained, the Board held that the delivery of materials for Luckie’s use through the Linbeck gate violated the integrity of the gates and, thereby, made permissible the picketing on Anderson Lane.

Regarding the July 25-August 2 picketing, the judge rejected Linbeck’s contention that its ownership of the materials that Luekie was to work on insulated delivery of those materials from the Union’s primary picketing of Luekie. Yet, while the Union could picket when deliveries of materials for Luckie’s use were being made or when Luekie and his supervisor visited the site during the day, the judge concluded that because the Union picketed at times during the day when deliveries and visits by Luekie were not being made, this additional picketing constituted unlawful secondary activity.

Free access — add to your briefcase to read the full text and ask questions with AI

Linbeck Construction Corporation v. National Labor Relations Board, 550 F.2d 311, 94 L.R.R.M. (BNA) 3230, 1977 U.S. App. LEXIS 13888 (5th Cir. 1977).

550 F.2d 311 (Linbeck Construction Corporation v. National Labor Relations Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Howard Gault Co. v. Texas Rural Legal Aid, Inc.
848 F.2d 544 (Fifth Circuit, 1988)
Constar, Inc. v. Plumbers Local 447
568 F. Supp. 1440 (E.D. California, 1983)
Abreen Corp. v. Laborers' International Union
709 F.2d 748 (First Circuit, 1983)
Anchortank, Inc. v. National Labor Relations Board
601 F.2d 233 (Fifth Circuit, 1979)