Liberty Roofing Company v. The Haskell Company

CourtDistrict Court, D. Massachusetts
DecidedMarch 14, 2022
Docket1:20-cv-10419
StatusUnknown

This text of Liberty Roofing Company v. The Haskell Company (Liberty Roofing Company v. The Haskell Company) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liberty Roofing Company v. The Haskell Company, (D. Mass. 2022).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

UNITED STATES OF AMERICA, f/b/o * LIBERTY ROOFING COMPANY * * Plaintiff, * * v. * * THE HASKELL COMPANY, * Civil Action No. 20-cv-10419-ADB TRAVELERS CASUALTY AND SURETY * COMPANY OF AMERICA, and * FIDELTY AND DEPOSIT COMPANY OF * MARYLAND/ZURICH AMERICAN * INSURANCE COMPANY, * * Defendants. *

MEMORANDUM AND ORDER

BURROUGHS, D.J. This dispute arises out of an agreement between Plaintiff Liberty Roofing Company (“Liberty”) and Defendant The Haskell Company (“Haskell”) concerning a construction project on a United States Coast Guard (“Coast Guard”) base at Woods Hole, Massachusetts. [ECF No. 1]. On February 18, 2021, an Arbitrator issued an interim award (the “Interim Award”) resolving several claims in favor of Haskell and awarding it $248,837.59. [ECF No. 15-4 at 13–14]. The Arbitrator then issued a final award (the “Award”) on April 15, 2021, which incorporated all of the findings and conclusions set forth in the Interim Award and also granted Haskell attorneys’ fees and costs, for a total award of $512,344.59. [ECF No. 15-5]. Liberty now moves the Court to vacate the Award. [ECF No. 15]. Haskell, along with Defendants Travelers Casualty and Surety Company of America and Fidelity and Deposit Company of Maryland/Zurich American Insurance Company (collectively, “Defendants”), responded with a cross-motion asking the Court to confirm the Award, enter final judgment, and dismiss the case. [ECF No. 16]. For the reasons set forth below, Liberty’s motion to vacate the Award, [ECF No. 15], is DENIED, Defendants’ motion to confirm the Award and enter final judgment, [ECF No. 16], is GRANTED, and Defendants’ request for additional attorneys’ fees and costs incurred in responding to Liberty’s motion, [ECF No. 19], is DENIED.

I. BACKGROUND A. Factual Background The following facts are taken from the parties’ submissions and the documents cited therein. 1. The Subcontract Agreement and Woods Hole Project

Pursuant to a contract with the Coast Guard, Haskell was tasked with constructing three buildings (the ANT Building, Station Building, and Guardhouse) at a military base in Woods Hole, Massachusetts. [ECF No. 15-5 at 9]. On or around February 26, 2018, Haskell engaged Liberty as a subcontractor to, among other things, perform sheet metal roofing work for the Woods Hole project (the “Subcontract Agreement”). [Id.; ECF No. 15-2 at 3]. Under the Subcontract Agreement, Liberty agreed to provide sufficient resources to accomplish the Scope of Work within the time frame set forth in the Progress Schedule. The most current version of this schedule shall be considered the updated Progress Schedule. It will be the only basis for the performance of the Work and for the establishment of intermediate milestone dates and completion dates.

Near term schedules will be created by Haskell and will be issued at the weekly subcontractor’s meeting. [Liberty’s] attendance at this meeting is mandatory. Persons attending the progress meeting must be able to address all manpower and material issues regarding this project, including the authority to direct overtime as required to meet these schedule requirements. Unless written notice of any objection to the schedule and its subsequent updates is provided within five (5) business days of receipt of said updates, the schedule and its updates will be considered acceptable to [Liberty][.] [ECF No. 15-2 at 10]. As part of the roof installation, Liberty was required to install an “underlayment,” which is a product that is adhered over the roofing insulation to protect it from water damage. [Id. at 3; ECF No. 15-1 at 2]. The metal seam roof would then be installed over the insulation and underlayment. [ECF No. 15-2 at 3; ECF No. 15-1 at 2].

By the fall of 2018, Liberty had installed the underlayment on all three buildings and begun installing the sheet metal roof on the ANT Building. [ECF No. 15-1 at 2–3]. Eventually, the Coast Guard issued a stop work order because a portion of the sheet metal roof that Liberty had installed did not meet the wind uplift requirements that were structurally necessary. [ECF No. 15-5 at 10]. Haskell directed Liberty to stop work on the project until the roof could be re- engineered. [ECF No. 15-1 at 3; ECF No. 19 at 2]. On December 3, 2018, Liberty and Haskell entered into a Subcontract Modification (“Mod. D”), whereby Haskell agreed to pay Liberty an additional amount to remove, redesign, and reinstall the sheet metal roof on the Ant Building with one that met the relevant requirements. [ECF No. 15-3 at 2; ECF No. 15-5 at 11]. 1 Mod. D also states that “[a]ll terms and conditions of the previous Subcontract Agreement not modified

herein shall remain in full force and effect.” [ECF No. 15-3 at 2]. While the new roof was being engineered, Liberty represents that the underlayment that Liberty had installed on all three buildings continued to be exposed to the elements. [ECF No. 15-1 at 3–4]. Liberty continued with reinstallation of the roof until Haskell terminated their relationship in March 2019 after Liberty had failed to meet project deadlines. [ECF No. 15-5 at 12]. Prior to the termination, in January 2019, Haskell had issued Liberty a Notice to Cure, “indicating that [Liberty] was not using sufficient manpower to stay current with the Project

1 The parties continue to dispute who is responsible for the faulty roof design. The Arbitrator considered the issue resolved with the adoption of Mod. D. [ECF No. 15-5 at 11–12]. schedule.” [Id. at 13]. Liberty claims that the delay caused by the roof redesign required it to operate under winter conditions that were unanticipated in the original project schedule, causing even further delays. [Id. at 13 n.3]. 2. The Arbitration

Although Liberty initially filed suit in this Court, [ECF No. 1], the parties proceeded to arbitration in December 2020 pursuant to an arbitration clause in the Subcontractor Agreement, [ECF No. 15-5 at 2; ECF No. 4]. In the arbitration, Liberty argued that it was wrongfully terminated and sought payment for labor and materials in connection with its work on the Woods Hole project. [ECF No. 15-5 at 9; ECF No. 15-1 at 4; ECF No. 19 at 3]. Haskell asserted counterclaims stemming from Liberty’s allegedly defective performance and seeking the costs associated with that defective performance. [ECF No. 15-5 at 9; ECF No. 15-1 at 4; ECF No. 19 at 3]. The parties jointly selected the Arbitrator, participated in five days of hearings where they presented testimony and exhibits, and submitted post-hearing briefing. [ECF No. 15-5 at 8]. The Arbitrator issued his Interim Award, finding that Liberty had breached its contract with

Haskell and awarding Liberty $0.00 and Haskell $248,837.59. [Id. at 19]. In relevant part, the Arbitrator made three findings in his Interim Award in support of his conclusion that Liberty had breached its obligations and that an award should be issued in favor of Haskell. First, that Liberty “failed to advance the work after December 3, 2018 in a timely manner[,]” “provided inadequate manpower to the Project[,] and failed to meet scheduled durations.” [ECF No. 15-5 at 13]. In support of this finding, the Arbitrator dismissed Liberty’s argument that winter weather caused the delay and concluded that Liberty “knew that the work would be performed in winter conditions” when Mod. D was signed and “agreed to the price and schedule and had the obligation to provide the manpower to perform the work as agreed.” [Id. at 13 n.3]. Second, that, pursuant to Mod. D, Liberty had agreed to “reinstall the ANT metal roof, in accordance with manufacturer’s requirements” which included that “the underlayment be installed and in required condition.” [Id. at 13, 15]. Third, Liberty was responsible for maintaining the underlayment during the work stoppage and the post-December 3, 2018

reinstallation process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Teamsters Local Union No. 42 v. Supervalu, Inc.
212 F.3d 59 (First Circuit, 2000)
Cytyc Corporation v. Deka Products
439 F.3d 27 (First Circuit, 2006)
Advest, Inc. v. Patrick McCarthy
914 F.2d 6 (First Circuit, 1990)
Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Hoolahan v. IBC Advanced Alloys Corp.
947 F.3d 101 (First Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Liberty Roofing Company v. The Haskell Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liberty-roofing-company-v-the-haskell-company-mad-2022.