Lewis v. Jones

251 S.W.2d 942, 1952 Tex. App. LEXIS 1735
CourtCourt of Appeals of Texas
DecidedJuly 17, 1952
Docket12435
StatusPublished
Cited by2 cases

This text of 251 S.W.2d 942 (Lewis v. Jones) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis v. Jones, 251 S.W.2d 942, 1952 Tex. App. LEXIS 1735 (Tex. Ct. App. 1952).

Opinions

CODY, Justice.

This was a suit by appellee, a general contractor, to recover from appellant the balance of the unpaid contract price for the construction of a building in the City of Houston, which appellee alleged he had performed according to the terms of their written contract. And, as ancillary to his suit, appellee sought to impress a statutory lien upon the building and premises, to foreclose it, and to recover attorney’s fees. Appellant answered with a general denial, and a cross-action alleging that appellee had not substantially performed the contract, and sought damages. The court, trying the case without a jury, rendered judgment awarding appellee judgment for the sum sued for, being in excess of $9,-000, and attorney’s fees in the sum of $20. No conclusions of fact and law were requested, and none were filed. Appellant has appealed from the judgment, except as to the amount of attorney’s fees. Appellee 'has appealed from the amount awarded as attorney’s fees.

The contract was executed on November 25, 1947, on a form bearing the name of appellant’s architects, which bore the warning that the “material” used therein could [943]*943only be used with the permission of the American Institute of Architects. The contract provided that work thereunder should begin not later than November 28, 1947, and should be completed within 125 working days, with $25 per day liquidated damages. The contract price was $40,837. It was not disputed that the work was not completed until November 18, 1948, or a total of 356 calendar days. The contest largely concerned what the parties meant by “working days”.

The parts of the contract material on this appeal are the following (The portion of the contract which is printed in the form is italicized; the remainder was typewritten) :

“Article 2. Time of Completion— The work to he performed wider this Contract shall he commenced not later than November 28, 1947, and shall be substantially completed in one hundred twenty-five (125) working days.
(Here insert stipulation as to liquidated damages, if any,) and from the compensation otherwise to be paid, the Owner may retain the sum of $25.00 for each day thereafter, (Sundays, whole holidays not included) that the work of the General Contractor remains incomplete and unacceptable to the Architects, which sum is agreed upon as the proper measure of liquidated damages which the Owner will sustain per diem by failure of the General Contractor to complete the work by the time stipulated, and this sum shall not be construed in any sense a penalty.”

(The trial court apparently adopted the view that the forepart of Article 2 specified the time of completion, and that the remainder, which we have indicated by the break was concerned with the stipulation as to stipulated damages.)

“Article 5. Acceptance and Final Payment — Final payment shall be due 30 days after substantial completion of the work provided the work be then fully completed and the Contract fully performed.
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the Architect shall promptly make such inspection, and when he finds the work acceptable under the Contract and the Contract fully performed he shall promptly isstte a final certificate, over his own signature, stating that the work provided for in this Contract has been, completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the Contractor, and noted in said final certificate, is due and payable.
“Before issuance of final certificate the Contractor shall submit evidence satisfactory to the Architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.
“If after the work has been substantially completed, full completion thereof is materially delayed through no fault of the Contractor, and the Architect so certifies, the Owner shall, upon certificate of the Architect, and without terminating the Contract, make payment of the balance due for that portion of the work fully completed and accepted. Such payment shall be made under the terms and conditions governing final payment, except that it. shall not constitute a % waiver of claims.”

By letter dated January 4, 1949, addressed to appellee, the Architects notified appellee that there was being transmitted under separate cover voucher for $8,401.46 “for final payment on the above building:

“This is to advise that we find that the work completed as per your contract * * and the plans and specifications.”

The 'balance of the principal sued for was the amount of the voucher, $8,401.16, which was not in fact paid.

Appellant’s points 1 and 2 complain that the court committed reversible error in admitting evidence of custom as to the meaning of the term “working days” (1) since the contract itself defined working days, and (2) since there was no pleading of custom. His points 3 and 4 complain of the judgment as being based upon evidence of custom as to the meaning of “working days” (3) since appellee failed to sustain the bur[944]*944den of proving appellant had knowledge of said custom, and (4) since appellee failed to prove any such custom existed at the time the contract was executed. And in his 5th point, appellant complains of the judgment for not allowing appellant deductions of $25 per day for each day, after 125 working days, he alleged appellee failed to complete the building.

By Article 2 of the contract, quoted above, the parties stipulated that appellee should be allowed 125 “working days” in which to construct the building in accordance with the plans and specifications. By said Article the parties additionally stipulated that in case appellee failed to substantially complete the building within the 125 “working days” that the appellant should be allowed to deduct from the contract price as liquidated damages the sum of $25 per day for each day in excess of the 125 “working days” that it took the contractor to so complete the building, excepting from such excessive days it might take the contractor to complete the 'building any right in appellant to liquidated damages for any Sundays or holidays so in excess of the 125 “working days”. The reason for such exception was that the building was 'being constructed for commercial use and would not be occupied on Sundays or holidays and so appellant would not be entitled to, and should not be allowed, liquidated damages for the said days so- excepted.

We overrule appellant’s first point. There was nothing uncertain or ambiguous about what the parties meant by excepting Sundays and holidays from being taken into account in determining liquidated damages. The interpretation, therefore, of the provision so excepting Sundays and holidays was a question of law for the court, and we must assume that the court determined the intention of the parties as SO' expressed by them in excluding Sundays and holidays as a matter of law; and as a matter of law ruled that the parties did not intend by the parenthetical “(Sundays, whole holidays, not included)” to define “working days”. In other words, the admission by the court of evidence of custom as to the meaning of the term “working days” had no bearing whatsoever as to the meaning of the term “working days” as used in Article 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCollum v. Nowell
275 S.W.2d 866 (Court of Appeals of Texas, 1955)
Lewis v. Jones
251 S.W.2d 942 (Court of Appeals of Texas, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
251 S.W.2d 942, 1952 Tex. App. LEXIS 1735, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-v-jones-texapp-1952.