Laurel Miller and Eliana Miller v. Debo Homes, LLC

CourtCourt of Appeals of Texas
DecidedSeptember 27, 2016
Docket14-15-00004-CV
StatusPublished

This text of Laurel Miller and Eliana Miller v. Debo Homes, LLC (Laurel Miller and Eliana Miller v. Debo Homes, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laurel Miller and Eliana Miller v. Debo Homes, LLC, (Tex. Ct. App. 2016).

Opinion

Affirmed in Part, Reversed and Remanded in Part, and Memorandum Opinion filed September 27, 2016.

In The

Fourteenth Court of Appeals

NO. 14-15-00004-CV

LAUREL MILLER AND ELIANA MILLER, Appellants/Cross-Appellees V. DEBO HOMES, LLC, Appellee/Cross-Appellant

On Appeal from the 400th District Court Fort Bend County, Texas Trial Court Cause No. 13-DCV-209822

MEMORANDUM OPINION

Laurel and Eliana Miller appeal the trial court’s denial of their motion for judgment notwithstanding the verdict and motion for new trial following a jury trial. They contend the jury’s award of zero attorney’s fees was improper and not supported by evidence. Debo Homes, LLC cross-appeals to challenge the trial court’s judgment on grounds that (1) there is no evidence to support the jury’s finding of a violation of the Deceptive Trade Practices Act (DTPA); and (2) the trial court erroneously awarded the Millers pre- judgment and post-judgment interest. We affirm the trial court’s judgment in part with respect to the Millers’ DTPA claim and reverse and remand in part with respect to the trial court’s award of zero attorney’s fees and the trial court’s award of pre-judgment and post- judgment interest.

BACKGROUND

Debo Homes contracted with Laurel and her daughter Eliana in April 2013 to build a house for them in Needville, Texas. The parties agreed the Millers would pay $178,000 in three cash installments: one-third was to be paid up front, one-third was to be paid when the house was ready for drywall installation, and one-third was to be paid when the house was completed.

The Millers had several meetings with Debo Homes salesman Kris Dominguez regarding the house’s specifications before signing the construction contract. Construction began in April 2013, after the Millers made their first $60,3001 cash payment. Laurel soon became concerned about the construction quality after she noticed broken or cracked boards and beams in the framing; pipes and vents that were not connected; uneven beams; “cracked things;” “wood just floating;” and other “things that didn’t look right.” Laurel hired a home inspector because she was “uncomfortable with what [she] saw.”

The inspector visited the construction site on May 9, 2013, and wrote a report describing the things that needed to be fixed in the home. Laurel met with Dominguez and gave him the inspector’s report. According to Laurel, Dominguez told her: “We’re going to fix some things. We’re not going to fix everything.” Soon thereafter, Dominguez told Laurel that Debo Homes wanted to start installing the drywall and asked for the next installment payment of $59,300; Laurel told Dominguez that she was not going to make another payment until the problems with the home were fixed.

Laurel scheduled a second inspection on May 13, 2013, during which the inspector

1 The $60,300 payment was for the first installment of $59,300 and for $1,000 in earnest money.

2 discovered additional problems with the home. Dominguez informed Laurel that Debo Homes would start installing drywall in the home on May 14, 2013. The Millers wanted construction to stop until repairs were completed. The Millers sent an email to Dominguez outlining the repairs they wanted and informing Debo Homes that they would make no payment until all repairs were made. The Millers also hired attorney Brian Crockett, who sent an email to Debo Homes on May 22, 2013. The email said the Millers retained him to investigate whether their home was being constructed in accordance with the contract and asked Debo Homes to stop further construction on the home to “ensure that any defects have been corrected prior to continued building.” After receiving Crockett’s email, Debo Homes stopped construction of the home for approximately three weeks.

Debo Homes sent the Millers a letter on May 29, 2013, stating that (1) Debo Homes “fixed the minor issues [the Millers’ inspector] requested;” and (2) “[i]f you are not happy with our service, you are free to terminate the contract with Debo Homes and we will refund you 100% of the money you have given us after we sell the house.” According to Laurel, the Millers “gave [Debo Homes] 90 days to sell the house” and “tried to work it out that it would happen within 90 days,” but the Millers “never heard anything back from [Debo Homes] until [they] got a letter from [Debo Homes’s] attorney.”

Debo Homes resumed construction in June 2013, and the house was completed in July 2013. According to Debo Homes, all problems identified by the inspector were repaired.

Debo Homes, through its attorney, sent a letter to the Millers on August 30, 2013, stating that (1) the Millers breached their contract with Debo Homes; and (2) if Debo Homes “is able to sell the home for at least $178,000.00, the sum your client agreed to pay plus all attorney[’]s fees, broker[’]s fees, interest paid, cost of necessary alterations to make the home marketable, and other expenses associated with mitigation of the damages, she may receive a reimbursement of the amount she paid to him . . . [a]ny diminution of

3 the amount that the home sells for will be directly reflected in the reimbursement.”

The Millers sued Debo Homes on October 7, 2013, alleging fraud and fraudulent inducement to contract, fraud in a real estate transaction, DTPA violations, and breach of contract. Debo Homes filed its original answer and counterclaim on November 13, 2013, alleging an affirmative defense of fraud, an affirmative defense of failure of consideration, and breach of contract as a counterclaim.

Debo Homes sold the house for $168,000 on October 19, 2013, and closed on the sale on December 31, 2013.

Debo Homes deposited $60,300 into the court’s registry on August 14, 2014. A jury trial began five days later and concluded on August 22, 2014. The jury (1) answered “No” to questions asking whether Debo Homes or the Millers breached the contract; (2) found that Debo Homes engaged in a “false, misleading, or deceptive act or practice;” (3) awarded the Millers $60,650 in compensatory damages; and (4) awarded zero dollars for attorney’s fees. The compensatory damages consisted of $1,000 paid by the Millers as earnest money, $59,300 paid as an installment payment, and $350 paid for fixtures.

The Millers filed a motion for judgment notwithstanding the verdict on September 10, 2014. Debo Homes filed a motion to disregard the jury’s answer to Question No. 1 on September 23, 2014. The trial court denied both motions on September 29, 2014. The Millers filed a motion for new trial on September 30, 2014, which the trial court denied on October 20, 2014.

On December 22, 2014, the trial court signed a final judgment in accordance with the jury’s verdict and also awarded the Millers pre-judgment and post-judgment interest. The Millers filed a timely notice of appeal on December 31, 2014, and Debo Homes timely filed its notice of cross-appeal on January 21, 2015.

4 ANALYSIS

I. Debo Homes’s Appeal

We first address the issues Debo Homes raises in its cross-appeal before turning to the issues the Millers raise in their appeal.

A. DTPA Claim

Debo Homes argues in its first issue that (1) there is no evidence its alleged representations were false; and (2) the assertedly false representations were non-actionable puffery.

The jury was asked to answer the following question regarding the Millers’ DTPA claim:

QUESTION 1: Did Debo [Homes] engage in any false, misleading, or deceptive act or practice that the Millers relied on to their detriment and that was a producing cause of damages to the Millers? “Producing cause” means a cause that was a substantial factor in bringing about the damages, if any, and without which the damages would not have occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Farm Life Insurance Co. v. Martinez
216 S.W.3d 799 (Texas Supreme Court, 2007)
Smith v. Patrick W.Y. Tam Trust
296 S.W.3d 545 (Texas Supreme Court, 2009)
Wal-Mart Stores, Inc. v. Miller
102 S.W.3d 706 (Texas Supreme Court, 2003)
Miga v. Jensen
96 S.W.3d 207 (Texas Supreme Court, 2002)
Tiller v. McLure
121 S.W.3d 709 (Texas Supreme Court, 2003)
Ragsdale v. Progressive Voters League
801 S.W.2d 880 (Texas Supreme Court, 1990)
Sellers v. Harris County
483 S.W.2d 242 (Texas Supreme Court, 1972)
Lee v. Lee
47 S.W.3d 767 (Court of Appeals of Texas, 2001)
Pegasus Energy Group, Inc. v. Cheyenne Petroleum Co.
3 S.W.3d 112 (Court of Appeals of Texas, 1999)
Johnson & Higgins of Texas, Inc. v. Kenneco Energy, Inc.
962 S.W.2d 507 (Texas Supreme Court, 1998)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Browning Oil Co., Inc. v. Luecke
38 S.W.3d 625 (Court of Appeals of Texas, 2000)
Rosenblatt v. Freedom Life Insurance Co. of America
240 S.W.3d 315 (Court of Appeals of Texas, 2007)
Britton v. Texas Department of Criminal Justice
95 S.W.3d 676 (Court of Appeals of Texas, 2002)
Cale's Clean Scene Carwash, Inc. v. Hubbard
76 S.W.3d 784 (Court of Appeals of Texas, 2002)
Brainard v. Trinity Universal Insurance Co.
216 S.W.3d 809 (Texas Supreme Court, 2006)
Walling v. Metcalfe
863 S.W.2d 56 (Texas Supreme Court, 1993)
Bocquet v. Herring
972 S.W.2d 19 (Texas Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Laurel Miller and Eliana Miller v. Debo Homes, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laurel-miller-and-eliana-miller-v-debo-homes-llc-texapp-2016.