LaShip, L.L.C. v. Jamestown Metal and Marine Sales, Inc.

District Court, E.D. Louisiana·Decided May 23, 2025·No. 2:23-cv-06815·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

LASHIP, LLC AND RIVER 1, LLC CIVIL ACTION

VERSUS No. 23-6815

JAMESTOWN METAL MARINE SECTION: “J”(3) SALES, INC.

ORDER & REASONS Before the Court are Plaintiffs, LaShip, LLC (“LaShip”) and River 1 LLC (“River 1”)’s, Motion for Partial Summary Judgment (Rec. Roc. 85), Defendant, Jamestown Metal and Marine Sales, Inc. (“Jamestown”)’s, opposition (Rec. Doc. 102), and a reply (Rec. Doc. 107). Plaintiffs seek partial summary judgment on various counterclaims brought by Jamestown. Having considered the motion and legal memoranda, the record, and applicable law, the Court finds that the motion should be GRANTED IN PART as to Counterclaim Ten–Unjust Enrichment and DENIED IN PART. FACTS AND PROCEDURAL BACKGROUND Buying a car means driving off the lot with confidence; building a vessel means finally setting sail—only to discover the ‘finished’ product is still a work in progress. This litigation arises out of a dispute related to the construction of the vessel Viking Mississippi, a luxury cruise vessel navigating the Mississippi River. The dispute is between the shipbuilder, LaShip, and one of many subcontractors, Jamestown. The Viking Mississippi is owned by River 1. 1 In January 2020, River 1 entered into a Time Charter Party (Rec. Doc. 85-4) with Viking USA, LLC (“Viking”), to charter a luxury cruise liner. It provided that River 1 was to deliver the vessel in July 2022, but did provide for “permissible delays.”

The Time Charter also provided a bonus to River 1 for early delivery of the vessel by April 13, 2022; however, to be eligible for the early delivery bonus, River 1 had to notify Viking by October 15, 2021, of its intent to delivery the vessel early. River 1 then executed a Vessel Construction Contract with LaShip to construct the vessel, which required delivery in July 2022. (Rec. Doc. 85-2, at 1). On January 17, 2020, Jamestown submitted a bid (Rec. Doc. 85-5) to supply

and install the vessel’s passenger cabins and certain public spaces aboard. Jamestown’s bid was based, in part, on the delivery date of June 2022. In February or March 2020, LaShip accepted Jamestown’s bid when it issued a purchase order. Construction of the vessel began, but not without significant setbacks. The project experienced delays—Hurricanes Marco, Laura, Delta, and Zeta; the February 2021 Winter Storm Uri; the COVID 19 pandemic and its impacts; and Hurricane Ida—resulting in a total of 71 days of “permissible delays” under the Charter Party’s

force majeure provision. (Rec. Doc. 85-10, at 5). In September 2021, LaShip, with its eye on the early delivery bonus, communicated to Jamestown that it wanted to achieve a March 2022 delivery date. Acceleration efforts began with no formal agreement between LaShip and Jamestown on accelerating construction or on-time performance at a higher price.

2 On October 4, 2021, River 1, hoping to earn the early delivery bonus, provided Viking the required notice of River 1’s intent to deliver the vessel early on April 11, 2022, two days before the contractual early delivery date of April 13, 2022. However,

on October 30, 2021, River 1 asserted its contractual rights under the Charter Party in a letter to Viking and claimed the 71 days of “permissible delays.” This contractually changed the delivery date from July 2022 to September 22, 2022. (Rec. Doc. 85-10). This in turn adjusted the early delivery date from April 13, 2022 to June 23, 2022.

The vessel was not delivered by the early delivery date of June 23, 2022. River 1 lost its right to the early delivery bonus. In August 2022, LaShip attempted delivery of the vessel to Viking before the contractual delivery date of September 22, 2022. When the vessel arrived in New Orleans, though, deficiencies remained and it was decided to deliver the vessel on

September 3, 2022, in St. Paul, Minnesota. Between the attempted first delivery in August and the final delivery on September 3rd, it was all hands on deck, as crews from both Jamestown and LaShip were aboard completing outstanding or deficient work. On September 3, 2022, River 1 delivered the vessel to Viking in St. Paul.

Numerous defects with the passenger cabins were revealed when passengers came onboard during the first few cruises and reported issues such as the shower drains not working, lighting in cabins not working, and other various issues. 3 Following the delivery of the vessel, LaShip and Jamestown asserted various claims against one another related to the project. Jamestown claimed amounts owed on unpaid invoices, unpaid change order work, and on acceleration costs. (Rec. Docs.

85-19, 102-8). Whereas LaShip issued its invoices to Jamestown asserting amounts owed for completing Jamestown’s work during the project; to provide housing for Jamestown’s employees; and to remedy deficiencies discovered in Jamestown’s work. (Rec. Doc. 85-1, at 10). Additionally, on August 22, 2024 (after the filing of suit), Jamestown submitted to LaShip change order requests and project impact change orders for productivity losses and expenses based on LaShip’s breach of contract.1

(Rec. Doc. 85-1, at 11). On September 6, 2023, LaShip and River 1 filed suit against Jamestown for breach of contract and negligence in Terrebonne Parish state court. Jamestown was served on October 23, 2023. In November 2023, Jamestown removed to the Eastern District of Louisiana.

In August 2024, Jamestown filed a Motion to Dismiss Plaintiffs’ Negligence Claims (Rec. Doc. 18) on grounds of prescription, which the Court denied without prejudice, permitting Plaintiffs to file an amended complaint. (Rec. Doc. 31). Plaintiffs filed their amended complaint; Defendants did not re-assert their motion to dismiss.

1 The Court notes that Jamestown disputes that it asserted such change order requests on August 22, 2024. Jamestown asserts that such claims were asserted in its pleadings, “starting with Jamestown’s Notice of Removal [Rec. Doc. 1], and thereafter, further defined in Jamestown’s Original Answer, Affirmative Defense and Counterclaims [Rec. Doc. 5].” (Rec. Doc. 102, at 8). 4 Jamestown filed a Motion for Summary Judgment seeking dismissal with prejudice of River 1 and LaShip’s damages for reputational harm. (Rec. Doc. 75). The Court granted the motion, in part, relating to the dismissal of River 1, because “River

1 [did] not oppose its dismissal” (Rec. Doc. 93, at 1). (Rec. Doc. 105). The Court denied the motion as moot, relating to LaShip’s reputational harm damages, because “LaShip [had] now disclaimed seeking reputational harm damages,” (Rec. Doc. 93, at 1). Id. Presently before the Court is LaShip’s Motion for Partial Summary Judgment.

(Rec. Doc. 85). LEGAL STANDARD Summary judgment is appropriate when “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.”

Free access — add to your briefcase to read the full text and ask questions with AI

LaShip, L.L.C. v. Jamestown Metal and Marine Sales, Inc., (E.D. La. 2025).

LaShip, L.L.C. v. Jamestown Metal and Marine Sales, Inc. (LaShip, L.L.C. v. Jamestown Metal and Marine Sales, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
T L James & Co Inc v. Traylor Bros Inc
294 F.3d 743 (Fifth Circuit, 2002)
Allan E. Amundson, Inc. v. Hoppmeyer
442 So. 2d 1254 (Louisiana Court of Appeal, 1983)
Tri-Parish Electrical Supply, Inc. v. Cypress Bend Investments, LLC
105 So. 3d 1036 (Louisiana Court of Appeal, 2012)
Benton v. Clay
123 So. 3d 212 (Louisiana Court of Appeal, 2013)
Semco, LLC v. Grand Ltd.
221 So. 3d 1004 (Louisiana Court of Appeal, 2017)
Gerald v. Doucette & Associated Contractors, Inc.
229 So. 3d 667 (Louisiana Court of Appeal, 2017)
L.G.W., Inc. v. Darcy P
496 So. 2d 384 (Louisiana Court of Appeal, 1986)