Lemartec Engineering & Construction n/k/a Lemartec Corporation v. Advance Conveying Technologies, LLC

CourtSupreme Court of Iowa
DecidedMarch 20, 2020
Docket18-2183
StatusPublished

This text of Lemartec Engineering & Construction n/k/a Lemartec Corporation v. Advance Conveying Technologies, LLC (Lemartec Engineering & Construction n/k/a Lemartec Corporation v. Advance Conveying Technologies, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lemartec Engineering & Construction n/k/a Lemartec Corporation v. Advance Conveying Technologies, LLC, (iowa 2020).

Opinion

IN THE SUPREME COURT OF IOWA No. 18–2183

Filed March 20, 2020

LEMARTEC ENGINEERING & CONSTRUCTION n/k/a LEMARTEC CORPORATION,

Appellant,

vs.

ADVANCE CONVEYING TECHNOLOGIES, LLC,

Appellee.

Appeal from the Iowa District Court for Monroe County, John

Telleen, Judge.

On interlocutory appeal of a district court order granting summary

judgment in appellee’s favor, appellant argues appellee is not entitled to

claim preclusion or issue preclusion even though the federal court found

in appellee’s favor in the parallel federal case. REVERSED AND

REMANDED WITH DIRECTIONS.

Erik W. Scharf, Miami, Florida, Mark L. Tripp, Andrew C. Johnson,

Thomas M. Boes, and Robert J. Thole of Bradshaw, Fowler, Proctor &

Fairgrave, P.C., Des Moines, and Jason L. Molder, Miami Florida, for

appellant.

Kevin J. Caster and Dana L. Oxley (until withdrawal) of Shuttleworth

& Ingersoll, P.L.C., Cedar Rapids, for appellee. 2

APPEL, Justice.

In this construction law case, we consider the applicability of the

doctrines of claim and issue preclusion to disputes arising out of a contract

between two subcontractors in a construction project.

First, a dispute arose around the fabrication and operation of a salt

conveyor system. In federal litigation, a number of subcontracting parties

litigated questions related to the fabrication of the salt conveyor system

prior to litigation. The federal controversy was eventually reduced to

judgment.

The owner of the facility filed a second lawsuit against

subcontractors involved in the federal litigation in state court. The owner

claimed in the state court litigation that after installation, the salt conveyor

system developed corrosion issues in breach of contract and express and

implied warranties. The parties filed various cross-claims, with one

contractor seeking indemnity from the fabricator of the salt conveyor

system.

After the federal litigation was resolved, a successful subcontractor

in the federal litigation brought a motion for summary judgment in the

state court action, arguing that determinations in the federal litigation

precluded parties from litigating issues related to the salt conveyor system

in state court.

The district court granted summary judgment to the successful

federal subcontractor on claim and issue preclusion grounds. A

disappointed party sought interlocutory appeal, claiming, among other

things, that the successful party in the federal litigation waived its claim

preclusion argument in the state court litigation because it failed to give

notice of intent to pursue claim preclusion in the simultaneously pending

state court litigation. On the question of issue preclusion, the 3

disappointed party asserted that it had no reasonable opportunity in

federal court to litigate its indemnity claim related to the alleged corrosion

problems that arose after the salt conveyor equipment was installed and,

therefore, issue preclusion did not apply.

We granted the application for interlocutory review. For the reasons

expressed below, we conclude that the district court erred in granting

summary judgment based on claim and issue preclusion under the facts

of this case.

I. Factual and Procedural Background.

A. Relationship of the Parties. In 2013, HF Chlor-Alkali, LLC

(HFCA) entered into a written agreement with Conve & AVS, Inc. (Conve)

to construct a chlor-alkali manufacturing facility (the Project) in Eddyville,

Iowa. Conve in turn entered into a subcontract with Lemartec Engineering

& Construction n/k/a Lemartec Corporation (Lemartec) to design and

build the physical plant for the Project which included a salt conveyor

system (conveyor system).

Lemartec subcontracted part of the work on the conveyor system to

two other entities. Lemartec, through a purchase order, hired Advance

Conveying Technologies, LLC (ACT) for the design and manufacture of the

conveyor system. Later, Lemartec entered into a subcontract with

Southland Process Group, LLC (SPG) for the installation and erection of

the conveyor system at the Project location.

The conveyor system aspect of the Project did not proceed smoothly.

SPG claimed that there were problems with the component parts supplied

by ACT. Lemartec contacted ACT, claiming deficiencies in ACT’s work.

SPG eventually finished the work but claimed that it incurred significant

additional costs and that Lemartec and ACT were responsible for them. 4

B. Filing of Federal Court and State Court Litigation.

1. Overview of federal court litigation. The first litigation arrow in

this case was fired by SPG on October 16, 2015, in the United States

District Court for the Southern District of Iowa. SPG sought to recover its

additional expenses related to the assembly of the conveyor system from

Lemartec and ACT. Lemartec and SPG settled outstanding disputes

between them, leaving ACT’s claim that Lemartec improperly withheld

from ATC the balance owed under the purchase order to be litigated.

2. Overview of state court litigation. The completed Project was

turned over to Conve in June 2015 and later to owner HFCA. HFCA was

dissatisfied with many aspects of the Project. As a result, HFCA launched

the second litigation arrow in this case in state court, naming a number of

defendants including Conve. HFCA alleged, among other things, that the

conveyor system was installed, turned over and put to use, and failed to

perform to specifications. Conve, in turn brought a third-party claim

against Lemartec for indemnification and contribution. Lemartec on

June 5, 2017, brought a third-party claim against ACT.

ACT filed an answer to Lemartec’s third-party claim. In its answer,

ACT did not make reference to the pending federal litigation and did not

raise a res judicata affirmative defense.

Discovery proceeded in the state court litigation. On June 14, 2018,

HFCA served interrogatory responses on the parties. According to the

responses, HFCA claimed that the conveyor system failed to perform in

that the conveyor components and electrical system corroded; the

conveyor belt did not pass approval testing; the bucket system leaked,

corroded, and fell apart; and the equipment ruptured due to the failure to

prevent vibrations. 5

3. Federal court judgment. The federal court held a bench trial in

the federal litigation in April 2018. The federal court characterized the

issue to be tried as “whether either of the two remaining parties [Lemartec

and/or ACT] owes money to the other for money earned, but unpaid;

project delays; and for additional work that was required to make the

conveyor system functional.”

On May 21, 2018, the federal district court entered its ruling in favor

of ACT. The federal district court awarded ACT $317,467.07 plus interest.

Lemartec has appealed the case to the United States Court of Appeals for

the Eighth Circuit.

4. Summary judgment in state court proceedings based on preclusive

effect of federal judgment. On August 15, 2018, ACT filed a motion for

summary judgment in the state court proceedings. In its moving papers,

ACT claimed that the judgment in the federal litigation compelled

judgment in its favor in the state court litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Bank of Louisville v. Stone, Auditor
174 U.S. 432 (Supreme Court, 1899)
Bank of New York v. First Millennium, Inc.
607 F.3d 905 (Second Circuit, 2010)
Mitchell v. City of Moore
218 F.3d 1190 (Tenth Circuit, 2000)
Smith v. Potter
513 F.3d 781 (Seventh Circuit, 2008)
Pagel v. Notbohm
186 N.W.2d 638 (Supreme Court of Iowa, 1971)
Johnston Equipment Corp. of Iowa v. Industrial Indemnity
489 N.W.2d 13 (Supreme Court of Iowa, 1992)
Arnevik v. University of Minnesota Board of Regents
642 N.W.2d 315 (Supreme Court of Iowa, 2002)
Colvin v. Story County Board of Review
653 N.W.2d 345 (Supreme Court of Iowa, 2002)
Grant v. Iowa Department of Human Services
722 N.W.2d 169 (Supreme Court of Iowa, 2006)
Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Evjen v. Brooks
372 N.W.2d 494 (Supreme Court of Iowa, 1985)
B & B Asphalt Co. v. T. S. McShane Co.
242 N.W.2d 279 (Supreme Court of Iowa, 1976)
Iowa Coal Mining Co. v. Monroe County
555 N.W.2d 418 (Supreme Court of Iowa, 1996)
Winnebago Industries, Inc. v. Haverly
727 N.W.2d 567 (Supreme Court of Iowa, 2006)
Fischer v. City of Sioux City
654 N.W.2d 544 (Supreme Court of Iowa, 2002)
Noel v. Noel
334 N.W.2d 146 (Supreme Court of Iowa, 1983)
Bertran v. Glens Falls Insurance Company
232 N.W.2d 527 (Supreme Court of Iowa, 1975)
State v. Harper
222 N.W.2d 450 (Supreme Court of Iowa, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Lemartec Engineering & Construction n/k/a Lemartec Corporation v. Advance Conveying Technologies, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lemartec-engineering-construction-nka-lemartec-corporation-v-advance-iowa-2020.