Lees v. Chicago & North Western Railway Co.

89 N.E.2d 418, 339 Ill. App. 227, 1947 Ill. App. LEXIS 390
CourtAppellate Court of Illinois
DecidedDecember 30, 1947
DocketGen. No. 43,632
StatusPublished
Cited by3 cases

This text of 89 N.E.2d 418 (Lees v. Chicago & North Western Railway Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lees v. Chicago & North Western Railway Co., 89 N.E.2d 418, 339 Ill. App. 227, 1947 Ill. App. LEXIS 390 (Ill. Ct. App. 1947).

Opinions

Mr. Presiding Justice Friend

delivered the opinion of the court.

Plaintiff brought suit against defendant under the Federal Employers’ Liability Act to recover damages for injuries sustained by him in connection with the installation of a piling cluster adjacent to defendant’s right of way over its Illinois River bridge near Pekin, Illinois. Trial by jury resulted in a verdict in his favor for $30,000, and after defendant’s motions for judgments notwithstanding the verdict and, in the alternative, for a new trial or for a remittitur were overruled, the court entered judgment on the verdict, from which defendant appeals.

The essential facts disclose that defendant has a single line track from Nelson to South Pekin, Illinois, which crosses the Illinois River in a north and south direction over a bridge approximately 1500 feet long. The bridge is commonly designated as a vertical lift drawbridge and is constructed so that there is a multiple span across the clear channel of the river, a section of which span is raised in a horizontal position to clear the channel whenever necessary to permit river ships to pass. As a protection to the bridge against damage by ship traffic, pilings are driven in clusters on both sides of the bridge and near the clear channel. A pile cluster on the west or downstream side of the bridge, which had been damaged by a river ship some months prior to the accident here involved, had to be replaced.

The defendant railway company was not equipped to perform the work of removing the old cluster and installing a new one, and it therefore entered into a written contract with Carl Budd and Noal Lorance, doing business as the Deneen River Company (hereinafter referred to as the contractor), to do the job. The contract is dated May 13,1941, and provides for removing the damaged cluster and constructing a new one. The work was to be done in accordance with blueprint No. 24200, attached to the contract. By the terms of the agreement the contractor was to furnish all labor, tools and equipment and certain materials, including the steel jacket, splice plates, etc. The piles were to be furnished by the railway company. The work was to be completed in a manner satisfactory to the chief engineer of the railway company within 60 days from the date of the contract. The contractor was to be paid 40 cents a foot for handling and driving the creosoted piles, approximately $800 for furnishing and placing the steel jacket on the cluster, $350 for removing the damaged cluster, and 2% cents a pound for driving I-beams. Work not included in the specified unit prices but which should be ordered by the railway company was to be done on a cost plus 20 per cent basis.

The timbers or piles, which were each about 60 feet long, were to be unloaded from the defendant’s freight cars and handled by the contractor. The contractor undertook to indemnify and save harmless the railway company from all liability arising out of injury to the contractor or its employees, and also from all liability growing out of injury to any railway company employees caused by the negligence of the contractor or its employees.

The blueprint attached to the contract indicates that the piles were to have a minimum penetration of 20 feet below the bottom of the river; it shows the number and spacing of the piles, the angles at which they are to be put in, and the steel jacket in which they are to be encased. Splicing details are given, as well as types of bolts, I-beams, etc. At the right side of the blueprint is a bill of material which states that the railway company is to furnish the creosoted piles, the steel strands, clips and staples. The steel jacket is to be furnished by the contractor.

In the course of construction the railway company’s division engineer, L. R. Lamport, wrote the contractor, stating that it would be necessary to provide a walkway from the bridge to reach the new pile cluster and that a steel support for the walk was being shipped from Chicago; that the railway company desired the contractor to handle the steel support from the cars and place it on the pile cluster so that at a later date a walkway could be laid on the steel support. The purpose of the walk was to enable the bridge tender to go out on the cluster to service and maintain the navigation lights.

Work was commenced under the contract on June 24, 1941. In the installation of this pile cluster the contractor employed three of its own barges, one of which was used for timbers and other material, on another was installed a derrick, and on the third a pile driver. The new cluster contained 37 pilings, and each piling was hoisted from the material barge by a derrick, put in place, and then hammered down by the pile driver. The contractor furnished and paid for all labor for this work. The crew consisted of an engineer and a fireman who operated the pile driver, and five carpenters who handled the piling and other materials.

The timbers used for the piling were ereosoted so as to protect them against the elements, and because the work was done in hot weather the hammering on the tops of the piles brought out the creosote, creating a slippery condition on the surface of the cluster. After the piles were driven into position, there was a variation of six inches or more from the top of one pile to the top of another. This variation in height was to be compensated for upon the completion of the work by placing a block on top of the cluster. The installation was properly completed by the contractor and payment made by the railway company in accordance with the terms of the contract.

Plaintiff had been employed in the engineering department of the railroad since 1934. His immediate superior was division engineer Lamport. Several days before the work was started plaintiff was called in to Lamport’s office and given a plan of the proposed installation. He testified that Lamport told him to go to the site of the bridge “and see that a good job was done, go as near the plan as they could, and keep the job moving, as they were late in starting.” In compliance with his directions plaintiff proceeded to the scene of the job. He testified that he kept a record of the position of the piles that were removed from the damaged cluster and made himself generally useful assisting the contractor in keeping the job moving along, helping the contractor dismantle the old cluster and install the new timber and I-beams. He stated that on two occasions Lamport came to the bridge while he (plaintiff) was there, and that on one of these occasions he was working with piling.

The driving of the new piles was completed three or four days before the accident. The steel jacket was placed on the cluster July 21, 1941. At that time the contractor’s employees on the job were Lorance, two steel workers and two carpenters. The accident occurred July 21. Shortly after lunch on that day it became necessary to put a wooden bearing block on top of the cluster to serve as a basis or support for the steel frame that was to be hoisted in place. Although there was a carpenter standing on the barge right beside plaintiff, he (plaintiff) decided that he would help with the carpentry work required in fastening the block on the cluster. Just before plaintiff went up Vincent Eudolph, one of the contractor’s steel workers, had been lifted up from the barge to the top of the cluster.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moss v. Central of Georgia Railroad
219 S.E.2d 593 (Court of Appeals of Georgia, 1975)
Tinsley v. Massman Const. Co.
270 S.W.2d 835 (Supreme Court of Missouri, 1954)
Downs v. Baltimore & Ohio Railroad
102 N.E.2d 537 (Appellate Court of Illinois, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
89 N.E.2d 418, 339 Ill. App. 227, 1947 Ill. App. LEXIS 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lees-v-chicago-north-western-railway-co-illappct-1947.