Lane Construction Corp. v. Department of Highways

17 Ct. Cl. 180
CourtWest Virginia Court of Claims
DecidedFebruary 3, 1989
DocketCC-83-172
StatusPublished

This text of 17 Ct. Cl. 180 (Lane Construction Corp. v. Department of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane Construction Corp. v. Department of Highways, 17 Ct. Cl. 180 (W. Va. Super. Ct. 1989).

Opinion

WALLACE, JUDGE:

This claim arises out of a construction project in Kanawha County designated as Project No. I-IG-77-2(39)89, (320-77-82.20 C-I), dated June 1, 1978. The parties to the contract are The Lane Construction Corporation, hereinafter referred to as Lane, and the Department of Highways. The contract completion date was October 31, 1980. The project consisted of the construction of approximately 4,730 linear feet of a four-lane, concrete paved, divided highway (West Virginia Turnpike 1-77), 4,300 linear feet of relocated U.S. Route 119, eight bridges, four interchange ramps, and various other incidental items. Lane contends that various delays were incurred as a result of plan errors, changed site conditions, and respondent's failure to timely approve rock borrow sources as well as extra work necessitated by various design changes. Lane also included three additional claims for particular costs which it incurred in the construction of this project. The actual completion date for the project was in October 1981.

Lane alleges the following items of damages:

$1,735,482.00 (1) Increased unclassified excavation

$154,413.00 (2) Increased rock borrow excavation

$26,269.00 (3) Increased Portland cement costs

$18,964.00 (4) Increased concrete production costs

[181]*181(5) Increased structures costs $148,396.00

(6) Increased traffic maintenance costs $65,853.00

(7) Increased indirect costs $187,922.00

(8) Increased project layout costs $23,868.00

(9) Increased property tax costs $17,974.00

(10) Increased home office overhead costs $73.278.00

TOTAL. OF DELAY CLAIM $2,452,419.00

The extra work portion of the claim consists of the following items:

(1) Temporary concrete median barrier $16,278.00

(2) Relocation of waterline $1,200.00

(3) Rebuilding shoulder at toll plaza $6.349.00

TOTAL OF EXTRA WORK ITEMS $23,827.00

The first phase of the contract required Lane to fill a swamp area for the relocation of Route 119. The plans indicated that Lane would need approximately 94,989 cu yds. of select rock for this swamp area. This item was critical as the contract required that the area be allowed to settle for 450 days before completion of the area. Phase I also included construction of two access ramps and a portion of the northbound lane of the interstate. The plans indicated that the cuts in the area of relocated Route 119 would yield sufficient rock to complete the fills and leave a surplus of rock of 17,235 cu. yds. There were also supposed to be approximately 152,000 cu. yds. of rock available in the cuts adjacent to access road three. Only a portion of the rock would be needed for the embankments for Route 61. According to the plans, Lane would need to "borrow" 143,730 cu. yds. of select rock during the first phase of the project.

Lane submitted requests for rock borrow in early July 1978 in anticipation of the needed rock for Phase I construction. The request to borrow rock from Rock Borrow Areas 1 and 2 was made July 5, 1978, and the request for Rock Borrow Area 3 was made July 8, 1978. The respondent denied permission to borrow rock in these areas but the actual denial was not forthcoming until mid-August 1978. Lane alleges that its failure to offer a royalty for the rock in these areas which were within the project limits was the reason that it was not permitted to borrow from these areas. In early August 1978 Lane submitted requests to borrow rock from Rock Borrow Areas 4, 5, and 6. These requests were acted upon in a timely manner by respondent and Lane was permitted to borrow rock from Rock Borrow Area 4 when it was approved in early September 1978. The requests for areas 5 and 6 were denied. Borrow requests for Areas 7 and 8 were made on August 31, 1978. Area No. 7 was approved on September 28, 1978. Rock was available almost immediately from Area 7 an Lane was able to develop the rock from Area 4 shortly thereafter.

[182]*182By this point in the project, Lane recognized that the rock indicated in the original plans was not present on the project. It was anticipated by both parties that this project would be a "borrow" job. However, Lane needed a significantly greater amount of select embankment in the swamp area than indicated in the plans. Lane alleges that respondent measured the swamp area from the top of the water in the swamp rather than from the bottom of the swamp. This area required 140,000 cu. yds. of select embankment. The plans indicated 94,000 cu. yds. would be needed.

During this time Lane was completing excavation operations in the area that was to have produced the major portion of rock and the rock was absent. In these areas Lane was stockpiling unclassified material from the cuts where the plans indicated rock would be found. For example, one cut on the plans indicated 38,000 cu. yds. of available rock, but the cut contained no rock borrow. In another cut, the plans indicated 150,000 cu. yds. of rock, but contained only 150 cu. yds. This set of circumstances placed Lane in the position of stockpiling unclassified material which was not contemplated by the original plans. At the same time, Lane was in the construction phase in which select embankment requirements were increased. As a result, Lane was thirteen weeks behind schedule by the end of the 1978 construction season. Lane alleges the delay was due to respondent's delay in approving and disapproving borrow site requests.

The problem of lack of select rock on the project continued into the 1979 construction season. An extension for borrow from Rock Borrow Area 9 was requested on April 27, 1979, and approved May 17, 1979. The respondent authorized the borrowing of 48,000 cu. yds. of rock as it believed that sufficient rock was still present in the other cuts to be developed within the project limits. As the project progressed, lane actually ended up borrowing another 46,000 cu. yds. of rock. At each juncture of the project when rock was necessary Lane's progress was delayed by a lack of rock. In fact, during Phase I, Lane actually placed 140,000 cubic yards of rock. During Phase I, it was necessary for Lane to borrow 49,952 cu. yds. more rock than the contract quantity of borrow indicated for the project.

Respondent contends that it does not approve borrow sites within project right of ways. According to respondent, Lane was well aware of the normal policies regarding rock borrow areas and knew prior to the construction of this interchange that borrow areas would have to be found off the project site. Respondent also indicated its position with regard to the rejection of the borrow areas. The reason for rejecting borrow from areas 1, 2, 5, and 6 was that these were located within the State's right of way of the project limits. Areas 2 and 3 were rejected as respondent was of the opinion that these areas had unstable soil conditions. There was no explanation for the immediate answer provided to Lane for areas 5 and 6. Furthermore, respondent asserts that the delays in the approval, if any, were not unreasonable given their potential impact on the design of the project. Respondent also contends that there were a number of delays which were solely attributable to Lane.

A project which was calculated to be a borrow job, in that the respondent had estimated that the project limits contained approximately 160,000 yards of select sandstone borrow, and that [183]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. J. Baltes, Inc. v. Department of Highways
13 Ct. Cl. 1 (West Virginia Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
17 Ct. Cl. 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-construction-corp-v-department-of-highways-wvctcl-1989.