Leoff v. S and J Land Company

CourtCourt of Appeals for the Tenth Circuit
DecidedNovember 29, 2012
Docket11-1293
StatusUnpublished

This text of Leoff v. S and J Land Company (Leoff v. S and J Land Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leoff v. S and J Land Company, (10th Cir. 2012).

Opinion

FILED United States Court of Appeals Tenth Circuit

November 29, 2012 UNITED STATES COURT OF APPEALSElisabeth A. Shumaker Clerk of Court TENTH CIRCUIT

RICHARD CHANCE LEOFF,

Plaintiff - Appellee/ Nos. 11-1293, 11-1311 Cross-Appellant, v. (D. Colorado) S AND J LAND COMPANY, a (D.C. No. 1:08-CV-02112-RPM-MEH) Colorado limited liability company,

Defendant - Appellant/ Cross-Appellee.

ORDER AND JUDGMENT *

Before MURPHY, HARTZ, and HOLMES, Circuit Judges.

Richard “Chance” Leoff and S and J Land Company (S&J) went into

business together to build condominiums in Telluride, Colorado. When the

project faltered and the relationship soured, Leoff filed a mechanic’s lien against

the property and sued in federal district court for damages and to enforce the lien.

S&J responded with a counterclaim seeking damages for wrongful filing of a

mechanic’s lien and breach of contract, a declaration that S&J and Leoff had

* This order and judgment is not binding precedent except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1. formed a partnership, and a winding up of the partnership and an accounting of

the partners’ rights and obligations. The district court granted partial summary

judgment to S&J, holding that the parties had formed a partnership and that under

Colorado law a partner cannot place a mechanic’s lien on partnership property.

Leoff filed an amended complaint asserting fraud and breach of fiduciary duty,

and he also filed with the court and recorded with the county clerk a notice of lis

pendens. S&J filed an amended counterclaim, adding a claim for damages from

the allegedly improper filing of the notice of lis pendens.

After a bench trial on the remaining claims and counterclaims, the court

decreed the partnership to be dissolved and ordered the sale of the condominium

development. It refused, however, to conduct a final accounting of the partners’

respective rights and liabilities. And although it held that Leoff’s mechanic’s lien

and notice of lis pendens had been wrongfully filed, it also refused to award S&J

actual damages or attorney fees resulting from those filings, instead awarding

only a minimum statutory penalty of $1,000. Both parties appealed. Although we

affirm on most of the issues, we reverse and remand for the district court to

conduct a final partnership accounting and to permit S&J to present evidence of

the attorney fees incurred as a result of Leoff’s wrongful mechanic’s lien.

I. BACKGROUND

In 2004 three men agreed to develop a condominium project on a piece of

land in Telluride, Colorado. Two of them, Stephen Finger and Jeffrey Lehrer,

-2- were the only members of S&J, a Colorado limited-liability company. Finger was

a Telluride resident with some experience in developing local real estate; Lehrer

lived in Scottsdale, Arizona, but had worked with Finger on two earlier local

projects. The third man was Leoff, who then lived in Telluride and who knew

Finger and Lehrer socially. They referred to the proposed condominiums as the

White House Project. S&J paid for the land, and the title was in S&J’s name.

Although at first Leoff and S&J did not formally delineate the division of

responsibilities for the White House Project, both parties now agree that Leoff

was at least in charge of obtaining certain government approvals necessary to

begin construction. Leoff apparently maintains that his duties were limited to this

task, whereas S&J claims that Leoff was expected to supervise construction as

well. Leoff did obtain a building permit sometime in 2006.

Leoff and S&J finally memorialized their arrangement in a document titled

“Management Agreement,” which was executed on March 14, 2006. R., Vol. IX

Ex. A-2 at 1. It recited the parties’ prior understanding that “Chance Leoff would

manage the project from time of land acquisition to the sale and completion of all

units.” Id. It said that Leoff’s specific duties as Manager included the following:

(1) To manage and oversee the acquisition of the property, the design of development property improvements, including hiring and management of all architects, engineers, and other consultants, to secure a general contractor, and to manage the entitlement and approval process through all required municipalities.

-3- (2) To execute and deliver required permits, licenses, agreements, contracts, leases, documents and other instruments appropriate in furthering the acquisition, development, design, construction, management and completion of the development property improvements in accordance with the plans, specifications and budgets approved by the members.

(3) To manage and oversee the construction and development of development property improvements on the development property.

Id. The Agreement then declared that the parties agreed “that Duty 1, as specified

above, has been completed and that Leoff is entitled to 30% of all profits or

losses of S&J, as defined in III-R of the Operating Agreement of S&J, and to be

distributed as per Section 6 in the same agreement.” Id. S&J’s “Development

Agreement and Operating Agreement,” also executed on March 14, described

S&J’s governance; Leoff was not a signatory. Id. Ex. A-1 at 1–18. The

Management Agreement also specified that Leoff would be entitled to receive

$100,000 before construction was completed; half of that amount was designated

as a fee, and the other half would count as an advance on Leoff’s share of S&J’s

profits. Because $10,000 of the $100,000 had already been paid in 2005, the

remaining $90,000 was to be paid in monthly installments of $9,000 for each of

the ten months after the bank loan for the White House Project became funded.

The White House Project was a troubled one. In July 2006 S&J signed an

agreement with a contractor, High Mark Development, Inc., which would be paid

its costs plus 15% for building the condominiums. According to S&J, the project

-4- ran into a host of snags thereafter, allegedly because Leoff delayed in providing

the contractor with plans, failed to ensure those plans complied with local

building codes, had an uneasy relationship with the architect, and generally

neglected to keep either himself or S&J abreast of the day-to-day details of

construction. Leoff tells a different story. No sooner had he signed the

Management Agreement in March 2006, he claims, than S&J “took control of and

assumed complete responsibility for the White House Project.” Aplee. Br. at 23.

In Leoff’s version, S&J negotiated the construction contract, obtained the

financing, supervised High Mark and reported on progress to the lending bank,

wrote the checks, and marketed the condominiums to potential buyers. Leoff

disclaims any responsibility for overseeing construction, asserts that S&J’s

members never blamed him for problems during construction, and insists that any

difficulties were the fault of High Mark, which was supposed to be supervised not

by him but by Lehrer.

Whatever the explanation, the cost of the project soon overran the budget

as construction continued. S&J was able to negotiate a $200,000 reduction in

High Mark’s fee, but the various purchasers who had entered into preconstruction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenlaw v. United States
554 U.S. 237 (Supreme Court, 2008)
Cummings v. Norton
393 F.3d 1186 (Tenth Circuit, 2005)
Camuglia v. City of Albuquerque
448 F.3d 1214 (Tenth Circuit, 2006)
Creative Consumer Concepts, Inc. v. Kreisler
563 F.3d 1070 (Tenth Circuit, 2009)
United States v. Madrid
633 F.3d 1222 (Tenth Circuit, 2011)
Yoder v. Hooper
695 P.2d 1182 (Colorado Court of Appeals, 1985)
Stratman v. Dietrich
765 P.2d 603 (Colorado Court of Appeals, 1988)
Hammersley v. District Court in and for County of Routt
610 P.2d 94 (Supreme Court of Colorado, 1980)
Grau v. Mitchell
397 P.2d 488 (Supreme Court of Colorado, 1964)
Cooper v. Flagstaff Realty
634 P.2d 1013 (Colorado Court of Appeals, 1981)
Damrell v. Creagar
599 P.2d 262 (Colorado Court of Appeals, 1979)
Pierce v. Francis
194 P.3d 505 (Colorado Court of Appeals, 2008)
Kerns v. Kerns
53 P.3d 1157 (Supreme Court of Colorado, 2002)
Tucker v. Ellbogen
793 P.2d 592 (Colorado Court of Appeals, 1989)
Brossia v. Rick Construction, Ltd. Liabiltity Co.
81 P.3d 1126 (Colorado Court of Appeals, 2003)
Platt v. Aspenwood Condominium Ass'n, Inc.
214 P.3d 1060 (Colorado Court of Appeals, 2009)
Hooper v. Yoder
737 P.2d 852 (Supreme Court of Colorado, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Leoff v. S and J Land Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leoff-v-s-and-j-land-company-ca10-2012.