Lechner v. Reutepohler

545 N.E.2d 1144, 1989 Ind. App. LEXIS 1125, 1989 WL 138042
CourtIndiana Court of Appeals
DecidedNovember 15, 1989
Docket19A01-8904-CV-00121
StatusPublished
Cited by18 cases

This text of 545 N.E.2d 1144 (Lechner v. Reutepohler) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lechner v. Reutepohler, 545 N.E.2d 1144, 1989 Ind. App. LEXIS 1125, 1989 WL 138042 (Ind. Ct. App. 1989).

Opinion

RATLIFF, Chief Judge.

STATEMENT OF THE CASE

Virgil and Jo Ann Lechner appeal the judgment of the small claims court finding them liable to homeowners, Curtis and Sharon Reutepohler, for $8,000.00 plus court costs for work and material expended on structural repairs made to the Reute-pohlers' home in order to stem a water leakage problem. We reverse.

FACTS

The Reutepohlers purchased a new home from the Lechners through Century 21 Realty in November of 1981. The home was about ninety-five percent (95%) completed at the time of the purchase. Final grading of the lot had been completed, but no landscaping had been undertaken.

Virgil Lechner provided the blue print from which the house was constructed. Lechner hired subcontractors to do most of the actual construction on the house, and claimed at trial that he was not otherwise involved in constructing the house. However, the Reutepohlers claimed that he did do some work on the house. Lechner admits to inspecting the house.

As the house was being constructed, Lechner listed the house for sale with Century 21 Realty. All negotiations and transactions with respect to the purchase of the house took place between the Reutepohlers and Linda Schroering, the real estate agent. The Lechners previously sold twelve (12) other homes following a similar method. The Reutepohlers signed a purchase agreement which contained a clause releasing the seller from all liability relating to any defect in the house.

When the Reutepohlers moved into the house in 1981 they noticed small cracks in a basement wall and that small puddles ap *1146 peared on the floor of the basement after every rainfall. The Reutepohlers also noticed that the ground slope away from the house was inadequate and that after a rainfall water would stand in front of the house and puddles would form.

In 1982, the Reutepohlers poured a concrete driveway and began landscaping the property. At this time the Reutepohlers added dirt in an attempt to increase the ground slope away from the house. However, water continued to run up against the house despite this attempt at repair.

In April of 1985, after the basement flooded once again, the Reutepohlers called +»Gene CGiehl of G & S Homes who indicated that the cracks in the basement wall needed to be repaired. The Reutepohlers then contacted Lechner to tell him that they were having their basement repaired and to find out where the cement blocks in the basement changed from ten inch to six inch blocks. Lechner testified that the Reute-pohlers never complained to him about water problems in the basement nor did the Reutepohlers reveal to him the extent of structural repair being undertaken to rectify the problem. Lechner stated at trial that the Reutepohlers indicated to him at this time that they did not want Lechner to do the repair work. The Reutepohlers noted that in the past when they had experienced problems with the house, including a malfunctioning air-conditioner and septic system, they had contacted Lechner. Lech-ner would then refer the Reutepohlers to the subcontractors who installed the faulty equipment, and the Reutepohlers would contact that party for repairs.

G & S Homes attempted to fix the water problem in April of 1985. However, additional work was needed in September of 1985 and again in January of 1986. In April of 1986, more repair efforts were made which were completed in July of 1986.

In early 1987 the Reutepohlers contacted Lechner and indicated that they wanted Lechner to pay for the repairs made on the basement. Lechner refused to pay.

On March 28, 1988, the Reutepohlers filed suit in small claims court against the Lechners for breach of the implied warranty of habitability. On October 18, 1988, the trial court entered judgment against the Lechners in the amount of $8,000 plus court costs. From this decision the Lech-ners now appeal.

ISSUES

Because we reverse the judgment of the trial court only the following two issues will be discussed in this opinion:

1. Was the Reutepohlers' cause of ac tion barred by the statute of limitations?

2. Was the Reutepohlers' cause of action barred by the release provision of the purchase agreement?

DISCUSSION AND DECISION

Issue One

The Lechners first claim that the trial court erred in entering judgment for the Reutepohlers because this action was barred by the statute of limitations. The Lechners first raised this claim of error in their motion to correct errors.

Because the Reutepohler's cause of action was filed in a small claims court, the Lechners were not required to plead the statute of limitations as an affirmative defense. Indiana Rules of Procedure, Small Claims Rule 4(A). ("All defenses shall be deemed at issue without responsive pleadings ..."). Frank H. Monroe Heating and Cooling Inc. v. Rider (1983), Ind.App., 450 N.E.2d 1056 (Trial Rules govern small claims proceedings only to the extent that they are not inconsistent with the Small Claims Rules). Nonetheless, the Lechners were still required to litigate this issue at trial. S.R. 4(A) ([TJhis provision shall not alter the burden of proof). The party claiming the statute of limitations defense bears the burden of proving that the cause of action was instituted beyond the time allowed. Ballard's Estate v. Ballard (1982), Ind.App., 434 N.E.2d 136, 142; H.W.K. v. M.A.G. (1981), Ind.App., 426 N.E.2d 129, 133. It was conceded at oral argument that the statute of limitations was never mentioned at trial. Further *1147 more, evidence elicited from the Reutepoh-lers on direct and cross-examination conflicted with statements made by the Lech-ners' attorney during closing argument concerning when the Reutepohlers' cause of action actually occurred. The Reutepoh-lers testified that they first noticed standing water in the basement and cracks in the basement wall soon after moving into the house in 1981. During closing arguments, the Lechners' attorney stated that "[t]here was no real problem in '82. There was no real problem in '88. The problem started after that, I guess the evidence would be in '84, and then it got bad in '85." Record at 817. The Reutepohlers filed suit in 1987. The Lechners now correctly claim that a six year statute of limitations is applicable to the Reutepohlers' claim. 1 If the Lechner's had actually litigated the statute of limitations claim at trial, the Lechners' attorney would not have claimed during closing argument that "the problem" started in 1984 or 1985, therefore implying that the Reutepohlers' 1987 suit was brought well within the six year statute of limitations. Because the Lechners failed to preserve at trial the issue of the Reutepohlers' alleged violation of the statute of limitations, the issue is waived on appeal. 2

Issue Two

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wolverine Mutual Insurance Co. v. Oliver
933 N.E.2d 568 (Indiana Court of Appeals, 2010)
Zollman v. Geneva Leasing Associates, Inc.
780 N.E.2d 387 (Indiana Court of Appeals, 2002)
Wells v. Trinity Universal Insurance Co.
655 N.E.2d 514 (Indiana Supreme Court, 1995)
Wright Motors, Inc. v. Marathon Oil Co.
631 N.E.2d 923 (Indiana Court of Appeals, 1994)
Prall v. Indiana National Bank
627 N.E.2d 1374 (Indiana Court of Appeals, 1994)
OEC-Diasonics, Inc. v. Major
622 N.E.2d 1025 (Indiana Court of Appeals, 1993)
Citizens National Bank of Tipton v. Indianapolis Auto Auction
592 N.E.2d 1256 (Indiana Court of Appeals, 1992)
Smith v. Hansen
582 N.E.2d 446 (Indiana Court of Appeals, 1991)
Stampco Const. Co., Inc. v. Guffey
37 Cont. Cas. Fed. 76,176 (Indiana Court of Appeals, 1991)
Callander v. Sheridan
546 N.E.2d 850 (Indiana Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
545 N.E.2d 1144, 1989 Ind. App. LEXIS 1125, 1989 WL 138042, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lechner-v-reutepohler-indctapp-1989.