Lawrence E. Young and Judith A. Young v. Dimension Homes, Inc.

Court of Appeals of Texas·Decided August 30, 2016·No. 01-14-00331-CV·Published

Opinion

Opinion issued August 30, 2016

In The

Court of Appeals

For The

First District of Texas

quantum meruit claim; (2) there is legally and factually insufficient evidence to support the jury’s finding of $146,000 in quantum meruit damages; (3) the Youngs are entitled to a new trial because of procedural errors including (a) an untimely pleading of that claim in the alternative and (b) a finding by the jury that is inconsistent with the quantum meruit issue; (4) the trial court erred in awarding Dimension the unpaid retainage as breach of contract damages because Dimension failed to get a jury finding that the Youngs breached the contract; (5) there is legally and factually insufficient evidence supporting the jury’s findings that (a) Dimension’s failure to execute and deliver an Affidavit of Completion to the Youngs was excused, and (b) Dimension’s failure to obtain written Change Orders was excused; and (6) the trial court abused its discretion in awarding $260,417.70 in attorney’s fees, plus over $140,000 in contingent appellate fees.

We affirm the breach of contract award, reverse the quantum meruit award, and remand for further proceedings with respect to the award of attorney’s fees.

Background

The Youngs hired Dimension, a custom home builder, to build their new home in Fort Bend County. The construction contract, executed by the parties on January 15, 2007 (the Contract), obligated Dimension to “furnish all labor, services, equipment, materials, and all other facilities (the Work) for the construction of certain improvements, generally described as a private residence, Plan 9767 (the

Improvements)” on the Youngs’ property. In exchange, the Youngs agreed to pay Dimension for the cost of the Work, defined by the Contract, plus fifteen-percent of the cost of the Work.

The parties initially agreed to an overall budget amount of approximately $1,812,000. The Contract, however, expressly stated that Dimension did not “represent these budgets to be the actual cost,” and that the Youngs “acknowledge[d] and agree[d] that any overage in the budgets is the sole responsibility of the [Youngs].” The parties also agreed on a “Construction Loan Budget for building the plan with the defined specifications [which] contains detail[ed] budgets itemizing the necessary labor, material, permits, approvals, assessments, insurance, and all other costs associated with the construction of the Improvements,” which was attached to the contract. The Construction Loan Budget included two line items allocating $20,000 to pay for any “construction extras.”

The parties also included a “Change Order” provision in the Contract which required the parties to execute a Change Order for any “changes or alteration[s] to the Work” that were requested by the Youngs and approved by Dimension, and stated that any such Change Order would serve as an amendment to the Contract.

Construction on the Youngs’ home began in February 2007. Dimension’s president, Jeff Dzuik, testified that although there was a working draft of the plans and specifications when the Contract was executed, there was no final agreed set of

plans and specifications, and, in fact, many items were still left open for decision. According to Dzuik, the plans and specifications grew while the home was under construction as the Youngs made changes and added upgrades and extras. Among other things, the square footage of the house was increased, low voltage was substantially increased, the Youngs’ choice of brick was upgraded, additional HVAC added, driveway gates and openers were added, entrance columns added, countertops and appliances were upgraded, additional stone work was added and windows were upgraded. Despite the Change Order provision, the Youngs never asked Dzuik for a Change Order covering any of the modifications. Dzuik testified that he advised the Youngs of the cost impacts of their decisions and that he “did exactly what Larry Young asked [him] to do.”

Larry Young, on the other hand, testified that the Contract capped the total cost of the home at approximately $1,812,000 and that he understood that any additional costs incurred as a result of their design choices would be offset by savings elsewhere in the budget. Young testified that he learned that the original budget had been exceeded for the first time in February 2008. According to Young, he and Dzuik met that month to discuss the blown budget and, at the meeting, Young agreed to pay an additional $254,355.18, which covered the additional cost incurred up to that point, for a total of cost of $2,079,223.14 (the February Amendment).

Dzuik disagreed with Young’s interpretation of that meeting and testified that he would never have represented that the $2,079,223.14 was the total cost of the home because the home was still under construction in February 2008 and additional specifications were still being added. According to Dzuik, the Youngs made changes to the project after the parties’ February Amendment. Among other things, substantial upgrades to the interior woodwork were added, additional concrete work (flatwork) was added, upgrades to the driveway were made, additional fencing was added, the pool was expanded, additional landscaping was added, wood floors upstairs were added, and lighting fixtures were upgraded. Dzuik testified these changes caused several categories included in the original budget to be exceeded.

The Youngs closed on the home in April 2008. At the closing, Dzuik and the Youngs executed an “Owner’s and Contractor’s Affidavit” in which they averred that:

‘all of the persons, firms, and corporations . . . including the General Contractor and all sub-contractors, who have furnished services, labor, or materials, according to the plans and specifications, or extra items, used in the construction or repair of such improvements, have been paid in full, that there are no mechanics’ or materialmen’s liens against said property . . . and that such construction or repair has been fully completed and accepted by the Owner. General Contractor hereby waives and releases his right to file a mechanics’ or materialmen’s lien against the property. . . .”

It is undisputed that the Youngs paid Dimension $1,963,036.84 and that they have not paid Dimension the remaining five percent retainage of $103,317.71. Larry

Young and his counsel testified that they would have paid Dimension the retainage, if Dzuik had provided them with the documentation they were requesting. The record also includes various correspondence between the Youngs or their counsel and Dzuik in which the Youngs offered to pay Dimension if Dzuik provided a final all-bills paid affidavit and provided them with lien releases from all of the subcontractors who had worked on the Youngs’ home. At trial, the Youngs’ counsel “stipulate[d] that if [Dimension] g[a]ve [the Youngs] an affidavit of the completion executed by [Dimension], [the Youngs] will pay the $103,000-plus retainage.”

The Youngs’ position at trial was that the February Amendment fixed the final amount that they were obligated to pay under the Contract at $2,066,354.57. Dimension argued that the amendment did not cap the Youngs’ liability under the Contract, but that if it did, Dimension was entitled to recover in quantum meruit for the additional extras and upgrades that were added after the February Amendment.

Free access — add to your briefcase to read the full text and ask questions with AI

Lawrence E. Young and Judith A. Young v. Dimension Homes, Inc., (Tex. Ct. App. 2016).

Lawrence E. Young and Judith A. Young v. Dimension Homes, Inc. (Lawrence E. Young and Judith A. Young v. Dimension Homes, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Ridge Oil Co., Inc. v. Guinn Investments, Inc.
148 S.W.3d 143 (Texas Supreme Court, 2004)
Haggar Clothing Co. v. Hernandez
164 S.W.3d 386 (Texas Supreme Court, 2005)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
Intercontinental Group Partnership v. KB Home Lone Star L.P.
295 S.W.3d 650 (Texas Supreme Court, 2009)
Bank of Texas v. VR Electric, Inc.
276 S.W.3d 671 (Court of Appeals of Texas, 2008)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Sullivan v. Barnett
471 S.W.2d 39 (Texas Supreme Court, 1971)
Jernigan v. Langley
111 S.W.3d 153 (Texas Supreme Court, 2003)
Lafarge Corp. v. Wolff, Inc.
977 S.W.2d 181 (Court of Appeals of Texas, 1998)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Penhollow Custom Homes, LLC v. Kim
320 S.W.3d 366 (Court of Appeals of Texas, 2010)
Grohman v. Kahlig
318 S.W.3d 882 (Texas Supreme Court, 2010)
ASI Technologies, Inc. v. Johnson Equipment Co.
75 S.W.3d 545 (Court of Appeals of Texas, 2002)
Gill Savings Ass'n v. Chair King, Inc.
797 S.W.2d 31 (Texas Supreme Court, 1990)