Landau v. Fred Schmitt Contracting Co.

179 S.W.2d 138, 237 Mo. App. 908, 1944 Mo. App. LEXIS 180
CourtMissouri Court of Appeals
DecidedApril 4, 1944
StatusPublished
Cited by6 cases

This text of 179 S.W.2d 138 (Landau v. Fred Schmitt Contracting Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Landau v. Fred Schmitt Contracting Co., 179 S.W.2d 138, 237 Mo. App. 908, 1944 Mo. App. LEXIS 180 (Mo. Ct. App. 1944).

Opinion

*912 HUGHES, P. J.

Appellant filed this suit to recover on account of damages alleged to have resulted to an apartment building owned by him by reason of blasting operations conducted by the respondent. The trial below, before the court and a jury, resulted in. a verdict and judgment in favor of the respondent, and this appeal followed. We will herein refer to the parties as plaintiff and defendant, according to the position they occupied below, and narrate the facts with a few changes as contained in respondent’s printed-statement.

*913 Plaintiff, in his petition, alleged that his property consisted of a three-family brick apartment with a brick garage and concrete driveway, located at 6401 Cates avenue, University City; that the property was located immediately south of the River Des Peres; that the City of University City and the Public Works Administration had entered into a contract to share the cost of constructing the River Des Peres drainage canal, on condition that the. bids, contracts, insurance, bonds and supervision of the project should comply with the requirements of the Public Works Administration; that pursuant to the agreement University City advertised for bids, and that the defendant was the successful bidder. Plaintiff further alleged that defendant entered into a contract with University City for the construction of the sewer project through University City, and that the defendant agreed to comply with the requirements of the Public Works Administration; that the contract included provisions for the protection of adjacent property, care in the use of explosives and a provision that any damage caused to adjacent property should be promptly repaired by the contractor. That defendant entered into the construction of the sewer and in the course of the work used dynamite and other explosives; that vibrations caused by the blasting damaged plaintiff’s property in the amount of $5700, for which sum plaintiff prayed judgment.

Defendant’s second amended answer to plaintiff’s petition was filed on January 29, 1942. Therein defendant, after a general denial, pleaded that plaintiff negligently failed to brace the structures on his land, after notice of defendant’s intention to excavate; further, that plaintiff held the policies of tw'o insurance companies, insuring plaintiff’s property against damage by explosion; that he brought suit against one of the companies and recovered a judgment of $2650; that after the defendant’s motion for a new trial had been overruled in said suit, on December 29, 1941, said insurance company paid plaintiff a sum in excess of the damages, if any, referred to in his petition, and that plaintiff assigned and transferred the alleged cause of action mentioned in his petition and any and all right, title and interest therein to said insurance company, and that the latter was the sole owner and holder of the cause of action, if any, and was the real party in interest.

On January 31, 1942, two days after defendant filed the foregoing answer, plaintiff signed a paper entitled “loan agreement’’ introduced in evidence as Plaintiff’s Exhibit A.

On April 21, 1942, plaintiff filed a reply to said answer, and a motion for á separate trial of the issue of. assignment set up therein, alleging that the trial of this issue would require the attendance of witnesses and the production of documents distinct from those required for the trial of the principal issue; that the defendant was aware that the allegation of assignment made by the answer was untrue and could not be substantiated, and that the issue was colorable and would confuse *914 the jury at the trial. The motion was submitted to the court and was overruled by the court on June 16, 1942.

On October 15, 1942, plaintiff filed his second amended reply to said answer, consisting of a general denial, and a plea that defendant by its contract had agreed to protect adjacent property from damage; that the cost of restoring adjacent property was included in the sum defendant had bid and received for the work, and that the contract relieved adjoining owners from any requirement to protect their property.

"When the ease was called for trial, on November 16, 1942, before the voir dire examination of the jury, plaintiff’s counsel offered to introduce evidence to show that there had been no • assignment of the plaintiff’s cause of action to the insurance companies.

Defendant’s counsel objected to any evidence being offered at that time, on the ground that such evidence would not be competent or binding on the defendant, in that the offer concerned an issue raised by the pleadings and which had been adjudicated by the court, and further that there was no rule permitting the introduction of evidence at that stage of the case. The court sustained defendant’s objection, but permitted plaintiff to make an offer of proof. A colloquy ensued in which plaintiff’s two attorneys, defendant’s attorney and the court participated. Plaintiff’s counsel admitted that plaintiff had sued the two insurance companies to recover his damage, and had recovered a verdict and judgment in one of the cases, but denied that the plaintiff had assigned his cause of action. He stated that the insurance companies and plaintiff had entered into a “loan agreement,” whereupon the .judgment obtained by plaintiff against the one insurance company had' been set aside, and the cases dismissed. Defendant’s counsel objected to the offer of proof on the ground that such proof could not affect the issues raised by the pleadings; that the answer had been attacked by motion, that the motion had been overruled and the question thereby adjudicated. Counsel further objected to the offer of proof because defendant was not bound by the terms of the written instrument, and that the real terms of the agreement would be an issue of fact for the jury. Plaintiff’s counsel charged that defendant had no evidence to sustain the defense that the plaintiff was not the real party in interest, and defendant’s counsel stated that if he could prove the facts in plaintiff’s case that would be sufficient.

The court in the course of the colloquy stated a number of reasons for his ruling rejecting the offer of proof. He stated that the plaintiff had asked for a separate trial of the issue, and that the court at a prior term had ruled on the motion, and that such ruling was binding. The court further stated that whether the agreement between plaintiff and the insurance companies was a loan agreement, a settlement or an *915 assignment was a question for the jury, upon which the defendant’s counsel had a right to cross-examine the plaintiff.

After plaintiff’s offer of proof had beemrejected Mr. Wehrle, one of plaintiff’s counsel, made an objection to any statement that defendant’s counsel might make on voir dire examination or opening statement to the jury, or any questions addressed to any witness, or any offer to introduce any testimony of any facts relating to the plaintiff’s cases against the insurance companies, on the ground that such matter was incompetent, immaterial and irrelevant to any of the issues, highly prejudicial to the plaintiff, and would inject a false and fictitious issue into the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilson v. Bob Wood & Associates, Inc.
633 S.W.2d 738 (Missouri Court of Appeals, 1981)
Hayes v. Jenkins
337 S.W.2d 259 (Missouri Court of Appeals, 1960)
Epstein v. City and County of Denver
293 P.2d 308 (Supreme Court of Colorado, 1956)
Monsanto Chemical Co. v. American Bitumuls Co.
249 S.W.2d 428 (Supreme Court of Missouri, 1952)
Standard Brands, Inc. v. Bateman
184 F.2d 1002 (Eighth Circuit, 1950)
Kinsella v. Kinsella
183 S.W.2d 905 (Supreme Court of Missouri, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
179 S.W.2d 138, 237 Mo. App. 908, 1944 Mo. App. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/landau-v-fred-schmitt-contracting-co-moctapp-1944.