LeChase Constr. Servs., LLC v. Albany Place Dev., LLC

2026 NY Slip Op 50020(U)
CourtNew York Supreme Court, Albany County
DecidedJanuary 9, 2026
DocketIndex No. 906676-19
StatusUnpublished
AuthorLynch

This text of 2026 NY Slip Op 50020(U) (LeChase Constr. Servs., LLC v. Albany Place Dev., LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court, Albany County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeChase Constr. Servs., LLC v. Albany Place Dev., LLC, 2026 NY Slip Op 50020(U) (N.Y. Super. Ct. 2026).

Opinion

LeChase Constr. Servs., LLC v Albany Place Dev., LLC (2026 NY Slip Op 50020(U)) [*1]
LeChase Constr. Servs., LLC v Albany Place Dev., LLC
2026 NY Slip Op 50020(U)
Decided on January 9, 2026
Supreme Court, Albany County
Lynch, J.
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and will not be published in the printed Official Reports.


Decided on January 9, 2026
Supreme Court, Albany County


LeChase Construction Services, LLC, Plaintiff,

against

Albany Place Development, LLC and JOHN DOES, Defendants.

Albany Place Development, LLC, Defendant and Third-Party Plaintiff,

against

Schopfer Architects, LLP, DAVID SCHLOSSER, individually,
WILLIAM FUEGEL ENGINEERING, P.C. And
COLLETT MECHANICAL, INC., Third-Party Defendants.




Index No. 906676-19

Brendan Wolf, Esq.
COUCH WHITE, LLP
Attorneys for Defendant/Third-Party Plaintiff
Albany Place Development, LLC
540 Broadway P.O. Box 22222
Albany, New York 12201-2222

Kevin F. Peartree, Esq.
ERNSTROM & DRESTE, LLP
Attorney for Plaintiff
LeChase Construction Services, LLC
925 Clinton Square
Rochester, New York 14604

BURKE, SCOLAMIERO & HURD, LLP
Natalie M. Weaver, Esq.
Attorneys for Third-Party Defendant
Collett Mechanical, Inc.
7 Washington Square P.O. Box 15085
Albany, New York 12212-5085

Cory J. Schoonmaker, Esq.
SUGARMAN LAW FIRM, LLP
Attorneys for Third Party Defendant
Schopfer Architects, LLP and
David Schlosser, Individually
211 W. Jefferson Street
Syracuse, New York 13202

William Fuegel Engineering, P.C.
Third-Party Defendant
109 South Warren Street
1604 State Tower Bldg
Syracuse, New York 13202 Peter A. Lynch, J.
INTRODUCTION

This is a breach of contract action, with corresponding tort claims.[FN1] Third-Party Defendant Collett Mechanical, Inc. (hereinafter "Collett") moved for partial summary judgment pursuant to CPLR 3212, dismissing third party-plaintiff's, Albany Place Development, LLC (hereinafter "Albany Place"), independent tort claim, gross negligence claim, and claim for consequential damages.[FN2] Third-Party Defendants Schopfer Architects, LLP ("Schopfer"), and [*2]David Schlosser, moved for summary judgment dismissing all claims.[FN3] Plaintiff LeChase Construction Services, LLC (hereinafter "LeChase") also moved for summary judgment to dismiss the defendant's independent tort claim, and moved for partial summary judgment on its breach of contract claim.[FN4]

It is undisputed that the relationship between the parties is contractual. The central issue, however, is whether Albany Place has an independent tort claim, distinct from the breach of contract claim.



FACTS

On March 20, 2017, defendant Schopefer, and defendant/third-party plaintiff, Albany Place, as Owner, entered into an AIA agreement, in which Schopfer agreed to serve as the architect to draw the plans for the "Conversion and renovation of the existing Best Western Sovereign Hotel, 1228 Western Avenue, Albany New York to a 200 bed NYS licensed assisted living facility."[FN5]

On October 17, 2017, Plaintiff, LeChase, as Contractor, and Defendant, Albany Place, as Owner, entered into an AIA agreement, in which LeChase agreed to renovate the premises known as University Place, previously operated as a Best Western hotel, to an assisted living facility.[FN6]

On December 4, 2017, LeChase entered a subcontract with defendant Collett, in which Collette would perform plumbing work at University Place.[FN7]

LeChase claims it performed the renovation work, and filed a Mechanics lien, claiming:

"The total agreed price and value of the labor to be performed and material to be furnished under the contract is $11,681,937.34. The total amount that has been paid to date is $11,097,840.46. The value of the work completed is $11,681,937.34. The total amount unpaid for said labor performed and material furnished is $584,096.88. The total amount for which the lien is filed is $584,096.88 plus interest from the date payment fell due."[FN8]
Thus, as initially commenced, this was a breach of contract action, in which plaintiff sought money damages.

Albany Place claims it advised LeChase, Collett, and Schopfer, that University Place had a history of Legionella in the domestic water system.[FN9] In its first counterclaim for breach of [*3]contract, Albany Place claims the work was defective, including the failure to install a required recirculating hot water riser system, properly sized pumps and mixing valve equipment and the lack of a balanced system, resulting in a Legionella outbreak at the facility.[FN10] In its second counterclaim for an independent tort arising out of the same facts, Albany Place claims,

" . . . the failure of Plaintiff LeChase and Collett to perform the Legionella prevention duties contractually required of them affects a significant public interest, giving rise to a duty of care independent of their contractual obligations, which constitutes a separate tort."[FN11]

Albany Place made the same independent tort claims against Collett and Shopfer in its third-party complaint.[FN12] Does the record support the existence of an independent tort claim, arising out of the same facts which support a breach of contract claim? It does!


STATEMENT OF LAW

Plaintiff and Third-Party defendants moved for summary judgment to dismiss Defendant/Third-Party Plaintiff's, Albany Place, independent tort and gross negligence claims, effectively as duplicative of the corresponding breach of contract claims.

In Zuckerman v. New York, 49 NY2d 557, 562 [1980], the Court identified the summary judgment review standard as follows:

To obtain summary judgment it is necessary that the movant establish his cause of action or defense 'sufficiently to warrant the court as a matter of law in directing judgment' in his favor (CPLR 3212, subd [b]), and he must do so by tender of evidentiary proof in admissible form. On the other hand, to defeat a motion for summary judgment the opposing party must 'show facts sufficient to require a trial of any issue of fact' (CPLR 3212, subd [b]). Normally if the opponent is to succeed in defeating a summary judgment motion, he, too, must make his showing by producing evidentiary proof in admissible form. The rule with respect to defeating a motion for summary judgment, however, is more flexible, for the opposing party, as contrasted with the movant, may be permitted to demonstrate acceptable excuse for his failure to meet the strict requirement of tender in admissible form. (Internal quotations and citations omitted; emphasis added).


Recognizing that summary judgment is a "drastic remedy" the "facts must be viewed in the light most favorable to the non-moving party (see Vega v Restani Constr. Corp., 18 NY3d 499, 503 [2012]) (emphasis added). The Court's function is "not to determine credibility

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LeChase Constr. Servs., LLC v. Albany Place Dev., LLC
2026 NY Slip Op 50020(U) (New York Supreme Court, Albany County, 2026)

Cite This Page — Counsel Stack

Bluebook (online)
2026 NY Slip Op 50020(U), Counsel Stack Legal Research, https://law.counselstack.com/opinion/lechase-constr-servs-llc-v-albany-place-dev-llc-nysupctalbany-2026.