Lexington Insurance v. Hovensa, LLC

52 V.I. 959, 2009 WL 2950366, 2009 U.S. Dist. LEXIS 81538
CourtDistrict Court, Virgin Islands
DecidedSeptember 8, 2009
DocketCivil No. 2005-112 consolidated with Civil No. 2005-114
StatusPublished

This text of 52 V.I. 959 (Lexington Insurance v. Hovensa, LLC) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lexington Insurance v. Hovensa, LLC, 52 V.I. 959, 2009 WL 2950366, 2009 U.S. Dist. LEXIS 81538 (vid 2009).

Opinion

GÓMEZ, Chief Judge

MEMORANDUM OPINION

(September 8, 2009)

Before the Court are the respective motions of Lexington Insurance Company (“Lexington”) and HOVENSA, LLC (“HOVENSA”) for summary judgment on HOVENSA’s breach of contract claim.

I. FACTUAL AND PROCEDURAL BACKGROUND

Lexington is an insurer incorporated in Delaware with its principal place of business in Massachusetts.

HOVENSA is a Virgin Islands limited liability company that owns and operates a refinery on St. Croix, U.S. Virgin Islands. Jacobs Industrial Maintenance Company, LLC (“Jacobs Maintenance”) is a Virgin Islands limited liability company. Jacobs Maintenance is owned by Jacobs Engineering Group, Inc. (“Jacobs Engineering”), which is incorporated in Delaware and has its principal place of business in California (Jacobs [961]*961Maintenance and Jacobs Engineering are collectively referred to as “Jacobs”).

Jacobs Maintenance contracted to perform maintenance work at HOVENSA’s refinery from September 1999 until September 2002. Pursuant to that arrangement, Jacobs Maintenance purchased employment liability coverage from Lexington for itself, certain affiliates, and HOVENSA for claims arising out of the maintenance contract. One of the policies provided coverage from September 30, 2000 through September 30, 2001. Another provided coverage from September 30, 2001 through September 30, 2002 (together, the “Lexington Policies” or the “Policies”).1 The Lexington Policies have a combined total coverage limit of $6 million.

Between 2000 and 2002, several Jacobs Maintenance employees sued Jacobs Maintenance, alleging workplace discrimination. HOVENSA was named as a defendant in most of those lawsuits. Lexington agreed to defend and to indemnify Jacobs and HOVENSA for claims in many of those suits. By June 2005, Lexington had spent $2,414,396.33 in connection with defending and settling some of those suits. As a result, $3,585,603.67 remained under the Lexington Policies. At that time, there were 17 remaining employee suits pending against HOVENSA and Jacobs, most of which named both parties as defendants.

In the Spring of 2005, settlement efforts were undertaken to resolve 13 of the underlying lawsuits. Four actions were excluded from settlement talks. Two of those named both Jacobs and Hovensa as defendants, and two named Jacobs only. Lexington informed HOVENSA and Jacobs that it would not settle any claims unless both HOVENSA and Jacobs consented to any such settlement. HOVENSA claims that it reached a proposed settlement (the “proposed settlement”) of the 13 suits. Jacobs did not consent to the proposed settlement. In June 2005, HOVENSA demanded that Lexington tender the remaining policy limit to pay for the proposed settlement. Lexington declined, stating that it could not exhaust the policy limits for a settlement, which Jacobs did not approve. On June 28, 2005, settlement negotiations ended.

On August 5, 2005, Lexington filed a statutory interpleader action, pursuant to 28 U.S.C. § 1335 (the “interpleader action”). Lexington [962]*962alleged that additional defense and liability costs incurred in connection with the underlying lawsuits would likely exceed the Policies’ coverage limits. Named as defendants were Jacobs Maintenance, Jacobs Engineering, HOVENSA, those three entities’ attorneys, as well as the parties in the underlying lawsuits and their attorneys. Lexington filed a bond in the amount of $3,585,603.67, which represented the remaining limit under the Lexington Policies. It sought a discharge from liability in connection with the underlying lawsuits and a determination of the parties’ rights with respect to the Policies’ remaining coverage limit.

Hovensa filed counterclaims in the interpleader action. HOVENSA sought a declaration that Lexington was obligated to tender the remaining limits under the Lexington Policies to cover a settlement with the underlying plaintiffs. HOVENSA also alleged that Lexington breached its contractual obligations by refusing to tender the remaining limits. Jacobs also filed counterclaims in the interpleader action. Jacobs sought damages for breach of contract and breach of the implied covenant of good faith and fair dealing. Lexington and Jacobs reached a settlement of Jacobs’ claims, which were dismissed.

On August 8, 2005, three days after Lexington filed its interpleader action, HOVENSA commenced an action against Lexington (the “breach of contract action”). In that action, HOVENSA made the exact same claims as its counterclaims in the interpleader action.

By order dated March 28,2007, the Court consolidated the interpleader and breach of contract actions.

In April, 2007, HOVENSA, Jacobs and the underlying plaintiffs agreed to settle most of the underlying lawsuits for $10.6 million. Pursuant to that settlement, HOVENSA and Jacobs agreed to share equally any settlement costs in excess of Lexington’s interpleader bond. The parties subsequently stipulated to the discharge of the bond. After the Court discharged the bond, Lexington allocated $3,585,603.67 toward the settlement.

Lexington and HOVENSA now both seek summary judgment on HOVENSA’ a breach of contract claim against Lexington. The Court has since heard the parties’ arguments on the motion.

II. DISCUSSION

Summary judgment is appropriate if “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no [963]*963genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” FED. R. Crv. P. 56(c); see also Hersh v. Allen Products Co., 789 F.2d 230, 232 (3d Cir. 1986).

The movant has the initial burden of showing there is no genuine issue of material fact, but once this burden is met it shifts to the non-moving party to establish specific facts showing there is a genuine issue for trial. Gans v. Mundy, 762 F.2d 338, 342 (3d Cir. 1985). The non-moving party “may not rest upon mere allegations, general denials, or . . . vague statements . . . .” Quiroga v. Hasbro, Inc., 934 F.2d 497, 500 (3d Cir. 1991). “[T]here is no issue for trial unless there is sufficient evidence favoring the non-moving party for a jury to return a verdict for that party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S. Ct. 2505, 91 L. Ed. 2d 202 (1986).

“[A]t the summary judgment stage the judge’s function is not himself to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial.” Id. In making this determination, this Court draws all reasonable inferences in favor of the non-moving party. See Bd. of Educ. v. Earls, 536 U.S. 822, 850, 122 S. Ct. 2559, 153 L. Ed. 2d 735 (2002); see also Armbruster v. Unisys Corp.,

Related

Cite This Page — Counsel Stack

Bluebook (online)
52 V.I. 959, 2009 WL 2950366, 2009 U.S. Dist. LEXIS 81538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lexington-insurance-v-hovensa-llc-vid-2009.