Larry Morgan d/b/a Morgan Contracting v. Tellico Plains

CourtCourt of Appeals of Tennessee
DecidedJune 26, 2002
DocketE2001-02733-COA-R3-CV
StatusPublished

This text of Larry Morgan d/b/a Morgan Contracting v. Tellico Plains (Larry Morgan d/b/a Morgan Contracting v. Tellico Plains) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larry Morgan d/b/a Morgan Contracting v. Tellico Plains, (Tenn. Ct. App. 2002).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE June 26, 2002 Session

LARRY MORGAN d/b/a MORGAN CONTRACTING, INC. v. TOWN OF TELLICO PLAINS, TENNESSEE, ET AL.

Appeal from the Circuit Court for Monroe County No. V99274P Lawrence H. Puckett, Judge

FILED OCTOBER 30, 2002

No. E2001-02733-COA-R3-CV

In this contract dispute, the Plaintiff, Morgan Contracting, Inc. (“Morgan”) sued the Town of Tellico Plains, alleging that it was due $68,464.86 under the terms of the contract. Tellico Plains answered with the defense that Morgan’s claim was time-barred under the sixty-day limitations period set forth in the contract. After a non-jury trial, the Court ruled that Morgan had not filed suit within the contractual limitations period and consequently dismissed Morgan’s cause of action. On appeal, Morgan argues that the Trial Court erred in not finding that Tellico Plains waived its right to rely upon the contractual limitations period provision. We affirm the judgment of the Trial Court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed; Cause Remanded

HOUSTON M. GODDARD , P.J., delivered the opinion of the court, in which CHARLES D. SUSANO, JR., and D. MICHAEL SWINEY, JJ., joined.

John W. Cleveland, Sweetwater, for the Appellant, Morgan Contracting, Inc.

Wm. P. Biddle, III, Athens, for the Appellee, Town of Tellico Plains, Tennessee

OPINION

The contract at issue provided that Morgan was to install a system of water pipes for Tellico Plains’ water system, replacing a system of pipes that was, in the words of Tellico Plains’ City Engineer, “a patchwork quilt of small diameter lines of substandard grade materials, galvanized pipe, old plastic pipe, old duct line and some cast iron pipes, most of which had been installed, some as early as the early 1900's, at various times and by various people.” Morgan began work on the project in October of 1998. It soon became apparent that replacing the system of water pipes would be a rather complicated matter, as it was discovered that there were no records or drawings showing the location of the underground structures. Each of the parties took the position that the other was contractually responsible for locating and marking the existing underground pipes. On October 13, 1998, Morgan sent a letter to Joel Bruce Spaulding, Jr., the City Engineer, which states that “it is our position that any additional costs incurred, due to unmarked waterlines, will need to be compensated.” Responding to a short note sent by Mr. Spaulding which stated that the contract made it Morgan’s responsibility to locate and mark the lines, Morgan sent a letter dated October 15, 1998 which states as follows:

In short, we will not be held responsible for any water main, water service, sewer main, or sewer service damage if the lines are not marked. We will expect full compensation for the repair of such lines. We will also expect full compensation for any downtime or lost production due to the unmarked lines.

We feel a meeting about this conflict (A.S.A.P.) would be advantageous to all parties. Please advise.

On October 16, 1998, Mr. Spaulding sent Morgan a letter which states as follows in relevant part:

My formal decision under Section 9.11 of the General Conditions to your October 13, 1998 and October 15, 1998 notices is that the Contract Drawings clearly indicate that the Contractor is responsible for locating the existing underground utilities.

The location of the existing utilities and other obstacles as well as any incidental repairs to same are an essential work element of the Contract. * * * As this is an essential element of the Contract, there is no basis for additional compensation nor will the Town relieve you of your duties and responsibilities under the Contract.

Morgan continued to work on the project, locating and marking the water lines as best it could, after receipt of this letter.

On March 9, 1999, Mr. Spaulding sent a letter advising Morgan as follows:

The Town has requested that we delete the paving work from your contract with the exception of the work performed to date. They have

-2- elected to perform the work with their own forces and requested that I notify you of same.

The contract anticipated that Morgan would pave 10,000 square yards for Tellico Plains. At the time Morgan received this letter, it had completed paving only 424.78 yards. Subsequently, Morgan filed with the Town a claim for 10% overhead and 5% profit on the 9,575.22 square yards of paving work which Tellico Plains deleted from the contract.

On March 15, 1999, Morgan’s attorney sent a letter to Mr. Spaulding and Tellico Plains’ attorney, which states as follows in relevant part:

I am advising my clients, Morgan Contracting, Inc., that they may complete the job in the Town of Tellico Plains and keep a record of all costs associated with the slow downs, stops, repairs, and down time that are caused by the City of Tellico Plains’ inability to mark the underground utilities in their city.

It is in my best legal opinion that Morgan Contracting, Inc. is entitled to compensation for the loss of time and down-time as a result of the City of Tellico Plains’ inability to mark utilities. . .Therefore, I have advised my clients to serve upon the Town of Tellico Plains a bill for all additional costs which currently is running over Forty Thousand ($40,000) Dollars and additional costs are being accrued daily.

Tellico Plains’ attorney responded to this letter by sending the following letter, dated March 17, 1999, which forms the basis for Morgan’s waiver argument:

This will acknowledge receipt of your letter of March 15, 1999. We do not agree with the legal observations and conclusions made therein. Morgan can make whatever claim Morgan desires in regard to additional compensation and that will be addressed in accordance with the contract documents by the Town of Tellico Plains at such time as the contract by Morgan is completed based upon the obligations of the parties under the contract.

The Town of Tellico Plains is not accepting any liability for cost incurred by Morgan Contracting, Inc. resulting from the contractor’s damage to existing water lines, but recognize the right that Morgan has to claim additional compensation.

On May 10, 1999, Mr. Spaulding sent a letter to Morgan which states in relevant part as follows:

-3- The following represents my formal decision as ENGINEER as provided in the General Conditions Article 9.11 in response to the “Summary of Charges”, i.e., your requests for additional compensation under the above referenced contract as presented in our April 28, 1999 meeting.

* * * As regards your claims totaling $39,901.93 for marking unmarked water lines and repairing unmarked water lines, my decision remains the same as my previous decision to the contrary stated in detail in my October 16, 1998 letter. Based on the same reasons outlined in my October 16, 1998 letter, I can not approve your request for additional reimbursement for marking and/or repairing unmarked water lines.

As regards your claim for 5% overhead and 10% profit1 for the deletion of 9,575.22 square yards of pavement repair at $10.00 per S.Y. (which I calculate as a claim of $14,362.83), I can find no basis in the CONTRACT DOCUMENTS to support this claim.

Morgan filed the instant action on October 5, 1999, alleging that it was due the lost overhead and profits from the deleted paving work, and also reimbursement for the expenses it incurred due to the inability to locate and mark the water lines. Tellico Plains responded, alleging, inter alia, that the contract did not support Morgan’s claims and that Morgan had failed to comply with the following provision of the contract:

Decisions on Disputes:

9.11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fahrner v. SW Manufacturing, Inc.
48 S.W.3d 141 (Tennessee Supreme Court, 2001)
Gitter v. Tennessee Farmers Mutual Insurance
450 S.W.2d 780 (Court of Appeals of Tennessee, 1969)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)
State v. Evans
334 S.W.2d 337 (Court of Appeals of Tennessee, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
Larry Morgan d/b/a Morgan Contracting v. Tellico Plains, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larry-morgan-dba-morgan-contracting-v-tellico-plai-tennctapp-2002.