Lemoine Co. v. Durr Heavy Construction, LLC

206 So. 3d 244, 2015 La.App. 1 Cir. 1997, 2016 La. App. LEXIS 1970
CourtLouisiana Court of Appeal
DecidedOctober 31, 2016
DocketNO. 2015 CA 1997
StatusPublished
Cited by3 cases

This text of 206 So. 3d 244 (Lemoine Co. v. Durr Heavy Construction, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lemoine Co. v. Durr Heavy Construction, LLC, 206 So. 3d 244, 2015 La.App. 1 Cir. 1997, 2016 La. App. LEXIS 1970 (La. Ct. App. 2016).

Opinion

HIGGINBOTHAM, J.

12This is an appeal from a judgment of the district court that dismissed plaintiffs motion to stay the proceeding and compel arbitration, and granted defendants’ peremptory exception raising the objection of peremption, thereby dismissing all of plaintiffs claims.

FACTUAL AND PROCEDURAL HISTORY

This action arises out of the construction of the LLOG Exploration Co., LLC Executive Office and Athletic Club in Covington, Louisiana (the project), on which plaintiff, The Lemoine Company, LLC, acted as the general contractor. Lemoine subcontracted [246]*246portions of the work to several parties including defendants, Ceco Concrete Construction, LLC and Durr Heavy Construction, LLC. After construction on the project was completed, the last certificate of substantial completion documenting acceptance of the work by the project owner, Cypress Bend Real Estate Development Company, was recorded on June 26, 2009, in the St. Tammany Parish public records.

On March 31, 2014, Cypress Bend filed suit against Lemoine seeking damages for alleged defects in the project. On April 4, 2014, Cypress Bend commenced arbitration proceedings against Lemoine seeking to recover damages.

A year later, on April 2, 2015, Lemoine filed a petition against Ceco and Durr alleging that Ceco and Durr had breached their respective subcontracts for the project and owed Lemoine indemnity in conformance with the subcontracts for the claims asserted against it by Cypress Bend. In its petition, Lemoine stated that it did not intend to litigate the dispute subject to the petition, but instead would pursue its claims in arbitration pursuant to its arbitration agreements in the subcontracts with Ceco and Durr. On April 22, 2015, Lemoine filed a motion to stay the proceedings and compel arbitration.

^Subsequently, both Ceco and Durr filed peremptory exceptions of peremption, on grounds that Lemoine’s claims were per-empted and extinguished by La. R.S. 9:2772, because Lemoine’s petition was filed more than five years after the recor-dation of the last certificate of completion for the project and more than five years after Cypress Bend had assumed possession of and occupied the project. Lemoine opposed the peremptory exception contending first, that in accordance with the arbitration agreement in the subcontracts, peremption is for the arbitrator, not the district court, to decide and second, that its claims were not perempted.

Following a hearing, the district court signed a judgment denying Lemoine’s motion to stay proceedings and compel arbitration, granting Ceco and Durr’s peremptory exceptions of peremption, and dismissing all of Lemoine’s claims and causes of action against Ceco and Durr. It is from this judgment that Lemoine appeals, citing the following assignments of error:

1. The district court erred, as a matter of law, in refusing to stay the proceedings and compel arbitration in accordance with the written arbitration agreement between the parties.
2. The district court erred, as a matter of law, in considering and adjudicating the peremptory exception of per-emption since those issues were solely for the arbitrator to decide.

LAW AND ANALYSIS

I. Motion to Compel Arbitration

The determination as to whether to stay or compel arbitration is a question of law. The standard of appellate review for questions of law is simply to determine whether the district court was legally correct or incorrect. Arkel Constructors, Inc. v. Duplantier & Meric, Architects, L.L.C., 2006-1950 (La.App. 1 Cir. 7/25/07), 965 So.2d 455, 459. In ruling on a motion to compel arbitration, the threshold inquiry a court must decide is whether the parties agreed to arbitrate their dispute. This is a two-fold inquiry; to wit: (1) whether there is a valid arbitration agreement, and (2) Lwhether the dispute in question falls within the scope of that agreement. Collins v. Prudential Ins. Co. of America, 99-1423 (La. 1/19/00), 752 So.2d 825, 831.

[247]*247Arbitration is a matter of contract, and a party cannot be required to submit to arbitration any dispute to which he has not so agreed. The authority of an arbitrator to resolve disputes is derived from the parties’ advance agreement to submit such grievances to arbitration. AT & T Technologies, Inc. v. Communications Workers of America, 475 U.S. 643, 648-49, 106 S.Ct. 1415, 1418, 89 L.Ed.2d 648 (1986). The United States Supreme Court in Howsam v. Dean Witter Reynolds Inc., 537 U.S. 79, 83, 123 S.Ct. 588, 591, 154 L.Ed.2d 491 (2002), stated that “[t]he question whether the parties have submitted a particular dispute to arbitration, la, ‘the question of arbitrability,’ is ‘an issue for judicial determination [u]nless the parties clearly and unmistakably provide otherwise.’ ” See also Breaux v. Stewart Enterprises Inc., 2004-1706 (La. 10/8/04), 883 So.2d 983, 983-84. (per curiam.)

In support of its contention that the-parties submitted the issue of arbitrability and therefore the issue of peremption to arbitration, Lemoine cites to paragraph 34 of the subcontracts titled “disputes.”1 Paragraph 34 provides in pertinent part as follows:

(d)If at any time, any claim, dispute or controversy should arise between the Contractor and Subcontractor regarding any matter or thing involved in this Subcontract (or breach of it) or construction project.. .then the decision of the Contractor shall be followed by the Subcontractor and the claim, dispute or controversy shall be decided as stated -'below in the Paragraph 34.
(e) The Subcontractor shall conclusively be bound by and abide by the Contractor’s decision, unless arbitration proceedings are commenced as provided below.
(f) Should the Subcontractor decide to appeal from the decision of the Contractor, then the controversy shall be decided by arbitration ... and the arbitration decision shall be final and binding upon both parties to resolve the controversy— The arbitration shall be in accordance with the Construction Industry Rules of the American Arbitration Association. The arbitration will include, if possible, by consolidation or other joinder, all parties necessary to afford complete relief in the arbitration or necessary to avoid the possibility of inconsistent results.

Lit is Lemoine’s position that by incorporation of the Construction Industry Rules of the American Arbitration Association (AAA rules) into the subcontracts, specifically, rule 9 regarding jurisdiction, the parties agreed to delegate to the arbitrator all issues regarding the arbitrator’s jurisdiction and all issues regarding the existence, scope and validity of the arbitration agreement, including the issue of peremption.2 Lemoine relies on Jasper Contractors, which stated that when the [248]*248parties explicitly incorporate rules that empower an arbitrator to decide issues of arbitrability, the incorporation serves as “clear and unmistakable evidence of the parties’ intent to delegate such issues to an arbitrator.” Jasper Contractors, Inc. v. E-Claim.com, LLC, 2011-0978 (La.App. 1 Cir. 5/4/12), 94 So.3d 123, 133.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitney Bank v. Henry Rayford
Louisiana Court of Appeal, 2021
Bank v. Rayford
247 So. 3d 733 (Louisiana Court of Appeal, 2018)
Boh Bros. Construction Co. v. Cypress Bend Real Estate Development Co.
206 So. 3d 1131 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
206 So. 3d 244, 2015 La.App. 1 Cir. 1997, 2016 La. App. LEXIS 1970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lemoine-co-v-durr-heavy-construction-llc-lactapp-2016.