L.C. Gaskins Construction Co., Inc.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 14, 2018
DocketASBCA No. 58550, 59901, 59902
StatusPublished

This text of L.C. Gaskins Construction Co., Inc. (L.C. Gaskins Construction Co., Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.C. Gaskins Construction Co., Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) L.C. Gaskins Construction Co., Inc. ) ASBCA Nos. 58550, 59901, 59902 ) Under Contract No. N69450-09-C-5068 )

APPEARANCES FOR THE APPELLANT: Dirk D. Haire, Esq. Alexa Santora, Esq. Fox Rothschild LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Ellen M. Evans, Esq. David M. Marquez, Esq. Senior Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE GOVERNMENT'S MOTION FOR RECONSIDERATION

The government timely moves for reconsideration in part of our entitlement decision of 9 June 2017. L. C. Gaskins Construction Co., Inc., ASBCA No. 58550 et al., 17-1 BCA il 36,780. The government requests the Board reconsider our entitlement decision, modify the decision to deny appellant's claims and sustain the government's claim for liquidated damages. We assume familiarity with our 9 June 2017 decision.

DISCUSSION

The Board recently reiterated our reconsideration criteria:

In a motion for reconsideration, the moving party has the burden of "demonstrat[ing] a compelling reason for the Board to modify its decision." ADT Construction Group, Inc., ASBCA No. 55358, 14-1 BCA ,I 35,508 at 174,041 (citations omitted). In particular, it must provide newly discovered evidence or demonstrate mistakes in the original decision's findings of fact or conclusions of law. · Id. A motion for reconsideration is not the place to present arguments previously made and rejected. "[W]here litigants have once battled for the court's decision, they should neither be required, nor without good reason I permitted, to battle for it again. Motions for

II reconsideration do not afford litigants the opportunity to take a "second bite at the apple" or to advance arguments that properly should have been presented in an earlier I proceeding." Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (citations omitted); see also Avant I Assessment, LLC, ASBCA No. 58867, 15-1BCA136,137 at 176,383.

Supply & Service Team GmbH, ASBCA No. 59630, 17-1 BCA 136,742 at 179,097. II The government's motion asserts six grounds for reconsideration and requests clarification on two issues. We will address each in turn. I I 1. Board's Ruling on Gaskins' Entitlement to 25 Days of Compensatory Delay I II Related to the Multiple Containment Request Resulting in Mod. P00009

Our findings established that bilateral Mod. P00009 granted Gaskins a SO-calendar-day extension related to the review and approval of Gaskins' request to construct additional containments on the hangar roof. It did not grant any compensation for the delay but Gaskins, in executing the Mod., reserved the right to II claim for more time and money. (Findings 102-03) 1 Gaskins ultimately only sought compensation for the 50-day delay granted in Mod. P00009 (com pl. 1 117). The I government asserts five reasons why we should reconsider our decision on this issue: I First, the statement that the Navy's expert, Mr. Heckman, I "did not analyze this issue" is incorrect. Second, Mr. Lowe conceded at trial that his finding of 25 days of I! compensable delay was not tied to any actual analysis. Third, Mr. Lowe did not analyze contractor delays during the time period in question. Fourth, there is no objective I evidence that supports Mr. Lowe's assumption that Gaskins would have added containments in the fall of 2010 if it had been allowed to do so by October 5, 2010. I And finally, by considering the time extension in I modification P00009 as an admission of government fault, the board followed the "presumption" set out in Robert McMullan & Son, Inc., ASBCA No. 19023, 76-1 I BCA 1 11,728 at 55,903, which was specifically overruled

II 1 Record citations are from the Board's 9 June 2017 decision. I I I 2 I I in England v. Sherman R. Smoot Corp, 388 F.3d 844, 857 (Fed. Cir. 2004) (government's grant of a contract extension does not indicate government at fault).

(Gov't mot. at 1-2)

A compensable delay is one for which both a time extension and monetary relief are due and an excusable delay is one for which only a time extension is due. ME.S., Inc., ASBCA No. 56149 eta!., 12-1 BCA ,r 34,958 at 171,857 n.3. In order to prove that it is entitled to delay damages in the form of time and/or money, Gaskins must prove that the government was responsible for specific delays, overall project completion was delayed as a result of the government-caused delays, and any government-caused delays were not concurrent with delays within Gaskins' control. Versar, Inc., ASBCA No. 56857 eta!., 12-1 BCA ,r 35,025 at 172,128. Proof of damage is also an element of entitlement and, while mathematical certainty is not required, some proof of damage is required. BAE Systems San Francisco Ship Repair, ASBCA Nos. 58810, 59642, 16-1 BCA ,r 36,404 at 177,503; Lear Siegler Services, Inc., ASBCA No. 57264, 12-2 BCA ,r 35,112 at 172,425.

Mr. Heckman 's Analysis and Mr. Lowe's Failure to Consider Concurrent Delay

The government attacks the basis for Mod. P00009 arguing it was a mistake for which there is no objective factual support in the record (gov't mot. at 9-12). Mod. P00009 was a bilateral modification executed by the contracting officer, Ms. Eckert. The government argues:

Ms. Eckert, testified there was no schedule analysis to support the time extension in this modification, but that she relied in signing it on a prior ACO's representation that 50 days of excusable delay had been agreed upon with Gaskins. She testified she disagreed with the time extension in this modification because she later learned Gaskins had failed to provide necessary information to the Navy during this 50-day time period. Tr. 8/108-112.

(Gov't mot. at 12) Despite her testimony, the fact remains that Ms. Eckert signed the bilateral modification and there is no indication she lacked the authority to bind the government or other facts that would support a finding of mistake that would render the modification void or voidable. Furthermore, this argument was raised during the hearing (gov't br. at 59), and we rejected it. The government is not permitted to reargue this position in a motion for reconsideration.

3 "McMullen presumption"

The government also attacks the legal basis for relying upon the time extension in Mod. P00009 by arguing Gaskins was obligated to prove liability, causation and resultant injury for any alleged compensable delay, and should not have been allowed to simply rely on the time extension in Mod. P00009. Consequently, our decision was in error because it relied upon the presumption that the grant of the time extension in the Mod. established the contract was in fact extended by that amount. This presumption, the government argues, incorrectly relies upon the "McMullen presumption" which was specifically overruled by England v. Smoot Corp., 388 F.3d 844, 856-57 (Fed. Cir. 2004). The government asserts that the grant of a time extension in Mod. P00009 cannot provide a legal basis for us to conclude the project was actually delayed 50 calendar days or that the government was responsible for such delay.

The government's reliance upon England v. Smoot is misplaced. That decision holds that there is no presumption of government fault where the contracting officer issues an interim (unilateral) decision regarding the extent of a government-caused delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
L.C. Gaskins Construction Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lc-gaskins-construction-co-inc-asbca-2018.