Latham Land I, LLC v. TGI Friday's, Inc.

96 A.D.3d 1327, 948 N.Y.S.2d 147

This text of 96 A.D.3d 1327 (Latham Land I, LLC v. TGI Friday's, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Latham Land I, LLC v. TGI Friday's, Inc., 96 A.D.3d 1327, 948 N.Y.S.2d 147 (N.Y. Ct. App. 2012).

Opinion

Spain, J.

Cross appeals from a judgment of the Supreme Court (Platkin, J.), entered February 3, 2011 in Albany County, upon a decision of the court in favor of defendant.

Plaintiff commenced this action alleging that defendant breached a May 24, 2007 contract whereby defendant, as lessee, agreed to, among other things, build and operate a restaurant on a portion of plaintiffs real property in the Town of Colonie, Albany County (hereinafter the contract). The contract contemplated an initial lease term of 10 years, with five-year renewal options and, at the end of the lease, that plaintiff would take ownership of the building. Defendant, however, never commenced construction and instead, in March 2008, notified plaintiff that it was terminating the contract. Thereafter, plaintiff commenced this action and, after failing to find another tenant, ultimately sold to a third party both the property designated to be leased to defendant and an adjacent parcel improved by a lease with Chipotle Mexican Grill of Colorado, LLC.1 During a nonjury trial, plaintiff submitted evidence of damages based on the difference between the estimated value of the property had defendant performed under the contract, and the actual sale price that plaintiff received for the land alone. [1328]*1328Supreme Court held that defendant had breached the contract but, finding that plaintiff had failed to establish damages, dismissed the action. The parties now cross-appeal.

We concur with Supreme Court that defendant breached the contract. The contract contemplated a time line by which the parties would simultaneously make efforts to procure the necessary approvals to proceed with the project. Specifically, plaintiff agreed to seek site plan approval at the same time that defendant would “diligently pursue” its obligation to obtain the necessary building permits. Section 2.07 (a) of the contract required defendant to submit its building plans and specifications to plaintiff for approval “no later than” 90 days after its receipt from plaintiff of, among other things, written notice that a meeting between plaintiff and the Town of Colonie’s Development Coordination Committee (hereinafter DCC meeting) had occurred. After plaintiff approved its building plans, defendant then had 10 days to apply for its building permits. Although the DCC meeting occurred in July 2007, plaintiff did not then send written notice to defendant. Supreme Court found, however, that defendant had actual notice that the DCC meeting had occurred no later than the end of August 2007. Nevertheless, defendant did not submit building plans to plaintiff. By late 2007, defendant was experiencing financial difficulties and began negotiations with plaintiff to modify and postpone the contract, but the parties did not reach any new agreement and, on February 28, 2008, plaintiff sent formal written notice of the DCC meeting to defendant.

On March 24, 2008, defendant informed plaintiff that it was terminating the contract pursuant to section 2.08 (e), which provides that either party may terminate the contract if, despite the exercise of due diligence, defendant had been unable to satisfy a set of enumerated conditions — including obtaining necessary building permits — within one year from the date the contract was executed. May 24, 2008 represented the end of the one-year period and defendant terminated the lease in March 2008, two months prior to that date, arguing that plaintiffs delay in sending written notice of the DCC meeting left defendant with insufficient time within which to obtain building permits prior to the May 24, 2008 deadline.

The record amply supports Supreme Court’s finding that plaintiff substantially complied with its obligation to notify defendant of the DCC meeting in August 2007, triggering defendant’s obligation to submit building plans thereafter. Defendant’s director of development, who was the individual who negotiated for the language regarding the DCC meeting to be included in [1329]*1329the contract, was copied in a series of e-mails between plaintiff and defendant in late August 2007 indicating that the DCC meeting had occurred. One of defendant's design project managers in its architectural department was also included in these e-mails. Hence, although plaintiff never sent formal written notice of the DCC meeting as set forth in the contract, the record supports the court’s conclusion that defendant had actual notice by the end of August 2007. Further, evidence at trial indicated that, at defendant’s urging, the parties had engaged in unsuccessful negotiations to delay defendant’s performance until 2009. In addition, plaintiff submitted uncontradicted testimony that defendant made little perceivable effort to finalize building plans or apply for building permits. According appropriate deference to the trial court’s credibility determinations (see Richmor Aviation, Inc. v Sportsflight Air, Inc., 82 AD3d 1423, 1424 [2011]), we hold that plaintiff substantially complied with the requirements of section 2.07 (a) and that defendant thereafter breached the contract by terminating the contract rather than making diligent efforts to complete building plans and acquire permits.

Defendant contends, nevertheless, that section 2.07 (a)— “[t]enant shall submit its plans and specifications to Landlord for approval no later than ninety (90) days after (i) Landlord sends written notice” — constituted a condition precedent to its obligation to submit building plans and, as such, had to be “literally performed” as opposed to being satisfied by substantial compliance (Oppenheimer & Co. v Oppenheim, Appel, Dixon & Co., 86 NY2d 685, 690 [1995]). Because plaintiff failed to send written notice until February 28, 2008, defendant argues that it had until after the May 24, 2008 deadline (i.e., May 28, 2008) to tender its plans, hence triggering the option to terminate the contract pursuant to section 2.08 (e) of the lease. We do not agree. “A condition precedent is ‘an act or event, other than a lapse of time, which, unless the condition is excused, must occur before a duty to perform a promise in the agreement arises’ ” (Oppenheimer & Co. v Oppenheim, Appel, Dixon & Co., 86 NY2d at 690, quoting Calamari and Perillo, Contracts § 11-2, at 438 [3d ed] [citations omitted]; accord MHR Capital Partners LP v Presstek, Inc., 12 NY3d 640, 645 [2009]). Notably, section 2.07 (a) does not employ clearly conditional terms such as “if,” “unless” or “until” (MHR Capital Partners LP v Presstek, Inc., 12 NY3d at 645; see Oppenheimer & Co. v Oppenheim, Appel, Dixon & Co., 86 NY2d at 691; Restaurant Creative Concepts Mgt., LLC v Northeast Rest. Dev., LLC, 83 AD3d 1189, 1191 [2011]; Su Mei, Inc. v Kudo, 302 AD2d 740, 741 [2003]). Further, read in the context of the parties’ contract as a whole, it is clear that [1330]*1330the parties contemplated reciprocal good faith efforts to move the project forward, and this specific notice provision was intended as a means to impose a time limit on defendant’s performance, rather than a basis for conditioning that performance. Thus, Supreme Court properly held that written notice of the DCC meeting was not a condition precedent to defendant’s obligation to submit building plans and specifications to plaintiff, but rather that the language created a constructive condition, which could be — and was here — satisfied by substantial compliance (see Oppenheimer & Co. v Oppenheim, Appel, Dixon & Co., 86 NY2d at 691; Restaurant Creative Concepts Mgt., LLC v Northeast Rest. Dev., LLC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co.
660 N.E.2d 415 (New York Court of Appeals, 1995)
J. R. Loftus, Inc. v. White
649 N.E.2d 1196 (New York Court of Appeals, 1995)
Bi-Economy Market, Inc. v. Harleysville Insurance
886 N.E.2d 127 (New York Court of Appeals, 2008)
First National Mortgage Co. v. Federal Realty Investment Trust
633 F. Supp. 2d 985 (N.D. California, 2009)
American List Corp. v. U.S. News & World Report, Inc.
549 N.E.2d 1161 (New York Court of Appeals, 1989)
Imperial Water Co. v. Cameron
228 P. 678 (California Court of Appeal, 1924)
MHR Capital Partners LP v. Presstek, Inc.
912 N.E.2d 43 (New York Court of Appeals, 2009)
Simon v. Electrospace Corp.
269 N.E.2d 21 (New York Court of Appeals, 1971)
Kenford Co. v. County of Erie
493 N.E.2d 234 (New York Court of Appeals, 1986)
Kenford Co. v. County of Erie
537 N.E.2d 176 (New York Court of Appeals, 1989)
Appliance Giant, Inc. v. Columbia 90 Associates, LLC
8 A.D.3d 932 (Appellate Division of the Supreme Court of New York, 2004)
Rooney v. Slomowitz
11 A.D.3d 864 (Appellate Division of the Supreme Court of New York, 2004)
Richmor Aviation, Inc. v. Sportsflight Air, Inc.
82 A.D.3d 1423 (Appellate Division of the Supreme Court of New York, 2011)
Restaurant Creative Concepts Management, LLC v. Northeast Restaurant Development, LLC
83 A.D.3d 1189 (Appellate Division of the Supreme Court of New York, 2011)
Su Mei, Inc. v. Kudo
302 A.D.2d 740 (Appellate Division of the Supreme Court of New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
96 A.D.3d 1327, 948 N.Y.S.2d 147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/latham-land-i-llc-v-tgi-fridays-inc-nyappdiv-2012.