Landaw v. Tucker Freight Lines, Inc.

263 N.E.2d 756, 148 Ind. App. 48, 76 L.R.R.M. (BNA) 2029, 1970 Ind. App. LEXIS 327
CourtIndiana Court of Appeals
DecidedNovember 24, 1970
Docket1169A218
StatusPublished
Cited by5 cases

This text of 263 N.E.2d 756 (Landaw v. Tucker Freight Lines, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Landaw v. Tucker Freight Lines, Inc., 263 N.E.2d 756, 148 Ind. App. 48, 76 L.R.R.M. (BNA) 2029, 1970 Ind. App. LEXIS 327 (Ind. Ct. App. 1970).

Opinion

CARSON, J.

This is an appeal by plaintiff-appellant from a negative judgment entered by the St. Joseph Superior Court. Trial was by the court, without jury.

The issues were formed by plaintiff’s complaint in one paragraph and defendant’s answer thereto pursuant to Rule 1-3, Rules of the Supreme Court of Indiana, and a pre-trial conference and order.

Plaintiff’s complaint alleged, in substance, that plaintiff was employed by appellee in 1951 in South Bend, Indiana, and continued to work for appellee until his discharge in 1959. In 1955 he was transferred to appellee’s Gary terminal. During all of his employment plaintiff was a member in good standing of the Teamster’s Union. Plaintiff further alleged that on or about February 1, 1958, plaintiff-appellant’s bargaining unit entered into a collective bargaining agreement with appellee which agreement established wages, hours and terms of employment; that plaintiff-appellant performed all of the conditions of the contract which were not otherwise waived by appellee; and that on or about the 29th day of April, 1959, appellant was discharged. Plaintiff-appellant alleged that the sole reason being given for his discharge was *50 his refusal to purchase his own truck and become an owner-operator for the defendant-company. Plaintiff further alleged that appellee continued to keep in its employ persons with less seniority than appellant in violation of the collective bargaining agreement; that appellee wrongfully withheld from appellant the sum of $292; and that appellant was damaged in the amount of $9,135.55 as a result of the action of defendant-appellee. To appellant’s complaint appellee filed an answer first denying the discharge of appellant in breach of the collective bargaining agreement, and, secondly, denying that appellant had filed a written notice of appeal from his discharge; that appellant had failed to follow the grievance procedures as required by the contract; and further denied that plaintiff-appellant sustained any damage.

The issues before the trial court which are pertinent to this appeal may be summarized as follows:

“a. Did the Appellee fire Appellant in breach of its collective bargaining agreement?
“b. Whether Appellant did all he was required to do under the contract.”

The trial court found for defendant-appellee on all of the above issues. Following the entry of judgment, plaintiff-appellant filed a motion for new trial assigning as error that the decision of the court is contrary to law. The motion for new trial was overruled. Appellant’s sole assignment of error is the overruling of the motion for new trial.

THE DECISION OF THE COURT IS CONTRARY TO LAW

The assignment of error to the effect that the decision of the court is contrary to law presents for our consideration the determination of whether or not appellant has demonstrated reversible error under the requirements of the rule laid down in Pokraka v. Lummus Co. (1952), 230 Ind. 523, 104 N. E. 2d 669.

*51 *50 “It is only where the evidence is without conflict and can lead to but one conclusion, and the trial court has reached *51 an opposite conclusion, that the decision of the trial court will be set aside on the ground that it is contrary to law.” See also: Hinds, Executor etc. v. McNair, et al. (1956), 235 Ind. 34, 129 N. E. 2d 553.

Appellee argues that there is conflict in the evidence as to whether Landaw was actually discharged by the President of Tucker Freight Lines, Inc. We do not agree. Both Landaw and Konkle testified that appellant-Landaw had been discharged by the President of Tucker Freight Lines, Inc. in the lobby of the Gary Hotel following the April 29, 1959, meeting between the Union and representatives of Tucker Freight Lines, Inc. Appellee contends the conflicting testimony was elicited from Sam Raitzin, President of Tucker Freight Lines, Inc.

“Q. Now did you tell Mr. Landaw he was fired?
“A. I don’t recall anything of that. I may, I may not, I don’t recall that I fired any individual personally.”

Mr. Raitzin did not deny or affirm the discharge. His testimony, in short, amounted to nothing, neither affirmance nor contradiction of the evidence given by Landaw and Konkle.

Appellee next argues that the case before us should be judged upon the conclusions of law found in Tucker Freight Lines, Inc. v. Konkle (1968), 143 Ind. App. 501, 15 Ind. Dec. 735, 241 N. E. 2d 371. Tucker, supra, involved an employee who had been union steward receiving and processing grievances of members and who was refused employment when he declined to purchase or lease a truck in line with his duties as truck driver for Tucker Freight Lines, Inc. This court held in Tucker Freight Lines, Inc. v. Konkle, supra, that the employee in Tucker did not exhaust his grievance procedures and was not entitled to recover against the employer in court action. The present case may be distinguished from Tucker Freight Lines, Inc. v. Konkle, supra, in that nowhere in Tucker do we find any mention of the Union’s wrongful refusal to process an appeal for the discharged employee.

*52 The uncontroverted evidence in the case before us clearly demonstrates that the actions and words of the Union officials, as far as Landaw was concerned, would have made any appeal fruitless and, at the most, a hollow gesture. Equity has long held that it will look to substance of a situation and not to the form; nor does equity require to be done that which is fruitless. Cantwell v. Cantwell (1957), 237 Ind. 168, 143 N. E. 2d 275; Kerfoot v. Kessener (1949), 227 Ind. 58, 84 N. E. 2d 190.

Furthermore, the United States Supreme Court in Vaca v. Sipes (1967), 386 U. S. 171, at 185-186, 87 S. Ct. 903, 17 L. Ed. 2d 842, stated:

“We think that another situation when the employee may seek judicial enforcement of his contractual rights arises if, as is true here, the union has sole power under the contract to invoke the higher stages of the grievance procedure, and if, as is alleged here, the employee-plaintiff has been prevented from exhausting his contractual remedies by the union’s wrongful refusal to process the grievance. It is true that the employer in such a situation may have done nothing to prevent exhaustion of the exclusive contractual remedies to which he agreed in the collective bargaining agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walter v. Balogh
619 N.E.2d 566 (Indiana Supreme Court, 1993)
Commissioner of Labor v. Talbert Manufacturing Co.
593 N.E.2d 1229 (Indiana Court of Appeals, 1992)
McBride v. Cox
567 N.E.2d 130 (Indiana Court of Appeals, 1991)
Thompson v. Modernfold Industries
373 N.E.2d 916 (Indiana Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
263 N.E.2d 756, 148 Ind. App. 48, 76 L.R.R.M. (BNA) 2029, 1970 Ind. App. LEXIS 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/landaw-v-tucker-freight-lines-inc-indctapp-1970.