Larson v. Multnomah County

854 P.2d 476, 121 Or. App. 119, 1993 Ore. App. LEXIS 1051
CourtCourt of Appeals of Oregon
DecidedJune 16, 1993
DocketLUBA 92-100; CA A79157
StatusPublished
Cited by7 cases

This text of 854 P.2d 476 (Larson v. Multnomah County) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larson v. Multnomah County, 854 P.2d 476, 121 Or. App. 119, 1993 Ore. App. LEXIS 1051 (Or. Ct. App. 1993).

Opinion

*121 DEITS, P. J.

Petitioners seek review of LUBA’s decision affirming Multnomah County’s denial of their application to develop a marina on a 21-acre parcel in an exclusive farm use zone. Although the application included several components, among them a comprehensive plan amendment, a zone change and a Goal 3 exception request, all were part of and necessary to the application for the marina use.

Petitioners’ contention before LUBA was that the denial of the application deprived them of “all economically beneficial use,” and therefore constituted a regulatory taking, in violation of the state and federal constitutions. Petitioners requested an evidentiary hearing before LUBA, pursuant to ORS 197.830(13)(b), to establish that their parcel cannot be “economically used” for any of the uses permitted outright or conditionally in the EFU zone.

LUBA’s reasons for denying the requested evidenti-ary hearing and for its decision of the appeal were twofold: first, petitioners had not raised the takings issue in the local proceeding and, under ORS 197.763 and ORS 197.835(2), LUBA could not reach it; and second, because, inter alia, petitioner had not applied to the county for any use or approval except for the marina, the takings claim was not ripe for review.

Petitioners argue that both the denial of their request for an evidentiary hearing and LUBA’s affirmance of the county’s decision were erroneous. They contend that LUBA’s conclusions on both the preservation and the ripeness issues were incorrect. They also argue that the denial of the evidentiary hearing by LUBA deprived them of due process.

LUBA’s conclusions on preservation and on ripeness are stated as alternative grounds for the same result. Because we agree with LUBA on the ripeness issue, it is unnecessary for us to reach the preservation issue, and we expressly do not. The ripeness issue and the questions petitioners raise concerning their entitlement to an evidentiary hearing by LUBA are also intertwined. Petitioners’ view is that they were entitled to prove to LUBA that it would be futile for them to apply to the county for anything other than the *122 marina use, and they are therefore not required by the ripeness doctrine to make further applications to the county before seeking an adjudication of their regulatory takings claim. The county responds, in effect, that petitioners have the cart before the horse: Their claim cannot ripen until they seek and the county takes action on some application other than the one for the marina use, and LUBA correctly ruled that it could not review the takings claim or take evidence regarding it until that occurs.

In Joyce v. Multnomah County, 114 Or App 244, 835 P2d 127 (1992), we reviewed the currently relevant Oregon Supreme Court and United States Supreme Court decisions on the ripeness, or exhaustion of remedies, requirement that must be satisfied before regulatory takings claims under either constitution can become judicially cognizable. The rule that we derived from the two courts’ opinions is that a claim is not ripe for adjudication if a landowner has simply “unsuccessfully filed one application for the approval of a particular use and has pursued no alternative approaches to achieve permission for that or any other use.” 114 Or App at 247. (Footnote omitted.) 1

Similarly, in Dority v. Clackamas County, 115 Or App 449, 839 P2d 1103 (1992), rev den 315 Or 311 (1993), we held that, under Article I, section 18, of the state constitution, a landowner could not satisfy the ripeness requirement simply by pointing to the unavailability of a particular procedure for obtaining permission to conduct a use that had been initially denied, as long as at least one other local application procedure for the same or another economically viable use remained available and none had been pursued.

We further concluded, in Joyce and Dority, that arguments based on the futility exception to the ripeness rule should seldom be entertained and should not ever be considered if they amount to nothing more than predictions about the success of applications to the local governments. The underpinning for our conclusion was that the court should *123 not use the futility rationale as a device for making decisions about the permissibility of uses that are for other branches or levels of government to make initially. See 114 Or App at 248; see also MacDonald, Sommer & Frates v. Yolo County, 477 US 340, 352 n 8, 106 S Ct 2561, 91 L Ed 2d 285 (1986). 2

Petitioners attempt in a number of ways to distinguish this case from Joyce, Dority and the cases on which we relied in those decisions. They contend, first, that the futility argument that they advanced to LUBA, unlike the one in Joyce, was not that no possible alternative uses would be allowed by the county, but that no uses that could be permitted in the EFU zone would be economically viable. Assuming without deciding the correctness of their premise, petitioners may not depend solely on uses in the EFU zone unless they have sought a zone change or plan redesignation that might allow more extensive uses. Although we do not now decide whether a plan or zoning amendment must invariably be sought to achieve ripeness, we do hold that at least one application must be made after the initial denial, if any is available, and that a plan or zone change must be sought if only it is available. See note 1, supra.

Petitioners argue that they did seek a plan amendment and zone change as part of their application for the marina. However, as the county correctly points out, those requests were “denied as part of the package to permit a marina. * * * This does not mean that other projects, less ambitious but economically feasible, are not possible on petitioners’ property under the county’s land use regulations.” In sum, we do not agree with petitioners that they come to us *124 in a different posture from the petitioners in Dority and Joyce: They have made one application, and they point to no tenable reason why it would be futile for them to make others.

For the same reason, petitioners’ attempt to distinguish MacDonald, Sommer & Frates v. Yolo County, supra, does not succeed. What we said in Joyce concerning the petitioner’s argument based on MacDonald is equally applicable here: ‘ ‘ [Pjetitioner stands in precisely the same position as the applicant in MacDonald, Sommer &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

THUNDERBIRD HOTELS, LLC v. City of Portland
670 F. Supp. 2d 1164 (D. Oregon, 2009)
Murray v. State of Oregon
124 P.3d 1261 (Court of Appeals of Oregon, 2005)
Boise Cascade Corp. v. State Board of Forestry
991 P.2d 563 (Court of Appeals of Oregon, 1999)
Curran v. State
951 P.2d 183 (Court of Appeals of Oregon, 1997)
Larson v. Multnomah County
859 P.2d 574 (Court of Appeals of Oregon, 1993)
Lardy v. Washington County
857 P.2d 885 (Court of Appeals of Oregon, 1993)
Oregonians in Action v. Land Conservation & Development Commission
854 P.2d 1010 (Court of Appeals of Oregon, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
854 P.2d 476, 121 Or. App. 119, 1993 Ore. App. LEXIS 1051, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larson-v-multnomah-county-orctapp-1993.