Lanier Const. Co., Inc. v. CITY OF CLINTON, NC

812 F. Supp. 2d 696, 2011 U.S. Dist. LEXIS 101042, 2011 WL 3949814
CourtDistrict Court, E.D. North Carolina
DecidedSeptember 6, 2011
Docket5:11-cr-00036
StatusPublished
Cited by1 cases

This text of 812 F. Supp. 2d 696 (Lanier Const. Co., Inc. v. CITY OF CLINTON, NC) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lanier Const. Co., Inc. v. CITY OF CLINTON, NC, 812 F. Supp. 2d 696, 2011 U.S. Dist. LEXIS 101042, 2011 WL 3949814 (E.D.N.C. 2011).

Opinion

ORDER

TERRENCE WILLIAM BOYLE, District Judge.

This matter is before the Court on Defendants’ Motion to Dismiss [DE 26]. Because Plaintiff fails to state a claim upon which relief may be granted, the following claims are dismissed: claims for relief under 42 U.S.C. § 1983 for violations of Fourteenth Amendment procedural due process; as well as state law claims for defamation, intentional interference with prospective contractual relations, and breach of contract.

BACKGROUND

Plaintiff Lanier Construction Company alleges that its bid for a City of Clinton project was rejected because the company is owned by African-Americans [DE 3 at 4]. Lanier has specialized in public utilities, grading/road construction, site development, and road/street work for private and governmental clients for twenty-seven years [DE 3 at 3]. On October 14, 2010, Lanier was the lowest bidder on the City of Clinton’s “Downtown Revitalization Phase III” project. Lanier bid $1,056,403.75 [DE 3 at 4]. The next lowest bidder, Paul Howard Construction Company, is Caucasian-owned and was awarded the project on its bid of $1,097,300.00 [DE 3 at 4],

The bidding process was conducted by The Wooten Company, a professional engineering firm, through a contract with the City of Clinton [DE 3 at 5]. Wooten’s Project Engineer informed Lanier that it was recommending it for award of the final contract [DE 3 at 5]. However, Clinton City Manager John Connet later personally investigated Lanier’s qualifications and submitted a memorandum to the City Council on November 23, 2010, recommending rejection of the Lanier bid on the ground that Lanier was not the lowest “responsible” bidder [DE 3 at 5]. Lanier alleges that this memorandum was incorrect and misleading. In the memorandum, Mr. Connet told the City Council that “Lanier Construction had four out of five projects that were not completed within the time specified in the contract and resulted in liquidated damages.” Lanier also challenges Mr. Connet’s assertion that he had “completed a thorough reference and corporate background check of the two lowest bidders” [DE 3 at 25]. The City Council *699 placed the matter on its agenda for its December 7, 2010 meeting. Lanier was not notified of the meeting [DE 3 at 6].

At the meeting, the City Council unanimously adopted Mr. Cornet’s recommendation and rejected Lanier’s bid [DE 3 at 5]. The Council voted to award the contract to the next lowest bidder, Paul Howard Construction Company, which is Caucasian-owned [DE 3 at 4], Lanier was first notified that it did not receive the award in a letter from Mr. Connet dated December 13, 2010. The letter stated that Lanier was not a responsible bidder, taking into consideration its quality, performance, and timeliness on previous projects [DE 3 at 5].

Lanier’s attorney appeared at a City Council meeting on February 1, 2011, where all five Council members were present. Through its counsel, Lanier attempted to rebut Mr. Connet’s memorandum and presented a packet of information supporting its cause [DE 3 at 6]. Two African-American council members motioned and seconded to delay the scheduled March 7, 2011 start date for construction on the project, pending further deliberation of the matter. The remaining three Council members (all Caucasian) voted to reject he motion, affirming the Council’s December 7, 2010 decision [DE 3 at 7]. Lanier argues that its bid was rejected because it is an African-American-owned corporation and seeks money damages under 42 U.S.C. § 1983 for violation of its rights to equal protection and substantive and procedural due process under the Fourteenth Amendment, as well as state law claims for abuse of discretion in the bid process, defamation, interference with prospective contractual relations, and breach of contract [DE 3 at 19-28].

DISCUSSION

A motion to dismiss under Federal Rule of Civil Procedure 12(b)(6) will succeed if a plaintiff fails to establish a “plausible” claim for relief. Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 556, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007); Ashcroft v. Iqbal, 556 U.S. 662, 129 S.Ct. 1937, 1949, 173 L.Ed.2d 868 (2009).

Defendants do not seek to dismiss Lanier’s claims under 42 U.S.C. § 1981, its equal protection claims, or its state law abuse- of discretion claims. They do challenge Lanier’s claims under (1) Fourteenth Amendment procedural due process; as well as the state law claims of (2) defamation; (3) intentional interference with prospective contractual relations; and (4) breach of contract [DE 27]. Lanier’s claim under substantive due process appears to allege a procedural due process violation, and as such is considered within the discussion of the procedural due process claims. Although set forth as separate claims for relief, Lanier’s requests for relief under 42 U.S.C. §§ 1983 and 1988 and its requests for specific performance and for declaratory judgment each refer to remedies or mechanisms available to vindicate other claims. On a motion to dismiss, discussion of remedies is premature and only Lanier’s claims for relief will be addressed here.

Fourteenth Amendment Procedural Due Process

The Fourteenth Amendment of the United States Constitution provides that state actors shall not deprive any person of life, liberty, or property without due process of law. U.S. Const. Amend. XIV. In order to state a claim for relief for a violation of procedural due process, a plaintiff must establish (1) that he was deprived of a protected property or liberty interest; and (2) that the procedures provided were inadequate. Bd. of Regents of State Colls. v. Roth, 408 U.S. 564, 571, 92 S.Ct. 2701, 33 L.Ed.2d 548 (1972). A mere unilateral expectation of a government *700 benefit is insufficient; rather, the plaintiff must have a legitimate claim of entitlement to it. Town of Castle Rock, Colo. v. Gonzales, 545 U.S. 748, 756, 125 S.Ct. 2796, 162 L.Ed.2d 658 (2005) (citing Roth, 408 U.S. at 577, 92 S.Ct. 2701).

Here, Lanier fails to state a claim upon which relief can be granted because it fails to allege such a property or liberty interest. Generally speaking, an unsuccessful bidder (even the lowest bidder) for a government contract does not have a sufficient property interest to support a due process claim. Sowell’s Meats & Servs., Inc. v. McSwain,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darling v. Falls
236 F. Supp. 3d 914 (M.D. North Carolina, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
812 F. Supp. 2d 696, 2011 U.S. Dist. LEXIS 101042, 2011 WL 3949814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lanier-const-co-inc-v-city-of-clinton-nc-nced-2011.