Lifestyle Energy Corp. v. John Wilson Drilling Co.

611 S.W.2d 709, 1980 Tex. App. LEXIS 4287
CourtCourt of Appeals of Texas
DecidedDecember 31, 1980
Docket7038
StatusPublished
Cited by6 cases

This text of 611 S.W.2d 709 (Lifestyle Energy Corp. v. John Wilson Drilling Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lifestyle Energy Corp. v. John Wilson Drilling Co., 611 S.W.2d 709, 1980 Tex. App. LEXIS 4287 (Tex. Ct. App. 1980).

Opinions

OPINION

OSBORN, Justice.

John Wilson Drilling Company recovered judgment against Lifestyle Energy Corporation for the balance due for services rendered under a daywork drilling contract. We reverse and remand because the burden of proof as to performance of the contract was misplaced in the Court’s chaise to the jury-

Under the terms of the written contract, John Wilson Drilling Company, as contractor, agreed to perform all work under the contract “with due diligence and care and in a good and workmanlike manner * * *.” While drilling a well and performing work under this contract, someone dropped a piece of metal off the air rotary head while the drilling crew was “nippleing up.” This necessitated a fishing job with the rental of the necessary equipment to locate and remove the piece of metal and extra time for the rig and crew. The operator, Lifestyle Energy Corporation, paid for all of the costs of drilling the well except the cost attributed to the fishing operations. That balance was the amount in issue in this case.

[710]*710The Court submitted one issue and instruction to the jury, which with the answer, was:

SPECIAL ISSUE ONE

What sum of money, if any, not paid to date, do you find from a preponderance of the evidence is owed to John Wilson Drilling Co. under the day work contract on the Hoover # 8 well?
Answer in dollars and cents, if any.
Answer: $5.264.63
In connection with the above issue you are instructed that if you find from a preponderance of the evidence that John Wilson Drilling Co. failed to perform any of the work in accordance with orders and directions of Lifestyle Energy Corp. and in a good and workmanlike manner, you may reduce the amount owed to John Wilson Drilling Co. by the amount of expenses, if any, incurred by Lifestyle Energy Corp. as a proximate result of such failure.

The Appellant objected to the Court’s charge because it improperly placed the burden of proof upon the Appellant to show that the work was not done in a good and workmanlike manner, and does not require the Appellee to prove by a preponderance of the evidence that it has performed within the terms of the contract involved in a good and workmanlike manner. The Appellant’s one point of error complains about the trial Court misplacing the burden of proof on this issue.

Under the instruction given with the issue submitted, the burden of proof was placed upon Lifestyle Energy Corporation to prove by á preponderance of the evidence that the drilling company failed to perform its work in a good and workmanlike manner. In Triton Oil and Gas Corporation v. E. W. Moran Drilling Company, 509 S.W.2d 678 (Tex.Civ.App.—Fort Worth 1974, writ ref’d n. r. e.), the Court considered a dispute under a drilling contract with a daywork clause and said:

To recover on the drilling contract, as stated above, plaintiff was required to prove that it substantially performed the contract in a good and workmanlike manner with due diligence and care.

In Bolin Oil Company v. Staples, 496 S.W.2d 167 (Tex.Civ.App.—Fort Worth 1973, writ ref’d n. r. e.), the jury found that conduct of a crew in dropping tubing into a well was a failure to perform in a good and workmanlike manner. Strangely enough, the issue in that case seems to place the burden of proof on the operator but apparently no complaint was raised about that part of the charge. Nevertheless, the Court in its opinion noted that the contract imposed on the plaintiff the legal duty or obligation of drilling and completing the well in question in a good and workmanlike manner. Also see: Westbrook v. Watts, 268 S.W.2d 694 (Tex.Civ.App.—Waco 1954, writ ref’d n. r. e.).

The Court in J. F. Pritchard & Co. v. R. A. Stokes Co., 160 F.2d 739 (5th Cir. 1947), noted that, where a contract required the work to be done in a workmanlike manner, “[t]he plaintiff had the burden of proving substantial compliance with that provision of the contract before it could recover for work done under the contract.” And as pointed out by Professor Hodges, it is normally reversible error to place the burden of persuasion upon the wrong party. Hodges, Special Issue Submission in Texas, sec. 28 (1959).

We sustain Appellant’s Point of Error. The judgment of the trial Court is reversed and the case is remanded for a new trial.

WARD, J., not sitting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Brenham v. Honerkamp
950 S.W.2d 760 (Court of Appeals of Texas, 1997)
Paramount National Life Insurance Co. v. Williams
772 S.W.2d 255 (Court of Appeals of Texas, 1989)
Hirsch v. Hirsch
770 S.W.2d 924 (Court of Appeals of Texas, 1989)
W.E. Myers Drilling Corp. v. Elliott
695 S.W.2d 809 (Court of Appeals of Texas, 1985)
Lifestyle Energy Corp. v. John Wilson Drilling Co.
611 S.W.2d 709 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
611 S.W.2d 709, 1980 Tex. App. LEXIS 4287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lifestyle-energy-corp-v-john-wilson-drilling-co-texapp-1980.