LEVINE, Justice.

Twelve downstream landowners and the Heimdal Township Board [hereinafter collectively referred to as appellants] appeal from a district court judgment affirming a Wells County Water Resource Board [Board] decision approving a drain permit for the Heimdal Drain Project. We affirm.

In December 1979, several landowners petitioned the Board to establish the Heim-dal Drain Project as an assessment drain pursuant to Section 61-21-10, North Dakota Century Code. Subsequently, the Board issued an order establishing an assessment drain known as Heimdal Drain A and B. The Heimdal Drain Project was designed to provide drainage for approximately 3,600 acres of land in Wells County into the Heimdal Slough, which is part of a water course which flows into a reservoir known as the Big Slough which, in turn, flows into the James River.

On June 9, 1981, and after the time for appeal from the decision establishing the assessment drain had expired, the Board submitted an application to the North Dakota State Water Commission for a drain permit for the Heimdal Drain pursuant to Section 61-01-22, N.D.C.C. 1 The State Engineer determined the application to be of statewide significance and referred the application to the Board for a public hearing.

After notice to all affected landowners, the Board held a public hearing on July 9, 1981. Several downstream landowners appeared at that hearing and opposed the application. Among the concerns expressed at the hearing were: (1) the possibility of flooding downstream land; (2) the effect on the Heimdal lagoon and water supply; (3) the adverse impact on township roads; (4) the possibility of running the drain south rather than north; (5) the control of culverts feeding into the drain; and (6) the outlet of the Big Slough into the James River.

The Board requested an engineer to investigate the effect of the drain on the Heimdal lagoon and water supply, and the possibility of running the drain south rather than north. The engineer responded by letter dated July 15, 1981, that it would not be economically feasible to route the drain south and that there would be little effect on the lagoon and water supply. The Board met on August 21, 1981, to consider the application and thereafter forwarded the application to the State Engineer.

The State Engineer conducted an independent engineering analysis of the proposed project and, subject to certain conditions, approved the drain permit application. The conditions included acquiring flowage easements for certain downstream land, installing gates on the downstream end of certain culverts to control the flow of water and protect downstream lands, and improving an outlet into the Big Slough to handle 350 cubic feet of water per second without causing an adverse impact on adjacent land. On March 17, 1982, the Board approved the permit with the conditions prescribed by the State Engineer. The appellants appealed that decision to the district court, and, after concluding that the Board’s decision was not arbitrary, oppressive, or unreasonable, the district court affirmed that decision.

On appeal the appellants contend that the permit was invalid because flowage easements over downstream lands were not *482 obtained before the permit was granted, as required by Section 61-16.1-41, N.D.C.C. (see fn. 1). The appellants contend that the language of that statute is mandatory.

The Board counters that the drain permit was contingent upon obtaining the necessary easements, and, thus, satisfies the statutory requirements of Section 61-16.1-41, N.D.C.C.

That section provides, in relevant part:

“61-16.1-41. Permit to drain waters required — Penalty. Any person, before draining water from a pond, slough, or lake, or any series thereof, which drains an area comprising eighty acres [32.37 hectares] or more, shall first secure a permit to do so. The permit application shall be submitted to the state engineer. The state engineer shall refer the application to the water resource district or districts within which is found a majority of the watershed or drainage area of the pond, slough, or lake for consideration and approval, but the state engineer may require that applications proposing drainage of statewide or interdistrict significance be returned to him for final approval. A permit shall not be granted until an investigation discloses that the quantity of water which will be drained from the pond, slough, or lake, or any series thereof, will not flood or adversely affect downstream lands. In addition, consideration shall be given to the state water resources policy set forth in section 61-01-26. If the investigation shows that the proposed drainage will flood or adversely affect lands of downstream landowners, the water resource board shall not issue a permit until flowage easements are obtained. [Emphasis added.]

Our canons of statutory construction require a statute to be construed to fulfill the objective and intent of the Legislature. E.g., County of Stutsman v. State Historical Society of North Dakota, 371 N.W.2d 321 (N.D.1985). A statute must be construed to avoid absurd and ludicrous results or to require idle or unnecessary acts. Id.

The plain language of this statute mandates that flowage easements be obtained if a drain will flood or adversely affect downstream landowners. The obvious purpose of requiring a flowage easement is to protect downstream landowners and insure that they receive just compensation in the event of flooding or an adverse impact on their land. The dispositive question is whether or not the conditional permit satisfies the statutory requirements.

In the instant case, the drain permit was approved upon the condition that flowage easements be obtained. 2 This condition simultaneously eliminates the potential of fruitless action and costs in obtaining an easement where a drain permit is not ultimately approved, while remaining faithful to the purposes of the flowage easements and their protection of downstream landowners. We conclude that the conditional drain permit issued in this case satisfies the statutory requirements of Section 61-16.1-41, N.D.C.C., and that the conditions did not invalidate the permit.

The appellants next contend that, because the minutes of the Board’s August 21, 1981 meeting contain no record of the vote on a motion to approve the drain permit, the procedure for securing the drain permit was invalid.

The minutes of that meeting reflect that a motion was made and seconded, but do not record the actual vote on the application. The minutes state that the Board considered and determined that: (1) flow-age easements were necessary over certain downstream lands; (2) downstream property would not be adversely affected; and (3) the quantity of water to be drained would not exceed the limitations of the drain and the receiving water course. The application was then forwarded to the State Engineer. The Board’s action and the minutes *483 necessarily imply that the application received favorable approval at this stage of the procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klindt v. Pembina County Water Resource Board
2005 ND 106 (North Dakota Supreme Court, 2005)
Klindt v. PEMBINA COUNTY WATER RESOURCE BD.
2005 ND 106 (North Dakota Supreme Court, 2005)
Anderson v. Richland County Water Resource Board
506 N.W.2d 362 (North Dakota Supreme Court, 1993)
State v. Knudson
499 N.W.2d 872 (North Dakota Supreme Court, 1993)
Spectrum Emergency Care, Inc. v. St. Joseph's Hospital & Health Center
479 N.W.2d 848 (North Dakota Supreme Court, 1992)
Peterson v. McKenzie County Public School District No. 1
467 N.W.2d 456 (North Dakota Supreme Court, 1991)
Keepseagle v. Backes
454 N.W.2d 312 (North Dakota Supreme Court, 1990)
Aanenson v. Bastien
438 N.W.2d 151 (North Dakota Supreme Court, 1989)
Wells County Water Resource District v. Solberg
434 N.W.2d 577 (North Dakota Supreme Court, 1989)
Haider v. Montgomery
423 N.W.2d 494 (North Dakota Supreme Court, 1988)
Johnson v. Wells County Water Resource Board
410 N.W.2d 525 (North Dakota Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
385 N.W.2d 480, 1986 N.D. LEXIS 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larson-v-wells-county-water-resource-board-nd-1986.