LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedAugust 8, 2018
DocketA-0081-17T3
StatusUnpublished

This text of LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE) (LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE), (N.J. Ct. App. 2018).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-0081-17T3

LESSNER ELECTRIC COMPANY,

Plaintiff-Appellant,

v.

FIDELITY AND DEPOSIT COMPANY OF MARYLAND, ZURICH AMERICAN INSURANCE CO., and APS CONTRACTING, INC.,

Defendants-Respondents.

_____________________________________

Argued July 31, 2018 – Decided August 8, 2018

Before Judges Sabatino and Mawla.

On appeal from Superior Court of New Jersey, Law Division, Union County, Docket No. L-1353- 17.

Glenn C. Slavin argued the cause for appellant (Slavin & Morse, LLC, attorneys; Glenn C. Slavin, on the brief).

Eric J. Levine argued the cause for respondents Fidelity and Deposit Company of Maryland and Zurich American Insurance Company (Baron Samson, LLP, attorneys; Eric J. Levine, on the brief). Daniel Connolly Carmalt argued the cause for respondent APS Contracting, Inc. (Carmalt Law, LLC, attorneys; Daniel Connolly Carmalt, on the brief).

PER CURIAM

Plaintiff Lessner Electric Company (Lessner) appeals from

August 22, 2017 and September 20, 2017 orders dismissing its

complaint alleging breach of contract, delay damages, and unjust

enrichment on grounds of a failure to state a claim. We affirm.

In July 2013, Lessner entered into a subcontract with

defendant APS Contracting, Inc. (APS) to perform electrical work

on the construction of the Union County Family Courthouse. In

pertinent part, the contract between Lessner and APS stipulated

as follows:

To the fullest extent permitted by law, [Lessner] waives its right to any claim for damage for delay from [APS] . . . . [Lessner] expressly confirms its understanding that this is a complex project with multiple prime contractors and/or numerous other subcontractors, which conditions may result in, by way of example only and not by the way of limitation, coordination and interference issues, out of sequence work, recurring schedule revisions, compression and/or acceleration of the [w]ork, stoppage of the [w]ork, and/or other unspecified delays to the [p]roject and for which [Lessner] may not be compensated. [Lessner] expressly undertakes and assumes the risks of the above and disclaims any liability for same on the part of [APS].

[(Emphasis added).]

2 A-0081-17T3 Defendants Fidelity and Deposit Company of Maryland, and its

parent company Zurich American Insurance Co. (collectively, the

surety) insured the performance of APS through a warranty bond.

In April 2015, APS was removed from the project, and the surety

assumed APS's role for the remainder of the project.

In August 2015, the surety entered into an Assignment and

Ratification Agreement (ratification agreement) with Lessner to

reaffirm its subcontract, bring Lessner current for certain

payments and costs Lessner believed were due from APS, and have

Lessner complete the remainder of its work.

The ratification agreement expressly stipulated in paragraph

2: "Except as otherwise modified by this Agreement, the terms of

the Subcontract remain in full force and effect." The ratification

agreement further stated Lessner "hereby: (i) ratifies and affirms

its obligations under the Subcontract . . . [and] (iv) agrees

. . . [it] shall complete the Subcontract and the Subcontract Work

. . . for [the] Surety, as a subcontractor for [the] Surety, in

accordance with the terms of the Subcontract and Contract [with

APS] . . . ." The ratification agreement also set forth the amount

Lessner claimed it required from the surety in order to return and

complete its work. This figure was comprised of the original

amount agreed upon between Lessner and APS with an addition for a

change order, less sums already paid to Lessner.

3 A-0081-17T3 The surety and Lessner agreed on no other conditions on

Lessner's return to the project, other than to contract for the

payment of the sums due under the original contract. However, the

ratification agreement did identify damages Lessner claimed it had

suffered as a result of the delay of the project. Specifically,

paragraph 4 of the ratification agreement released APS and the

surety,

from any and all claims, of any type or kind, known or unknown, asserted or unasserted, which in any way arise from, relate to, or concert the Subcontract, the Contract, the Project, the Bond, and/or the [Lessner's] performance under the Subcontract, which claims have accrued or arise out of or relate to events occurring prior to the date of this Agreement, excluding only: . . . (ii) such claims as may be identified . . . in Rider A, which is attached hereto and made a part hereof.

Rider A was entitled "PENDING REQUESTS FOR CHANGE ORDERS AND

RESERVED CLAIMS," and allegedly included Lessner's non-waiver of

a claim for delay damages although the rider did not describe them

specifically as such.1

In September 2016, Lessner asserted a claim against the surety

seeking "additional compensation due to the delay damages"

1 The bottom of Rider A obliquely references a May 20, 2015 "Scheduling Concerns/Delays" letter. However, the letter was not supplied to the motion judge, and is not part of the record before us.

4 A-0081-17T3 totaling $1.82 million allegedly resulting in a twenty-four month

delay caused by APS's replacement on the project. The surety

noted Lessner's sole remedy for delay under the contract was to

seek an extension of time to complete its work. The surety also

noted there had been "no meeting of the minds" under the

ratification agreement to compensate Lessner for delay damages.

Lessner filed a complaint in the Law Division for breach of

contract against defendants seeking payment of the delay damages.

The complaint asserted three counts against the surety, alleging

a breach of the bonding agreement, the contract with APS, and

unjust enrichment. The surety and APS filed motions to dismiss

for failure to state a claim. Defendants argued their motions

should be granted because of the express waiver of delay damages

clause under the contract with APS, and that delay damages were

not recoverable under the express terms of the bond and the Bond

Act, N.J.S.A. 2A:44-143 to -147.

The motion judge granted the surety's motion to dismiss. The

judge found Lessner knew of its delay damages claim, yet entered

into the ratification agreement, which did not provide for payment

of the alleged damages. The judge also concluded the express

waiver of delay damages under the contract with APS was binding,

and therefore likewise dismissed the claims against APS. This

appeal followed.

5 A-0081-17T3 We begin by reciting our standard of review. Appellate review

of a trial court's ruling on a motion to dismiss is de novo.

Frederick v. Smith, 416 N.J. Super. 594, 597 (App. Div. 2010)

(citing Seidenberg v. Summit Bank, 348 N.J. Super. 243, 250 (App.

Div. 2002)). "A complaint should be dismissed for failure to

state a claim pursuant to Rule 4:6-2(e) only if 'the factual

allegations are palpably insufficient to support a claim upon

which relief can be granted.'" Ibid. (quoting Rieder v. State

Dep't of Transp., 221 N.J. Super.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borough of West Caldwell v. Borough of Caldwell
138 A.2d 402 (Supreme Court of New Jersey, 1958)
Eagle Fire Protection Corp. v. First Indemnity of America Insurance
678 A.2d 699 (Supreme Court of New Jersey, 1996)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
Kampf v. Franklin Life Insurance
161 A.2d 717 (Supreme Court of New Jersey, 1960)
Seidenberg v. Summit Bank
791 A.2d 1068 (New Jersey Superior Court App Division, 2002)
County of Morris v. Fauver
707 A.2d 958 (Supreme Court of New Jersey, 1998)
Printing Mart-Morristown v. Sharp Electronics Corp.
563 A.2d 31 (Supreme Court of New Jersey, 1989)
Friedman v. Tappan Development Corp.
126 A.2d 646 (Supreme Court of New Jersey, 1956)
Ribeira & Lourenco v. Jackson Health
554 A.2d 1350 (New Jersey Superior Court App Division, 1989)
Rieder v. State, Dept. of Transp.
535 A.2d 512 (New Jersey Superior Court App Division, 1987)
Karl's Sales & Serv., Inc. v. Gimbel Bros., Inc.
592 A.2d 647 (New Jersey Superior Court App Division, 1991)
Nieder v. Royal Indemnity Insurance
300 A.2d 142 (Supreme Court of New Jersey, 2004)
Monmouth Lumber Co. v. Indemnity Insurance Co. of North America
122 A.2d 604 (Supreme Court of New Jersey, 1956)
James v. Federal Insurance Co.
73 A.2d 720 (Supreme Court of New Jersey, 1950)
Reynolds Offset Co., Inc. v. Summer
156 A.2d 737 (New Jersey Superior Court App Division, 1959)
East Brunswick v. East Mill Assoc. Inc.
838 A.2d 494 (New Jersey Superior Court App Division, 2004)
Frederick v. Smith
7 A.3d 780 (New Jersey Superior Court App Division, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/lessner-electric-company-vs-fidelity-and-deposit-company-of-maryland-njsuperctappdiv-2018.