Lawrence M Clarke Inc v. Kim S Draeger

CourtMichigan Court of Appeals
DecidedJanuary 15, 2015
Docket316194
StatusUnpublished

This text of Lawrence M Clarke Inc v. Kim S Draeger (Lawrence M Clarke Inc v. Kim S Draeger) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lawrence M Clarke Inc v. Kim S Draeger, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

LAWRENCE M. CLARKE, INC., UNPUBLISHED January 15, 2015 Plaintiff/Counter Defendant- Appellee, V No. 316194 Ingham Circuit Court KIM S. DRAEGER, LC No. 08-000227-CZ

Defendant-Appellant, and

KD EQUIPMENT LEASING, INC. and AIC, INC.,

Defendants/Counter Plaintiffs/Third-Party Plaintiffs- Appellants,

v

GUARANTEE COMPANY OF NORTH AMERICAN USA and XL REINSURANCE AMERICA, INC.,

Third Party Defendants-Appellees.

Before: TALBOT, C.J., and CAVANAGH and M. J. KELLY, JJ.

PER CURIAM.

-1- In this contractor-subcontractor dispute, defendants, two corporations and the individual who exclusively owns and controls them,1 appeal as of right from the judgment of the circuit order awarding damages to plaintiff. We reverse and remand for further proceedings.

I. FACTS

Plaintiff was the general contractor for construction of a portion of a sanitary sewer system in Billings Township. Defendant had earlier encouraged plaintiff to bid on the project, and provided plaintiff with a unit-price proposal covering all the projected work. Plaintiff accepted the proposal and, after increasing the prices by 12 percent for its own profit, submitted it as its bid. Initially plaintiff had expected defendant, as its subcontractor, to provide all the materials and do all the work, with plaintiff contributing only some general supervision.

Defendant arranged with two subcontractors of its own to work on the project. The parties entered into a written subcontract for work to be performed by defendant in two sections of the project. Defendant and its subcontractors worked on other sections as well, but no additional subcontracts were executed. Plaintiff itself tended to some sections as well, in order to fulfill its obligations to the municipality under the general contract.

But, as the trial court summarized, “the project did not begin, progress, or end in a perfect world.” According to plaintiff s witnesses, defendant and its subcontractors provided less than perfect, competent, or complete work.

While the project was in progress, one of the corporate defendants sold its assets to the other, who then took over the project, and the proceeds of the sale were applied to an obligation for back taxes.

The evidence included copies of certificates of automatic dissolution of the two corporate defendants. The corporate owner admitted failing to pay annual corporation fees or file annual reports, but insisted that he had since achieved reinstatement of those corporations.

Plaintiff commenced action in 2008, setting forth several theories of recovery, including breach of contract and unjust enrichment. Defendants counterclaimed, alleging breach of contract and, alternatively, unjust enrichment, and initiated a third-party action for payment bond against plaintiff’s two sureties. The trial court summarized the evidence concerning deficiencies in defendant’s performance on the project, held that the individual defendant should be personally responsible for the corporate defendants’ liabilities in the matter, and awarded plaintiff over $900,000 in damages, costs, and interest. The court concluded that the question of the existence of attendant contracts, and of performance under them, was “somewhat problematic,” and elected to decide the case under the theory of quantum meruit.

1 For convenience, in light of the great identify of interest of the three defendants, except when there is a need to distinguish them they will be referred to collectively as “defendant.”

-2- On appeal, defendant argues that the trial court erred in eschewing contract law in favor of the equitable doctrine of unjust contract, or quantum meruit, in how it calculated damages, and in piercing the corporate veil. When reviewing an equitable determination reached by the trial court, this Court reviews the conclusion de novo, but reviews the supporting findings of fact for clear error. Mich Nat’l Bank & Trust Co v Morren, 194 Mich App 407, 410; 487 NW2d 784 (1992). “The applicability of a legal doctrine is a question of law,” calling for review de novo. James v Alberts, 464 Mich 12, 14; 626 NW2d 158 (2001).

II. CONTRACT OR UNJUST ENRICHMENT

Defendant argues that the trial court erred in applying the doctrine of unjust enrichment where there existed an express contract. We agree.

“ ‘A contract is a promise or a set of promises for the breach of which the law gives a remedy, or the performance of which the law in some way recognizes as a duty.’ ” Black’s Law Dictionary (6th ed, 1990), p 322, quoting Restatement Contracts, 2d, § 3. The elements of a valid contract are “parties competent to contract, a proper subject matter, a legal consideration, mutuality of agreement, and mutuality of obligation.” McInerney v Detroit Trust Co, 279 Mich 42, 46; 271 NW 545 (1937). In contrast, “[t]he elements of a claim for unjust enrichment are: (1) receipt of a benefit by the defendant from the plaintiff and (2) an inequity resulting to plaintiff because of the retention of the benefit by defendant.” Barber v SMH (US), Inc, 202 Mich App 366, 375; 509 NW2d 791 (1993). “In such instances, the law operates to imply a contract in order to prevent unjust enrichment.” Id. This theory of recovery is also variously labeled quasi-contract or contract-in-law, see Dumas v Auto Club Ins Ass’n, 437 Mich 521, 546; 473 NW2d 652 (1991), or quantum meruit, see Morris Pumps v Centerline Piping, Inc, 273 Mich App 187, 194; 729 NW2d 898 (2006).

“However, a contract will be implied only if there is no express contract covering the same subject matter. Generally, an implied contract may not be found if there is an express contract between the same parties on the same subject matter.” Id. (internal quotation marks, citations, and emphasis omitted). In this case, the trial court quoted extensively from Morris Pumps, including where this Court recited that, in earlier times, a party seeking a remedy for a breach of contract could choose between an action in contract law or an action in equity for quantum meruit, but Michigan law has evolved to where the latter is no longer available where an express contract exists. See Barber, 202 Mich App at 375. The trial court then stated as follows:

The only way to fairly dispose of this case is for the court to make a determination concerning damages based on a quantum meruit theory. Indeed, both sides during the course of trial seemed to agree that, on [defendant’s] part, it only wished to be paid for the work it performed, and on [plaintiff’s] part, it was prepared to pay [defendant] for the work it actually performed.

The parties could not figure out among themselves which party owed the other money, so they approached a trial judge that was otherwise ignorant about the transaction and gave him the authority to apply his ignorance to the hundreds of transactions that were documented during the course of the project.

-3- The court thus signaled its intention to resort to quantum meruit instead of contract law more in the matter of the election of remedies that Morris Pumps recounted was once, but no longer, available in litigation over express contracts. This is not a situation where the parties respectively pleaded in contract over part of their dealings with each other, and in unjust enrichment over other parts of those dealings. Neither party made any such distinction; each instead set forth a contract claim, then reiterated it under the rubric of unjust enrichment as an alternative. The parties’ acknowledged intention that defendant be paid for work actually performed comports with ordinary contract law, which provides for partial payment for partial performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James v. Alberts
626 N.W.2d 158 (Michigan Supreme Court, 2001)
Eerdmans v. Maki
573 N.W.2d 329 (Michigan Court of Appeals, 1998)
In Re Toler
484 N.W.2d 672 (Michigan Court of Appeals, 1992)
Barber v. Smh (Us), Inc
509 N.W.2d 791 (Michigan Court of Appeals, 1993)
Zeeland Farm Services, Inc v. Jbl Enterprises, Inc
555 N.W.2d 733 (Michigan Court of Appeals, 1996)
Parmet Homes, Inc. v. Republic Insurance
314 N.W.2d 453 (Michigan Court of Appeals, 1981)
Morris Pumps v. Centerline Piping, Inc.
729 N.W.2d 898 (Michigan Court of Appeals, 2007)
Allen v. Owens-Corning Fiberglas Corp.
571 N.W.2d 530 (Michigan Court of Appeals, 1997)
Tel-Ex Plaza, Inc. v. Hardees Restaurants, Inc.
255 N.W.2d 794 (Michigan Court of Appeals, 1977)
Berrios v. Miles, Inc
574 N.W.2d 677 (Michigan Court of Appeals, 1998)
Foodland Distributors v. Al-Naimi
559 N.W.2d 379 (Michigan Court of Appeals, 1997)
Goodwin, Inc. v. ORSON E. COE PONTIAC, INC.
233 N.W.2d 598 (Michigan Court of Appeals, 1975)
Stark v. Kent Products, Inc.
233 N.W.2d 643 (Michigan Court of Appeals, 1975)
Michigan National Bank & Trust Co. v. Morren
487 N.W.2d 784 (Michigan Court of Appeals, 1992)
Dumas v. Auto Club Ins. Ass'n
473 N.W.2d 652 (Michigan Supreme Court, 1991)
McInerney v. Detroit Trust Co.
271 N.W. 545 (Michigan Supreme Court, 1937)
Stevens v. Corbitt
33 Mich. 458 (Michigan Supreme Court, 1876)
Midwest Bridge Co. v. Department of Transportation
350 N.W.2d 913 (Michigan Court of Appeals, 1984)
Lakeview Commons Ltd. Partnership v. Empower Yourself, LLC
802 N.W.2d 712 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Lawrence M Clarke Inc v. Kim S Draeger, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawrence-m-clarke-inc-v-kim-s-draeger-michctapp-2015.