Layton v. Commissioner

11 T.C.M. 1115, 1952 Tax Ct. Memo LEXIS 35
United States Tax Court·Decided November 19, 1952·No. Docket Nos. 29968, 29969.·Unpublished

Opinion

L. O. Layton v. Commissioner. Mrs. Sammie A. Layton (Formerly Mrs. L. A. Layton) v. Commissioner.
Layton v. Commissioner
Docket Nos. 29968, 29969.
United States Tax Court
1952 Tax Ct. Memo LEXIS 35; 11 T.C.M. (CCH) 1115; T.C.M. (RIA) 52330;
November 19, 1952
Sam G. Winstead, Esq., for the petitioners. John P. Higgins, Esq., for the respondent.

JOHNSON

Memorandum Findings of Fact and Opinion

JOHNSON, Judge In these consolidated proceedings respondent has determined deficiencies in income and victory tax for the calendar year 1943 as follows:

Docket No.PetitionerDeficiency
29968L. O. Layton$21,378.27
29969Mrs. Sammie A. Layton
(Formerly Mrs. L. A.
Layton)8,617.63

The income for 1942 is also in controversy because of the provisions of the Current Tax Payment Act. The issues presented are (1) in which of two years, 1942 or 1943, was $66,990.26, the 10 per cent retained by the primary contractor, taxable to the subcontractor in the year 1943 in the amount of $7,500?

Findings of Fact

Some of the facts are stipulated and*36 are so found.

Petitioners are husband and wife and filed their separate income tax returns for the years 1942 and 1943 with the collector of internal revenue for the second district of Texas. L. O. Layton will hereinafter be referred to as the petitioner.

Issue 1.

Petitioner was a plumbing and heating contractor licensed in the State of Texas. In May 1942 petitioner entered into a contract with the prime contractor for the Longview General Hospital at Longview, Texas. Under his contract petitioner as a sub-contractor agreed to perform all of the plumbing, heating and steam work in connection with contract No. W-257-eng-1293, which was the contract between the prime contractor and the Federal Government. Petitioner began work under his contract in June 1942 and completed his work late in May or the early part of June 1943. Petitioner's original contract called for a total payment of $644,250.42, but with subsequent modifications the final contract aggregated approximately $705,000.

The contract between petitioner and the prime contractor is, in part, as follows:

"II

"Sub-Contractor further agrees to be bound to the Contractor by all the terms and conditions of the general*37 contract, plans, specifications, and addendums now issued or which shall be issued and to assume toward the Contractor all of the obligations, duties, and responsibilities that the Contractor has assumed toward the Government insofar as the equipment, material and work provided for in this contract is affected.

* * *

"VIII

"Contractor agrees to pay to the Sub-Contractor for the furnishing of equipment and material and performance of work as above set forth, the following amounts, Contract Items Nos. H-1 to H-43, inclusive: Six Hundred Forty-Four Thousand, Two Hundred and Fifty & 42/100 Dollars ($644,250.42). Said amounts to be paid promptly and on the same basis and conditions that the Contractor is paid, with the entire balance payable upon completion and acceptance and payment hereafter by the Government except that should the Government exercise its rights under Paragraph 1-45, Page I-17, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT, * * *."

The contract between the prime contractor and the Federal Government is, in part, as follows:

"ARTICLE 16. Payments to contractors. - (a) Unless otherwise provided in the specifications, partial payments will be made as the work*38 progresses at the end of each calendar month, or as soon thereafter as practicable, on estimates made and approved by the contracting officer. In preparing estimates the material delivered on the site and preparatory work done may be taken into consideration.

"(b) In making such partial payments there shall be retained 10 percent on the estimated amount until final completion and acceptance of all work covered by the contract: Provided, however, That the contracting officer, at any time after 50 percent of the work has been completed, if he finds that satisfactory progress is being made, may make any of the remaining partial payments in full: And provided further, That on completion and acceptance of each separate building, vessel, public work, or other division of the contract, on which the price is stated separately in the contract, payment may be made in full, including retained percentages thereon, less authorized deductions.

"(c) All material and work covered by partial payments made shall thereupon become the sole property of the Government, but this provision shall not be construed as relieving the contractor from the sole responsibility for all materials and work upon which*39 payments have been made or the restoration of any damaged work, or as a waiver of the right of the Government to require the fulfillment of the terms of the contract.

"(d) Upon completion and acceptance of all work required hereunder, the amount due the contractor under this contract will be paid upon the presentation of a properly executed and duly certified voucher therefor, after the contractor shall have furnished the Government with a release, if required, of all claims against the Government arising under and by virtue of this contract, other than such claims, if any, as may be specifically excepted by the contractor from the operation of the release in stated amounts to be set forth therein."

A schedule of payments to the petitioner from the prime contractor is as follows:

Date ReceivedAmount<

Free access — add to your briefcase to read the full text and ask questions with AI

Layton v. Commissioner, 11 T.C.M. 1115, 1952 Tax Ct. Memo LEXIS 35 (tax 1952).

11 T.C.M. 1115 (Layton v. Commissioner) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eckert v. Burnet
283 U.S. 140 (Supreme Court, 1931)
Spring City Foundry Co. v. Commissioner
292 U.S. 182 (Supreme Court, 1934)
Smith v. Commissioner
10 T.C. 398 (U.S. Tax Court, 1948)
Lowenstein v. Commissioner
12 T.C. 694 (U.S. Tax Court, 1949)
Schnitzer v. Commissioner
13 T.C. 43 (U.S. Tax Court, 1949)
Bihlmaier v. Commissioner
17 T.C. 620 (U.S. Tax Court, 1951)
Orino v. Commissioner
34 B.T.A. 726 (Board of Tax Appeals, 1936)
S. J. Harry Co. v. Commissioner
4 B.T.A. 211 (Board of Tax Appeals, 1926)