Lauren Plaza Associates, Ltd. v. Gordon H. Kolb Developments, Inc.

853 F. Supp. 941, 1994 WL 197266
CourtDistrict Court, E.D. Louisiana
DecidedMay 3, 1994
DocketCiv. A. No. 91-0703
StatusPublished
Cited by3 cases

This text of 853 F. Supp. 941 (Lauren Plaza Associates, Ltd. v. Gordon H. Kolb Developments, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lauren Plaza Associates, Ltd. v. Gordon H. Kolb Developments, Inc., 853 F. Supp. 941, 1994 WL 197266 (E.D. La. 1994).

Opinion

ORDER AND REASONS

BERRIGAN, District Judge.

The court has decided on the memoranda Leon Lowe & Sons, Inc.’s, Fidelity and Deposit Company of Maryland’s, T. Byron Smith and T. Byron Smith Architects, Ltd.’s., United States Fidelity and Guaranty Company’s, and Mike McAdams Roofing Company, Inc.’s Motions for Summary Judgment. For the reasons set forth below, the motions are GRANTED.

BACKGROUND

Lauren Plaza is a shopping center in Sli-dell, Louisiana owned by plaintiff Lauren Plaza Associates (LPA).1 LPA purchased the land on which the shopping center was to be built from Gordon H. Kolb Developments, Inc. (Kolb) and contracted with Kolb to develop the site. Kolb hired T. Byron Smith and Associates (Smith Associates) to design the shopping center and Clover Contractors, Inc. (Clover) to act as general contractor. Fidelity and Deposit Company of Maryland (Fidelity) issued a performance bond for private works on behalf of Clover that named [943]*943Kolb as the obligee (ie. the beneficiary).2 Clover enlisted Leon Lowe & Sons, Inc. (Lowe) to provide fill services on the Lauren Plaza site and Mike McAdams Roofing Company, Inc. (McAdams) to provide roofing services. United States Fidelity and Guaranty Company (USF & G) is obligated to defend McAdams in this action.3

On February 15, 1991, LPA sued the developer, Kolb, and Linda and Gordon H. Kolb individually, seeking damages for alleged construction deficiencies.4 On September 23, 1991, LPA amended its complaint to add, among others, Fidelity (the surety on Clover’s construction bond), and the project architects, Smith and Associates, and T. Byron Smith (Smith), individually. On the same day, Kolb answered LPA’s suit and asserted third party claims against Fidelity, Smith and Associates, and Smith. On January 17, 1992, Fidelity filed a cross claim against Smith and Associates and Smith, individually, and a third party complaint against Lowe and McAdams. On April 21, 1992, Smith responded with cross-claims and third party claims against Fidelity, Kolb, McAdams and Lowe.

The basis for the current motions for summary judgment is that the majority of the claims arising from the construction of the shopping center have been preempted by La.R.S. 9:2772. The statute provides:

A. No action ... shall be brought ... against any person performing or furnishing the design, planning, supervision, inspection, or ... the construction of an improvement to immovable property:
(1) More than ten years after the date of registry in the mortgage office of acceptance of the work by owner; or
(2) If no such acceptance is recorded within six months from the date the owner has occupied or taken possession of the improvement, in whole or in part, more than ten years after the improvement has been thus occupied by the owner;
This peremptive period shall extend to every demand whether brought by direct action or for contribution or indemnity or by third party practice, and whether brought by the owner or by any other person....

The dispositive issue is when the peremp-tive period should begin to run. The respondents allege that the period should begin when LPA filed its notice of acceptance of the construction with St. Tammany Parish on January 21, 1982. The movants allege that LPA occupied or possessed the shopping center more than six months before it filed its notice of acceptance by allowing one of its tenants, Delchamps, to install refrigeration equipment in June 1981. Thus, they allege the peremptive period should start in June, 1981, rather than January, 1982.

ANALYSIS

Summary judgment is appropriate where “there is no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law.”5 The facts in this case are not disputed — the primary issue is whether these facts, specifically Del-champs’ installation of refrigeration equipment in June, 1981, constitute occupancy or possession under La.R.S. 9:2772.

The peremption statute does not define occupancy or possession. Using definitions of the terms that involve physical presence or control, the movants argue that by making the shopping center available to Delchamps for installation of its refrigeration equipment, LPA exercised possession or occupancy over the space.6 The respondents base their argument on the legal status of the space, as opposed to Delchamps’ physical presence. They argue that possession or occupancy of [944]*944the shopping center did not occur until the opening date of Delchamps’ lease on September 30,1981.7 They further argue that occupancy or possession should be tied to their recognition of the substantial completion of the construction, which did not occur until September 25, 1981, or that occupancy or possession is a rough equivalent of acceptance, which did not occur until January 1982.8 Finally, the respondents argue that Delchamps’ access to its space in June 1981 was simply a de minimis convenience to the tenant that did not constitute occupancy or possession.9

The legislature enacted 9:2772 in order to prevent architects and contractors from being indefinitely liable for past construction projects.10 To achieve this goal, courts have looked to the “clear and precise” provisions of the statute.11 For example, in Guidry, the plaintiff was injured when a handrail failed while he was watching a cockfight on the defendant’s premises. In determining when occupancy or possession commenced, the court placed particular emphasis on the requirement that it be “in whole or in ‘part” (emphasis added).12 The court explicitly rejected the respondents, contention that the substantial completion of construction is determinative:

Under the statute, commencement of the peremptive period does not hinge on whether the construction is fully completed or substantially completed but rather the date when occupancy begins or possession is taken.
To defer the tolling of peremption until occupancy after substantial completion or after the last work on the project was performed would directly contravene the provisions of the statute.13

Though the use of the improvement in Gui-dry tended more toward occupancy in whole than partial occupancy, the words of the statute negate the importance of the distinction.

In contrast to the respondents’ focus on the terms of the lease, definitions of occupancy and possession in other parts of Louisiana law revolve around a physical presence. For instance, the Civil Code defines possession as “the detention or enjoyment of a corporeal thing ... that one holds or exercises by himself or by another who keeps or exercises it in his name.”14 The Civil Code definition of occupancy includes “the taking of possession of a corporeal movable ...”15 Additionally, Delchamps’ lease began at roughly the same time the store opened to customers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
853 F. Supp. 941, 1994 WL 197266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lauren-plaza-associates-ltd-v-gordon-h-kolb-developments-inc-laed-1994.