LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE)
Opinion
NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court."
Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION
DOCKET NO. A-0081-17T3
LESSNER ELECTRIC COMPANY, Plaintiff-Appellant, v.
FIDELITY AND DEPOSIT COMPANY OF MARYLAND, ZURICH AMERICAN INSURANCE CO., and APS CONTRACTING, INC.,
Defendants-Respondents.
Argued July 31, 2018 – Decided August 8, 2018 Before Judges Sabatino and Mawla.
On appeal from Superior Court of New Jersey, Law Division, Union County, Docket No. L-1353-
17.
Glenn C. Slavin argued the cause for appellant (Slavin & Morse, LLC, attorneys; Glenn C.
Slavin, on the brief).
Eric J. Levine argued the cause for respondents Fidelity and Deposit Company of Maryland and Zurich American Insurance Company (Baron Samson, LLP, attorneys; Eric J. Levine, on the brief).
Daniel Connolly Carmalt argued the cause for respondent APS Contracting, Inc. (Carmalt Law, LLC, attorneys; Daniel Connolly Carmalt, on the brief).
PER CURIAM Plaintiff Lessner Electric Company (Lessner) appeals from August 22, 2017 and September 20, 2017 orders dismissing its complaint alleging breach of contract, delay damages, and unjust enrichment on grounds of a failure to state a claim. We affirm.
In July 2013, Lessner entered into a subcontract with defendant APS Contracting, Inc. (APS) to perform electrical work on the construction of the Union County Family Courthouse. In pertinent part, the contract between Lessner and APS stipulated as follows:
To the fullest extent permitted by law, [Lessner] waives its right to any claim for damage for delay from [APS] . . . . [Lessner]
expressly confirms its understanding that this is a complex project with multiple prime contractors and/or numerous other subcontractors, which conditions may result in, by way of example only and not by the way of limitation, coordination and interference issues, out of sequence work, recurring schedule revisions, compression and/or acceleration of the [w]ork, stoppage of the [w]ork, and/or other unspecified delays to the [p]roject and for which [Lessner] may not be compensated. [Lessner] expressly undertakes and assumes the risks of the above and disclaims any liability for same on the part of [APS].
[(Emphasis added).]
Defendants Fidelity and Deposit Company of Maryland, and its parent company Zurich American Insurance Co. (collectively, the surety) insured the performance of APS through a warranty bond. In April 2015, APS was removed from the project, and the surety assumed APS's role for the remainder of the project.
In August 2015, the surety entered into an Assignment and Ratification Agreement (ratification agreement) with Lessner to reaffirm its subcontract, bring Lessner current for certain payments and costs Lessner believed were due from APS, and have Lessner complete the remainder of its work.
The ratification agreement expressly stipulated in paragraph 2: "Except as otherwise modified by this Agreement, the terms of the Subcontract remain in full force and effect." The ratification agreement further stated Lessner "hereby: (i) ratifies and affirms its obligations under the Subcontract . . . [and] (iv) agrees . . . [it] shall complete the Subcontract and the Subcontract Work . . . for [the] Surety, as a subcontractor for [the] Surety, in accordance with the terms of the Subcontract and Contract [with APS] . . . ." The ratification agreement also set forth the amount Lessner claimed it required from the surety in order to return and complete its work. This figure was comprised of the original amount agreed upon between Lessner and APS with an addition for a change order, less sums already paid to Lessner.
The surety and Lessner agreed on no other conditions on Lessner's return to the project, other than to contract for the payment of the sums due under the original contract. However, the ratification agreement did identify damages Lessner claimed it had suffered as a result of the delay of the project. Specifically, paragraph 4 of the ratification agreement released APS and the surety,
from any and all claims, of any type or kind, known or unknown, asserted or unasserted, which in any way arise from, relate to, or concert the Subcontract, the Contract, the Project, the Bond, and/or the [Lessner's]
performance under the Subcontract, which claims have accrued or arise out of or relate to events occurring prior to the date of this Agreement, excluding only: . . . (ii) such claims as may be identified . . . in Rider A, which is attached hereto and made a part hereof.
Rider A was entitled "PENDING REQUESTS FOR CHANGE ORDERS AND RESERVED CLAIMS," and allegedly included Lessner's non-waiver of a claim for delay damages although the rider did not describe them specifically as such.1 In September 2016, Lessner asserted a claim against the surety seeking "additional compensation due to the delay damages"
1 The bottom of Rider A obliquely references a May 20, 2015 "Scheduling Concerns/Delays" letter. However, the letter was not supplied to the motion judge, and is not part of the record before us.
totaling $1.82 million allegedly resulting in a twenty-four month delay caused by APS's replacement on the project. The surety noted Lessner's sole remedy for delay under the contract was to seek an extension of time to complete its work. The surety also noted there had been "no meeting of the minds" under the ratification agreement to compensate Lessner for delay damages.
Lessner filed a complaint in the Law Division for breach of contract against defendants seeking payment of the delay damages. The complaint asserted three counts against the surety, alleging a breach of the bonding agreement, the contract with APS, and unjust enrichment. The surety and APS filed motions to dismiss for failure to state a claim. Defendants argued their motions should be granted because of the express waiver of delay damages clause under the contract with APS, and that delay damages were not recoverable under the express terms of the bond and the Bond Act, N.J.S.A. 2A:44-143 to -147.
The motion judge granted the surety's motion to dismiss. The judge found Lessner knew of its delay damages claim, yet entered into the ratification agreement, which did not provide for payment of the alleged damages. The judge also concluded the express waiver of delay damages under the contract with APS was binding, and therefore likewise dismissed the claims against APS. This appeal followed.
We begin by reciting our standard of review. Appellate review of a trial court's ruling on a motion to dismiss is de novo. Frederick v. Smith, 416 N.J. Super. 594, 597 (App. Div. 2010) (citing Seidenberg v. Summit Bank, 348 N.J. Super. 243, 250 (App. Div. 2002)). "A complaint should be dismissed for failure to state a claim pursuant to Rule 4:6-2(e) only if 'the factual allegations are palpably insufficient to support a claim upon which relief can be granted.'" Ibid. (quoting Rieder v. State Dep't of Transp., 221 N.J. Super. 547, 552 (App. Div. 1987)). "This standard requires that 'the pleading be searched in depth and with liberality to determine whether a cause of action can be gleaned even from an obscure statement.'" Ibid. (quoting Seidenberg, 348 N.J. Super. at 250); see also Printing Mart- Morristown v. Sharp Elecs. Corp., 116 N.J. 739, 746 (1989).
Free access — add to your briefcase to read the full text and ask questions with AI
LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE) (LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.