Lano v. Osberg Construction Co.

462 P.2d 923, 77 Wash. 2d 369, 1969 Wash. LEXIS 596
CourtWashington Supreme Court
DecidedDecember 11, 1969
DocketNo. 39950
StatusPublished

This text of 462 P.2d 923 (Lano v. Osberg Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lano v. Osberg Construction Co., 462 P.2d 923, 77 Wash. 2d 369, 1969 Wash. LEXIS 596 (Wash. 1969).

Opinion

Hamilton, J.

This is an appeal by plaintiffs from a judgment for damages entered in an action for wrongful termination of a highway construction subcontract. The issue on appeal is limited to the propriety of the trial court’s allowance of a counterclaim interposed by defendant, Osberg Construction Company, arising out of an assignment of bonding company claims against plaintiff. We outline briefly the pertinent circumstances.

In late 1958, the defendant (respondent) entered into a contract with the State of Washington to construct a portion of the Tokeland-Raymond highway. Plaintiffs, in turn, executed a subcontract with defendant by the terms of which plaintiffs were to clear and grub certain portions of the proposed roadway. In so doing, plaintiffs were required [370]*370to post a performance bond in the amount of $78,500. To obtain the bond from the United Pacific Insurance Company, one E. C. Orton guaranteed plaintiffs’ indemnity agreement with the bonding company.

Plaintiffs’ progress on the job was unsatisfactory and defendant undertook to terminate the subcontract and pursuant thereto did take over completion of the work. Negotiations with the bonding company ensued and resulted in payments being made on the bond in the total sum of $40,000. The guarantor, E. C. Orton, reimbursed the bonding company and received an assignment of the company’s claim against plaintiffs under the indemnity agreement. Mr. Orton later assigned such claim to defendant.

In the meantime, although subsequent to completion of the prime contract and the advancements made by the bonding company, plaintiffs initiated this action against defendant seeking damages for termination of their subcontract. Defendant counterclaimed for damages incurred as a result of plaintiffs’ default.

This action initially went to trial on the issue of liability only. At the conclusion of such trial, the trial court found as a fact that plaintiffs were in default on their subcontract, determined that defendant had reasonably notified plaintiffs of such default, and dismissed the action. On appeal, after observing that the trial court’s finding with respect to plaintiffs’ default in performance was supported by substantial evidence, we concluded that the trial court erred in determining that defendant had complied with the notice requirements of the contract. We accordingly reversed the order of dismissal and remanded the cause for trial on the issue of damages. Lano v. Osberg Constr. Co., 67 Wn.2d 659, 409 P.2d 466 (1965).

Following the remand, plaintiffs amended their claim for relief to include an allegation of damage predicated upon their potential liability to the bonding company. In response, defendant pleaded the assignment it held of the bonding company’s claim against plaintiffs. Plaintiffs’ motion to dismiss the defendant’s claim under the assignment [371]*371was denied and a lengthy trial relating to the issue of damages followed.

At the conclusion of the trial, the trial court indicated that, in the interest of avoiding a multiplicity of suits, it intended to recognize defendant’s counterclaim predicated upon the assignment of the bonding company’s claim of indemnification. The trial court then tendered to plaintiffs a continuance to permit assembly and presentation of any additional evidence they might have in connection with defenses or setoffs to the assigned claim. Plaintiffs declined the proffered continuance and urged disposition of the case upon the evidence as it then stood.

Thereafter, the trial court in a considered memorandum opinion, the essence of which is carried into the findings of fact and conclusions of law, determined that it would have cost plaintiffs $65,269 to have completed performance of their subcontract. This amount, which is not challenged on appeal, is considerably in excess of the amount remaining due on the subcontract at the time defendant took over completion of the work. The trial court then found that defendant, in performing the balance of the work on the subcontract, received the sum of $82,912. This sum consisted of $42,912 remaining due on the subcontract at the time of its termination and $40,000 paid by the bonding company upon the performance bond. The trial court denominated the difference between the amount plaintiffs could have completed the work for and the amount received by defendant — $17,643—as an overpayment on the bond and awarded plaintiffs judgment in that amount, plus the sum of $3,039.24, representing the amount plaintiffs would have received for timber they could have removed from the jobsite, and $780 as rental upon equipment belonging to plaintiffs which defendant utilized in completing the work on the subcontract. The total recovery thus afforded plaintiffs was rounded out at $21,462. The trial court further determined and found that defendant was substantially damaged by reason of the delay in completing its prime contract, occasioned by plaintiffs’ failure to timely [372]*372perform their subcontract, but concluded that defendant was without recourse for this damage under the terms of the subcontract. As we have indicated, these calculations and findings by the trial court are in no way challenged on this appeal.

The trial court then turned to a consideration of defendant’s counterclaim as assignee of the bonding company’s claim of indemnification. In its memorandum decision the trial court, after noting that plaintiffs had declined to present any evidence relating to defenses or offsets against the assigned claim, determined that as the evidence stood the indemnity agreement executed by plaintiffs in obtaining the performance bond rendered them liable to reimburse the bonding company for expenditures under the bond, that the assignments of this right of indemnification first to Mr. Orton, the guarantor, and then to defendant were valid and effective, and defendant, as the then assignee, was entitled to assert the claim. The trial court then opined that judgment on the counterclaim should be entered on behalf of defendant for the amount of $40,000, the sum advanced by the bonding company, less the amount of the overpayment of $17,643 coupled with plaintiffs’ other damages. Again, by its memorandum decision, the trial court proffered plaintiffs additional time to present evidence bearing upon defenses or setoffs to the assigned claim and, for the second time, plaintiffs rejected the offer.

Findings of fact, conclusions of law, and judgment were then entered, the net effect of which was to award judgment to defendant upon its counterclaim in the amount of $18,538, representative of the difference between plaintiffs’ judgment of $21,462 and the full amount of plaintiffs’ liability on the assigned claim of the bonding company, i.e., $40,000.

On appeal plaintiffs challenge the award to defendant, primarily upon the basis of their contention that our decision in the first appeal, Lano v. Osberg Constr. Co., supra, established that the termination of their subcontract was wrongful and, hence, the bonding company was not legally [373]*373liable upon the performance bond. Therefore, plaintiffs argue, the payments made on the bond were voluntary payments and not reimbursable by them under their indemnity agreement.

We cannot agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lano v. Osberg Construction Co.
409 P.2d 466 (Washington Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
462 P.2d 923, 77 Wash. 2d 369, 1969 Wash. LEXIS 596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lano-v-osberg-construction-co-wash-1969.