Lano v. Osberg Construction Co.

409 P.2d 466, 67 Wash. 2d 659, 1965 Wash. LEXIS 725
CourtWashington Supreme Court
DecidedDecember 30, 1965
Docket38006
StatusPublished
Cited by10 cases

This text of 409 P.2d 466 (Lano v. Osberg Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lano v. Osberg Construction Co., 409 P.2d 466, 67 Wash. 2d 659, 1965 Wash. LEXIS 725 (Wash. 1965).

Opinion

Hunter, J.

— This is an action for damages for wrongful termination of a subcontract to clear and grub a state highway right-of-way in Pacific County.

In November, 1958, defendant (respondent) Osberg Construction Company, as prime contractor, executed a contract with the state of Washington to construct a portion of the Tokeland-Raymond highway.

Plaintiffs (appellants) executed a subcontract with defendant covering the clearing and grubbing portion of the prime contract. The plaintiffs, who were primarily loggers, contracted with a third party to perform the clearing and grubbing after the removal of the timber.

The subcontract was on a form known as the A.G.C. (Associated General Contractors of America) subcontract. Plaintiffs used the same form in contracting with the third party. The pertinent provisions of the subcontract provide:

The Subcontractor Agrees:

(b) To start work immediately when notified by the Contractor, and to complete the several portions and *661 the whole of the work herein sublet, at such times as will enable the Contractor to fully comply with the contract with the Owner, and to be bound by any provisions in the Main Contract with the Owner for liquidated damages, if caused by Subcontractor.
(m) To commence and at all times to carry on, perform and complete this Subcontract to the full and complete satisfaction of the Contractor, and of the Architect or Owner. It is specifically understood and agreed that in the event the Contractor shall at any time be of the opinion that the Subcontractor is not proceeding with diligence and in such a manner as to satisfactorily complete said work within the required time, then and in that event the Contractor shall have the right, after reasonable notice, to take over said work and to complete the same at the cost and expense of the Subcontractor, without prejudice to the Contractor’s other rights or remedies for any loss or damage sustained. (Italics ours.)

Work commenced on the project in late November, 1958. Due partially to the swampy terrain of the first mile of the project, the clearing and grubbing advanced very slowly. In January and February, 1959, defendant expressed to the plaintiffs dissatisfaction with the progress of the grubbing and clearing. Plaintiffs, in turn, warned their subcontractor that they would terminate his contract if progress were not improved. Progress of the grubbing and clearing did not improve satisfactorily, and on March 24, 1959, plaintiffs terminated their contract with the third party and took over his employees and equipment. Plaintiffs continued with the grubbing and clearing operation until their subcontract with defendant was terminated on August 17, 1959.

On July 20,1959, defendant’s owner, Mr. Osberg, verbally notified plaintiffs of his dissatisfaction with their work progress and urged them to improve the same. Again, on August 4, 1959, plaintiffs were notified verbally that their contract would be terminated if work progress did not improve.

On August 6,1959, a fire occurred on the project, shutting down work and causing cancellation of plaintiffs’ burning *662 permit. The permit was reissued with additional requirements for firefighting equipment. Plaintiffs did not comply with the new requirements, despite defendant’s urging them to do so and continue progress. On August 12, Osberg gave verbal notice to plaintiffs that their contract would be terminated on August 17, 1959, unless substantial improvement in the work progress were assured by then. This notice was confirmed by registered letter received by one of the plaintiffs on the evening of Thursday, August 13, 1959. The formal, written notice listed the following five conditions:

1. You have only six (6) men on the job.
2. Your fire permit has been cancelled due to your failure to take adequate preventions, thereby preventing you from further burning operations.
3. Much of your equipment is broken down and inoperable and is not being repaired.
4. You have made no effort to increase production and have insisted on working only 5-8 hour days per week.
5. You are having considerable labor difficulty and are being threatened with shutdowns by certain labor unions.

Plaintiffs’ attention was directed to paragraph (m) of the subcontract, supra. The notice then stated:

unless the above conditions are entirely corrected and you make satisfactory progress by Monday, August 17, we shall immediately proceed, without further notice, to take over and complete the balance of the work covered by said Subcontract. (Italics ours.)

Conditions did not change by August 17, and on the morning of that day, defendant terminated plaintiffs’ subcontract.

Plaintiffs brought suit for damages for breach of contract, and defendant cross-complained for damages for the plaintiffs breach. The trial court, sitting without a jury, granted a motion for segregation of the issues to try the issue of liability alone. The trial court then tried the case, made findings of fact and conclusions of law, and dismissed the action with prejudice, awarding the defendant its costs. Plaintiffs appeal.

Plaintiffs contend the trial court erred in approv *663 ing the cancellation of the subcontract. They argue first that the evidence does not show a default upon their contract which would justify defendant’s termination of the contract. We have carefully reviewed the entire record. The contract did not specify a completion date; the law, therefore, supplies the requirement that plaintiffs’ progress must be reasonable under the circumstances. Although there is a conflict in the evidence regarding the many factors to which defendant points as justifying the declaration of default, our review of the record clearly shows substantial evidence to support the trial court’s determination that plaintiffs were in default in the performance of the contract at the time the notice of termination was given on August 13, 1959.

Plaintiffs further contend that they were not given reasonable notice of termination of their contract, in violation of the requirement of such notice expressly set forth in the contract. We agree.

The subcontract provided that the contractor would have the right, after reasonable notice, to take over the grubbing and clearing. The contractor was bound to comply with that requirement in giving notice of termination. See, e.g., Annotation, 107 A.L.R. 1035, 1044.

What constitutes notice must be determined from the facts and circumstances of each case. Vance v. Mutual Gold Corp., 6 Wn.2d 466, 478, 108 P.2d 799 (1940). Black, Law Dictionary 1211 (4th ed.) defines reasonable notice as “Such notice or information of a fact as may fairly and properly be expected or required in the particular circumstances.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Hastings v. Unikrn, Inc.
Court of Appeals of Washington, 2020
Sak & Associates, / Cross- Res. v. Ferguson Construction, / Cross-app.
357 P.3d 671 (Court of Appeals of Washington, 2015)
Associated Petroleum Products, Inc. v. Northwest Cascade, Inc.
149 Wash. App. 429 (Court of Appeals of Washington, 2009)
Cascade Auto Glass v. PROGRESSIVE CAS. INS.
145 P.3d 1253 (Court of Appeals of Washington, 2006)
Cascade Auto Glass, Inc. v. Progressive Casualty Insurance
135 Wash. App. 760 (Court of Appeals of Washington, 2006)
Dravo Corp. v. L. W. Moses Co.
492 P.2d 1058 (Court of Appeals of Washington, 1971)
Lano v. Osberg Construction Co.
462 P.2d 923 (Washington Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
409 P.2d 466, 67 Wash. 2d 659, 1965 Wash. LEXIS 725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lano-v-osberg-construction-co-wash-1965.