Larry Carlson & Associates, Inc. v. State

40 Ill. Ct. Cl. 100, 1988 Ill. Ct. Cl. LEXIS 37
CourtCourt of Claims of Illinois
DecidedJune 17, 1988
DocketNo. 84-CC-1580
StatusPublished
Cited by1 cases

This text of 40 Ill. Ct. Cl. 100 (Larry Carlson & Associates, Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larry Carlson & Associates, Inc. v. State, 40 Ill. Ct. Cl. 100, 1988 Ill. Ct. Cl. LEXIS 37 (Ill. Super. Ct. 1988).

Opinion

Montana, C.J.

The Claimant, Larry Carlson & Associates, Inc., filed its complaint in the Court of Claims alleging a breach of contract. Specifically, Claimant alleges the State entered into a contract with Walsh Construction Company of Illinois to do bridge repairs on a bridge at the Chicago Circle Interchange in Chicago, Illinois. Claimant subcontracted with Walsh Construction to furnish all labor, material, and equipment required to do certain bridge repairs according to the specifications. The subcontract provided Claimant would be paid $170.00 per cubic foot and the rate was determined by the contract specifications which specified epoxy materials which were trowelable in layers not to exceed one inch in total depth. Claimant also alleges that upon beginning work it became apparent that the specified epoxy products were not appropriate for the job and it was necessary to change epoxy materials. The new substance required forming rather than trowel application. The cost escalated to $525.73 per installed cubic foot. Claimant asserts it completed 484 cubic feet using the substituted epoxy material for a net charge of $172,173.32. The Illinois Department of Transportation (IDOT) refused payment. Later, Claimant was directed by IDOT to change to a non-epoxy pneumatically-applied material called Sikatop and it completed 187.1 cubic feet of this material for a net charge of $51,098.88. When Claimant sought payment, IDOT denied the claim. Claimant alleges that the substituted epoxy, Sikatop and labor were outside the contract and due to the error in contract specifications. Claimant further alleges a breach of IDOT’s implied warranty that the plans and specifications furnished Claimant would enable it to do the work with the required materials. Walsh Construction Company assigned its cause of action to Claimant who now seeks a total of $223,272.20. This was in settlement of a lawsuit wherein Claimant sued Walsh.

A trial was held in this cause before Commissioner Robert Frederick. The Claimant presented evidence, but the State chose to rest without presenting any testimony. The evidence presented was the testimony of C. Stanton Fowler, Claimant’s exhibits B (attached to Claimant’s complaint), 1, 2, 3, 4, 5a, 5b, 6, 7, 8a, 8b, 8c, 8d, 9, 10a, 10b, 10c, lOd, 11, 12, 13, and Respondent’s exhibits 1 and 2. Claimant’s exhibits B, 1, 2, 3, 4, 5a, 5b, 6, 9, 11, and 12 were admitted. Exhibit 13 was refused. Exhibit 7 was taken under advisement. Exhibits 8a, 8b, 8c, 8d, 10a, 10b, 10c, and lOd were admitted for the limited purposes stated in the record. Respondent’s exhibit 1, the last two pages only, and Respondent’s exhibit 2 were admitted. The Commissioner requested that the entire contract be placed in evidence and both parties agreed. The issues have been fully briefed by the parties and the Commissioner has duly filed his report.

The parties stipulated that the Claimant installed 484 cubic feet of the substituted epoxy material and 187.1 of Sikatop material as pleaded in Claimant’s complaint. Foundations for admissibility of letters and literature from material suppliers were waived. The parties further stipulated that foundations for the tabulations concerning proof of damages relative to material supplied, labor costs, the raw data for the material supplied, and time records would be waived. The raw data reflected in the calculations, being Claimant’s exhibits 1 and 2, are accurate tabulations of the data from the payroll expenses and labor records of Claimant. Lastly, the parties stipulated that the job specifications at issue are those reflected in Claimant’s exhibit B which was attached to Claimant’s complaint.

C. Stanton Fowler testified for Claimant. He was employed by Claimant in 1980 at the time of the project at issue. He had started working in the epoxy repair industry in 1976. On the job at issue, he was responsible for evaluating the job, bidding on the job, and for execution of the work.

Mr. Fowler testified that epoxy is a very strong substance that is used with aggregate to reinforce deteriorating concrete. Some epoxies are used to protect concrete from further deterioration and others try to make it compatible with the concrete. Epoxy in its gel form generates its own heat. The heat is dissipated by having it absorbed into the concrete or into aggregate which is mixed in with it.

Mr. Fowler had worked on other various projects where he used epoxy materials. He was familiar with epoxy materials in the industry and had reviewed literature and had epoxy materials demonstrated by salespeople. He was familiar with the specifications for the instant project as set forth in exhibit B. The specifications listed a Colma-Dur Gel manufactured by the Sika Chemical Corporation and he was familiar with this material as he had seen it demonstrated and had used the product on a project. He was familiar with Ex-60 Hydro-Ester Low Modules Trowel manufactured by Fox Industries, Inc., which was also listed in the specifications. He also was familiar with the third product on the specification list, that being Duralith Gel manufactured by Dural International Corporation.

Each of the three listed products is a gel and very obviously trowelable. They are designed for an in-depth repair and can be put in at layers not to exceed one inch. The products are gummy and very sticky so they can be applied overhead. They stick and can be spread with a trowel. No forms need to be built to hold the substance.

After the Claimant became aware of this job through a job bulletin, Mr. Fowler reviewed the job specifications, and inspected the work area. He and his foreman personally inspected the bridge where the work was to be done. There were spots of rust where wire was too close to the surface of the concrete. As rust occurs, the concrete, due to weather, expands and breaks. The surfaces did look reasonably sound and smooth; however there were some chipped-out areas. In their opinion, there would be a minimal amount of concrete removal which would dovetail right into the product specifications and which would correlate to the depths for those allowable for Colma-Dur Gel or the Duralith. The Claimant had no reason to question the job specifications at the time of bidding, and it had had a similar job in Iowa on a bridge a month before where the same type of application that was intended to be used on this job was used. The three products specified could only be used within a very shallow depth and appeared to be correct for this job based on their inspection.

Claimant prepared a bid and it was based on the use of a specific family of epoxies and the labor and concrete removal required to apply it. This was a per unit contract.

After reviewing the job Claimant ordered epoxy. It was under a requirement to submit the product specifications from the manufacturer to the owner, IDOT. Claimant purchased Nilkepoxy No. 26 manufactured by Rocky Mountain Chemical Company, and this product was approved. It is the same type of epoxy as the other listed ones. Exhibit 4 is the specification sheet for Nilkepoxy No. 26. Exhibits 4, 5, and 5b are specification sheets for Nilkepoxy No. 26 and Sika Colma-Dur Gel. They appear to have very similar specifications and all fall well within the requirements of exhibit B.

Claimant gave exhibit 4, the specification sheet, to the Respondent and the product was approved for use. All the products were non-sag which means they can be troweled overhead without falling out of place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Genie Construction Co. v. State
51 Ill. Ct. Cl. 153 (Court of Claims of Illinois, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
40 Ill. Ct. Cl. 100, 1988 Ill. Ct. Cl. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larry-carlson-associates-inc-v-state-ilclaimsct-1988.