Laurel Construction Co. v. Paintsville Utility Commission

336 S.W.3d 903, 2010 WL 568934
CourtCourt of Appeals of Kentucky
DecidedMay 28, 2010
Docket2009-CA-000845-MR
StatusPublished
Cited by2 cases

This text of 336 S.W.3d 903 (Laurel Construction Co. v. Paintsville Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laurel Construction Co. v. Paintsville Utility Commission, 336 S.W.3d 903, 2010 WL 568934 (Ky. Ct. App. 2010).

Opinion

OPINION

DIXON, Judge.

Appellant, Laurel Construction Company (Laurel Construction), appeals from an order of the Johnson Circuit Court granting summary judgment in favor of Appel-lee, Paintsville Utility Commission. Finding no error, we affirm.

*905 The Paintsville Utility Commission (Commission) is a municipal entity that operates the water, sewer and gas services in Johnson and Lawrence Counties. In February 2007, the Commission entered into a grant assistance agreement with the Kentucky Infrastructure Authority (KIA) to help fund the construction of a new water tank in Johnson County. Section 3 of the grant agreement provided, in relevant part:

B. The [Commission] shall perform and/or cause to be performed all necessary acts (consistent with KRS 45A and in accordance with applicable laws) to plan, design and construct the Project including: the procurement of land, easements and rights of way; professional services, including but not limited to architectural and engineering services; construction contractor(s); and equipment and/or materials.

The grant money was part of the multi-county coal severance funding provided for in the' Kentucky state budget. The remaining funding for the water tank project was to come from the Commission’s general fund.

The Commission thereafter hired Sisler-Maggard Engineering, PLLC, as the design engineers for the project. Joe Sisler served as consultant and design engineer. After the project design was complete, the Commission posted an advertisement soliciting sealed bids for a water tank construction project. The bid documents described the project as the construction of a 100,000-gallon “[s]tandpipe water tank including access road, site grading, fencing, electrical service, telemetry, yard piping and miscellaneous appurtenances.” The bids were to be accepted until. November 15, 2007, on which date the bids would be publically opened and read.

On November 15, 2007, the Commission unsealed the two submitted bids for the project at a public meeting: Laurel Construction submitted a bid of $194,000 to construct a welded-steel, paint-lined water tank. Kentucky Glass Lined Tanks submitted a bid of $228,491 to construct a glass-lined tank.

On November 19, 2007, the Commission received a letter from Sisler advising, “We have made an investigation and evaluation of the 2(two) low bidders and we are familiar with both contractors. Both contractors are competent to perform the work. However, in conjunction with our discussions with the Paintsville Utilities staff, we would recommend as follows: ... KY Glass Lined Tank Systems, Inc.” At a December 12, 2007 Commission meeting, the project was formally awarded to Kentucky Glass Lined Tanks.

On April 3, 2008, Laurel Construction filed an action in the Johnson Circuit Court against the Commission alleging that the Commission’s rejection of Laurel’s bid violated KRS Chapter 45A, Kentucky’s Model Procurement Code (KMPC), and Section 2 of the Kentucky Constitution. Following discovery, both parties filed motions for summary judgment. On April 27, 2009, the trial court granted summary judgment in favor of the Commission and dismissed the case with prejudice. This appeal ensued. Additional facts are éet forth as necessary.

On appeal, Laurel Construction argues that the trial court erred by granting summary judgment in favor of the Commission and should have, in fact, granted summary judgment in favor of Laurel Construction as to the application and violation of the KMPC. Laurel Construction further contends that notwithstanding the applicability of the KMPC, the Commission’s decision was arbitrary and not supported by findings of fact. Finally, Laurel Construction argues that the trial court erred in *906 finding that it failed to exhaust its administrative remedies.

Summary judgment serves to terminate litigation when there is no issue of material fact and the moving party is entitled to summary judgment as a matter of law. Kentucky Rules of Civil Procedure (CR) 56. On a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party, and summary judgment should be granted only if it appears impossible that the nonmoving party will be able to produce evidence at trial warranting a judgment in his favor. Steelvest, Inc. v. Scansteel Service Center, Inc., 807 S.W.2d 476, 480 (Ky.1991). Summary judgment “is only proper where the movant shows that the adverse party could not prevail under any circumstances.” Id, (Citing Paintsville Hospital. Co. v. Rose, 683 S.W.2d 255 (Ky.1985)).

The standard of review on appeal when a trial court grants a motion for summary judgment is “whether the trial court correctly found that there were no genuine issues as to any material fact and that the moving party was entitled to judgment as a matter of law.” Scifres v. Kraft, 916 S.W.2d 779, 781 (Ky.App.1996). Because summary judgment involves only legal questions and the existence of any disputed material issues of fact, an appellate court need not defer to the trial court’s decision and will review the issue de novo. Lewis v. B & R Corporation, 56 S.W.3d 432, 436 (Ky.App.2001) (internal footnotes and citations omitted). See also Goldsmith v. Allied Building Components, Inc., 833 S.W.2d 378, 381 (Ky.1992).

The KMPC, Chapter 45A, was enacted by the legislature in 1978 and became effective on January 1, 1979. Its stated purposes are:

(a) To simplify, clarify, and modernize the law governing purchasing by the Commonwealth;
(b) To permit the continued development of purchasing policies and practices;
(c) To make as consistent as possible the purchasing laws among the various states;
(d) To provide for increased public confidence in the procedures followed in public procurement;
(e) To' insure the fair and equitable treatment of all persons who deal with the procurement system of the Commonwealth;
(f) To provide increased economy in state procurement activities by fostering effective competition; and
(g) To provide safeguards for the maintenance of a procurement system of quality and integrity.

KRS 45A.010(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rmi, Inc. v. City of Leitchfield, Kentucky
Court of Appeals of Kentucky, 2024

Cite This Page — Counsel Stack

Bluebook (online)
336 S.W.3d 903, 2010 WL 568934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laurel-construction-co-v-paintsville-utility-commission-kyctapp-2010.