Levitsky v. McPherson (In re McPherson)

564 B.R. 6
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedJanuary 17, 2017
DocketCase No. 14-10932-FJB; Adversary Proceeding No. 14-1218
StatusPublished
Cited by2 cases

This text of 564 B.R. 6 (Levitsky v. McPherson (In re McPherson)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levitsky v. McPherson (In re McPherson), 564 B.R. 6 (Mass. 2017).

Opinion

MEMORANDUM OF DECISION

Frank J. Bailey, United States Bankruptcy Judge

Plaintiffs Andrew and Hyeson Levitsky (collectively “the Levitskys”) live in Need-ham, Massachusetts. In 2010, they decided to put an addition on their home. While the renovation began as a modest one, eventually it became an extensive project, including a family room and garage with a master suite and additional room over the garage. They entered a construction agreement (the “Construction Agreement”) with the debtor, Brian McPherson (the “Debtor”), as a contractor. The construction project went badly, and the Debtor was terminated before the construction was complete. An arbitration proceeding ensued that resulted in a state court judgment’ against the Debtor in the amount of $149,515.54. The Debtor then filed a petition for relief under chapter 13 of the Bankruptcy Code. In the bankruptcy case thereby commenced, he has obtained confirmation of a chapter 13 plan and then two amended plans. He has been paying the amounts required by these plans. Provided he continues to do so, his current plan will result in payment of approximately 6.75 percent of the Levitskys’ judgment over five years. Upon completion of the plan and proper application to the Court, the Debtor may then obtain a discharge under 11 U.S.C. § 1328(a).

The Levitskys have now filed an adversary proceeding against the Debtor, seeking a determination that the unpaid balance of their state court judgment against him is excepted from discharge under 11 U.S.C. § 523(a)(2)(A), (a)(4), and (a)(6). After a trial that included the testimony of Andrew Levitsky and the Debtor—Mrs. Levitsky was- in the courtroom but did not testify—and the admission of well over one hundred exhibits, I find that the Levitskys have failed to carry their burden of establishing nondischargeability under the relevant sections of the Bankruptcy Code. Thé following constitute my findings of fact and conclusions of law in the matter. '

[10]*10The Facts

Before the Debtor filed his bankruptcy petition, the parties engaged in a full arbitration proceeding, as was mandatory under their Construction Agreement. The arbitrator eventually issued an arbitration award that determined the Levitskys to be the prevailing party, which award was confirmed by a state court of competent jurisdiction. In the award, the arbitrator made certain factual findings, and the parties have stipulated that the findings are binding in this proceeding. The arbitration award was admitted at trial. Because the parties agreed that those findings are essentially stipulations, I summarize them here:

1. The parties entered a construction contract dated May 29, 2010 for the renovation of the Levitsky home in Needham, Massachusetts. The agreed contract price was $807,100, including architectural design. On August 16, 2010 the parties agreed to a change order whereby additional work was added for a cost of $62,000 (the “First Change Order”), for a total contract price of $369,100. The parties also agreed to additional construction work after August 16, 2010.
2. The Construction Agreement stated that the “project completion date shall be approximately 147 days from the first date of construction, however, any change order and/or unusual weather might delay or otherwise affect the completion date.”
3. Construction started on November 1, 2010, and was still not substantially completed on March 29, 2012, when the Levitskys terminated the Debtor. The Debtor never requested any extensions of time to complete the project, and none were given. The Levitskys were justified in terminating the Debtor on March 29, 2012 because the Debtor should have completed the project, including all change orders and additions, “several months before the termination date.” The Debtor failed to perform his work on time and in accordance with the Construction Agreement.
4. The Levitskys obtained a construction loan from a bank. Payments were to be advanced when certain progress milestones were made on the project, and payments were to be advanced from the bank to Debt- or after inspection and approval by the bank’s agent. The Construction Agreement included an addendum dated May 21, 2010 that added a provision as follows: “since the bank will be making the progress payments to [the Debtor], there should not be any penalty to [the Levitskys] for slow payments.” Based on this provision, the arbitrator found that Debtor could not complain of slow payments from the bank as an excuse for delay.
5. The Levitskys wrote checks totaling $48,000 to the Debtor as advances on the work under the Construction Agreement because he “demanded that they do so.” When the bank paid the Debtor for the work covered by the advances, he was to repay the Levitskys so as not to be paid twice. The Debtor provided repayment checks to the Levitskys, but two of those checks were dishonored, and others were held by the Levitskys for fear they would be dishonored. This left a balance due to the Levitskys of $43,000 for unmade reimbursements.
6. The Levitskys received an arbitration award for breach of the Con[11]*11struction Agreement—including sums for some 18 items collectively labeled “cost to complete and repair work and consequential,” plus four items for “credits admitted by [the Debtor]”—and the Debtor received an offset award for unjust enrichment for work he did to improve the house but for which he was not paid. The net award for breach of contract to the Levitskys was $78,957.48, plus 12% interest until paid. The Levitskys also received an award for $200 in statutory damages for two dishonored checks. And the Levitskys received an award of “reasonable attorney fees” and costs as the prevailing party under the arbitration clause in the Construction Agreement. The total of such fees and costs was $55,234.54.

The parties agree that the arbitrator did not make a finding of any alleged fraud or statutory business torts, other than the statutory tort for dishonoring two checks.

The arbitrator’s findings did not specifi- v cally address certain other aspects of the deal between the parties. In addition to the change order stated in the addendum, the Levitskys also requested additional work totaling $79,000 (the “Additional Work”). Those additions were detailed on a sheet prepared by the Levitskys entitled “Approved Change Orders.” According to the sheet, of the $79,000 in additional work, all but $27,500 was completed.

The Construction Agreement anticipated the need for changes and additions to the scope of the work. In fact, the First Change Order and the Additional Work were added to the scope of the project. Article 9.1 of the Construction Agreement provided in part as follows:

A Change Order is any change to the original plans and/or specifications. All change orders need to be agreed upon in writing, ... 50% of the cost of each change order will be paid prior to the change, with the final 50% paid upon completion of the change order ... [additional time needed to complete change orders shall be taken into consideration in the project completion date.

Despite the First Change Order and “Additional Work,” there was no evidence that the process set forth at Article 9.1 was followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rable v. Childers
N.D. Ohio, 2023
Weiss v. Fautz
D. Massachusetts, 2022

Cite This Page — Counsel Stack

Bluebook (online)
564 B.R. 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levitsky-v-mcpherson-in-re-mcpherson-mab-2017.