Lifeline Youth & Family Services v. Installed Building Products, Inc. d/b/a Momper Insulation

996 N.E.2d 808, 2013 WL 5260011, 2013 Ind. App. LEXIS 445
CourtIndiana Court of Appeals
DecidedSeptember 18, 2013
Docket02A03-1211-CT-502
StatusPublished
Cited by10 cases

This text of 996 N.E.2d 808 (Lifeline Youth & Family Services v. Installed Building Products, Inc. d/b/a Momper Insulation) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lifeline Youth & Family Services v. Installed Building Products, Inc. d/b/a Momper Insulation, 996 N.E.2d 808, 2013 WL 5260011, 2013 Ind. App. LEXIS 445 (Ind. Ct. App. 2013).

Opinion

OPINION

PYLE, Judge.

STATEMENT OF THE CASE

Lifeline Youth & Family Services (“Lifeline”) appeals the trial court’s denial of its motion to correct error following a jury verdict and award of damages entered in favor of Lifeline and against Installed Building Products, Inc. d/b/a Momper Insulation (“Momper”).

We affirm.

ISSUE
Whether the trial court erred by denying Lifeline’s motion to correct error that requested the trial court to increase the amount of the jury’s award of damages that was entered in favor of Lifeline.

FACTS 1

In January 2008, Momper installed insulation in the attic of a building owned by Lifeline. A fire occurred in the attic, causing damage to Lifeline’s building.

On June 19, 2009, Lifeline filed a three-count complaint for damages against Mom-per, raising claims of: (1) negligence; (2) breach of implied warranty; and (3) breach of contract. In regard to the negligence claim, Lifeline alleged that Momper had acted negligently when it dropped a portable light fixture onto the attic floor; installed insulation over the light fixture; and failed to inspect the attic after installation of the insulation. For the breach of implied warranty claim, Lifeline alleged that Momper had installed the insulation in an unsafe manner and that it was not fit for its intended purpose. Finally, Lifeline alleged that Momper had breached its contract with Lifeline by failing to perform the work as set forth in Momper’s invoice. 2 More specifically, Lifeline alleged that Momper had “improperly installed the R-19 (4 inches) blown wood fiber in the ceiling of the building.” (App. 58).

A jury trial was held August 21 through August 23, 2012. Lifeline proceeded on the three claims in its complaint, and the trial court instructed the jury as to the *810 elements necessary before damages could be awarded for those claims. The parties stipulated to the amount of damages sustained, which was set forth in one of the final jury instructions:

The parties in this case have agreed that certain facts are true. You must accept these facts as true:
Although [Momper] denies that it is liable to [Lifeline] for any damages sustained by [Lifeline] as a result of the fire that is the subject of this litigation, the parties hereby stipulate and agree to the following:
1. The cost to repair is the proper measure of the damages sustained to [Lifeline’s] building as a result of the subject fire;
2. The cost to repair the damages sustained to [Lifeline’s] building as a result of the fire included $280,263.00, exclusive of any interest;
3. The repairs to [Lifeline’s] building were preformed [sic] as described in the invoices produced by [Lifeline] to [Momper];
4. The repairs performed on [Lifeline’s] building were reasonable and necessary to return the building to its pre-fire condition; and
5. Lifeline paid $280,263.00 to contractors and vendors to perform these repairs.

(App. 37).

The trial court instructed the jury regarding the apportionment of fault for comparative fault and instructed the jury that consideration of Lifeline’s fault was an issue as to Lifeline’s negligence claim. The trial court also instructed the jury— in two separate instructions — that it “must not consider comparative fault when considering whether to award damages for [Lifeline] for its breach of contract claim.” (App. 47). 3 Instead, the trial court provided specific instructions regarding damages for the breach of contract claim. The trial court instructed the jury that “[t]o recover damages ... for breach of contract,” Lifeline was required to prove that: (1) the parties entered into a contract; (2) Momper had breached its contract with Lifeline; (3) Momper’s breach damaged Lifeline; (4) the parties “reasonably anticipated that those damages could/might occur when they entered into the contract;” and (5) Momper’s breach was a “responsible cause of those damages.” (App. 44). The trial court also informed the jury that “[i]n a claim for breach of contract, a party may recover only those damages that are the natural and proximate consequence of the breach, and those reasonably anticipated by the parties when they entered into the contract.” (App. 50). Additionally, the trial court provided the jury with a verdict form that provided a space for the jury to assess fault to each party. The verdict form also contained a space for the jury to indicate, by placing a check mark, whether or not Momper had breached its contract with Lifeline. 4

The jury returned a verdict in favor of Lifeline and against Momper and awarded damages in the amount of $154,144.65. *811 Specifically, the jury determined that Lifeline was forty-five percent at fault and that Momper was fifty-five percent at fault. The jury also determined, as indicated by its check mark on the verdict form, that Momper breached its contract with Lifeline. The two-page jury verdict form, which is at issue in this appeal, appears as follows:

811

[[Image here]]

*812 [[Image here]]

(App. 22-23). The trial court entered judgment on the jury’s verdict.

Lifeline then filed a motion to correct error, claiming that the jury had erred in its calculation of damages. Lifeline did not include a copy of its motion to correct error in its Appellant’s Appendix but asserts in its appellate brief that it filed its motion under Trial Rule 52(A)(2), which is a claim that a jury verdict is “inadequate.” During the hearing on Lifeline’s motion, Lifeline argued that the jury erroneously applied comparative fault to its calculation of damages on its breach of contract claim. Lifeline argued that it did not want to disturb the jury’s general verdict in its favor but stated that it sought to have the trial court “correct an error that the jury made in which damages [it was] awarding for the breach of contract claim.” (Tr. 6). Lifeline requested the trial court to award Lifeline damages in the amount of $280,268.00, which it argued would be consistent with the jury’s finding that Mom-per had breached the contract. Momper argued that the jury’s finding that Mom-per breached the contract did not equate to a determination that the jury intended to award damages on the breach of contract claim. Momper argued that the jury’s damages verdict was consistent with the jury’s verdict regarding negligence and its determination of comparative fault, which Lifeline did not challenge. The trial court denied Lifeline’s motion to correct error. Lifeline now appeals.

DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
996 N.E.2d 808, 2013 WL 5260011, 2013 Ind. App. LEXIS 445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lifeline-youth-family-services-v-installed-building-products-inc-dba-indctapp-2013.