Lamb v. Wahlenmaier

77 P. 765, 144 Cal. 91, 1904 Cal. LEXIS 658
CourtCalifornia Supreme Court
DecidedJuly 9, 1904
DocketL.A. No. 1233.
StatusPublished
Cited by48 cases

This text of 77 P. 765 (Lamb v. Wahlenmaier) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamb v. Wahlenmaier, 77 P. 765, 144 Cal. 91, 1904 Cal. LEXIS 658 (Cal. 1904).

Opinion

HARRISON, C.

The plaintiff entered into a contract with the defendant Wahlenmaier for the construction of a building in Los Angeles at the agreed price of $6,277, and at the same time Wahlenmaier and his co-defendant, the Fidelity and Deposit Company, of Maryland, as his surety, executed a bond to the plaintiff for the faithful performance by him of his contract. The bond provided that Wahlenmaier should also cancel and release the building from all claims or liens that might accrue against it from the performance of the contract, and should save the plaintiff herein harmless from all damage thereby. Wahlenmaier abandoned work upon the building before it was completed, and thereafter the plaintiff finished its construction. The plaintiff paid to Wahlenmaier $2,577 before he abandoned the work, and afterwards paid $4,360 in discharge of liens for materials and labor furnished and employed in its construction at the request of Wahlenmaier. The present action is brought upon the above-named bond to recover the amount paid by the plaintiff in discharge of liens in excess of the contract price for constructing the building.

The contract for the construction of the building was not filed in the recorder’s office. Prior to the commencement of this action, but after the building had been completed, Wahlenmaier brought an action against the plaintiff to recover from him the reasonable value of the labor performed and materials furnished by him in its construction, alleging the same to be $8,448. In his answer to the complaint in that action the plaintiff herein alleged that Wahlenmaier had contracted with him to construct the building for the sum of $6,277; that the labor and materials furnished by him in its construction were under and by virtue of said contract; and that the said sum was the reasonable value of the labor and materials furnished by him. He also set forth in his answer *93 the abandonment by Wahlenmaier of his contract, and alleged that prior to such abandonment he had paid him the sum of $2,577, and that in order to protect his property from mechanics’ liens and foreclosure for materials and labor, and to complete the building, he had paid, and was compelled to pay, materialmen and laborers $4,360; that by reason of such payments there was due and unpaid from Wahlenmaier to him the full sum of $1,236.69, “said sum being in excess of the contract price and the reasonable value of said labor and materials,” for which amount he asked judgment against Wahlenmaier. Upon the trial of that action the court held that the contract for constructing the building was void by reason of the failure of the parties to sign the plans and specifications annexed thereto; that for this reason Wahlenmaier was entitled to recover the expenditures made by him in its construction and the reasonable value of his services therein, and found that the same amounted to $2,767.95; that the plaintiff herein had paid to and for him the sum of $2,925, and had also paid the sum of $4,360 in discharge of valid and subsisting liens filed against the building; that Wahlenmaier had thereby been fully paid for the construction of the building. The court thereupon rendered judgment that Wahlenmaier take nothing by his action, and that Lamb, the plaintiff herein, recover his costs from- him, but did not render any judgment in favor of Lamb upon his claim to recover "from Wahlenmaier the amount paid for the discharge of the liens in excess of the contract price.

The defendants herein have pleaded the judgment in that action in bar of the plaintiff’s right of recovery. The superior court held that it was a bar in favor of Wahlenmaier, but not in favor of the surety company, and rendered judgment against the latter and in favor of the plaintiff for $691. The surety company has appealed.

The rule formulated by Lord Chief Justice De Grey in the Duchess of Kingston’s ease, and frequently repeated in other cases, that “The judgment of a court of concurrent jurisdiction directly upon a point is, as a plea, a bar, or as evidence conclusive between the same parties upon the same matter directly in question in another court,” has been substantially reproduced in section 1908 (subd. 2) of the Code of Civil Procedure of this state. The estoppel thus created is not *94 limited to an action which is identical in form with the former action, or where the same parties are plaintiff and defendant in each of the actions, hut may be invoked whenever, in the second action, the parties are in privity with the parties to the first action and the same issue is presented for determination which was determined in the former action. As between the parties to the action, the judgment therein is an estoppel as to all matters which are actually and necessarily included in the judgment. (Code Civ. Proc., sec. 1911.) The determination in the former action of an issue presented on the part of the defendant therein by way of counterclaim, or in recoupment, or by way of a cross-complaint against the plaintiff, is res judicata, as fully as if determined in a separate and independent action brought by the defendant against the plaintiff. (Freeman on Judgments, see. 282; Black on Judgments, sec. 761; Taylor on Evidence, 9th ed., sec. 1699; Timmons v. Dunn, 4 Ohio St. 680; Howell v. Goodrich, 69 Ill. 536; Litch v. Clinch, 136 Ill. 410; McNicholas v. Lake, 13 Colo. App. 164; Ehle v. Bingham, 7 Barb. 494; Baker v. Stinchfield, 57 Me. 363; South and North etc. R. R. Co. v. Heinlein, 56 Ala. 368; Jemvison v. West Springfield, 13 Gray, 544.)

The liens, for whose payment in excess of the contract price for constructing the building the plaintiff now seeks to recover from the defendants, are the same liens which were set forth by him in the former action in support of his claim against Wahlenmaier. In that action he presented to the court, as an issue to be tried and determined, his right to recover from Wahlenmaier the amount of money paid by him upon these liens in excess of the contract price for constructing the building, and asked for a judgment therefor against Wahlenmaier. His right to recover this excess was thus brought into judicial investigation, and at the trial evidence was presented by him to the court in support of his demand, and the court found that he had paid the liens to the extent claimed by him, but refused to give him judgment therefor upon the ground that, as the contract was invalid, Wahlenmaier was entitled to the entire value of the labor and materials used in the construction of the building, irrespective of the price named in the contract. The omission of the court to give him any relief for the payment of this excess was, in its legal effect, an adjudication that he was not entitled to *95 relief therefor. (Thompson v. McKay, 41 Cal. 221.) The court erred in giving this judgment (Laidlaw v. Marye, 133 Cal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grande v. Eisenhower Medical Center
California Supreme Court, 2022
Meridian Financial etc. v. Phan
California Court of Appeal, 2021
Proctor v. Vishay Intertechnology, Inc.
213 Cal. App. 4th 1258 (California Court of Appeal, 2013)
Bennett v. Leatherby
3 Cal. App. 4th 449 (California Court of Appeal, 1992)
Lunsford v. Kosanke
295 P.2d 432 (California Court of Appeal, 1956)
Brewer v. King
293 P.2d 126 (California Court of Appeal, 1956)
McNulty v. Copp
271 P.2d 90 (California Court of Appeal, 1954)
M. H. Golden Construction Co. v. El Centro Properties, Inc.
246 P.2d 942 (California Court of Appeal, 1952)
Greenfield v. Mather
194 P.2d 1 (California Supreme Court, 1948)
McManus v. Bendlage
187 P.2d 854 (California Court of Appeal, 1947)
Scarbourough v. Briggs
183 P.2d 683 (California Court of Appeal, 1947)
Denio v. City of Huntington Beach
168 P.2d 785 (California Court of Appeal, 1946)
Pellett v. Sonotone Corp.
160 P.2d 783 (California Supreme Court, 1945)
People v. Gorman
158 P.2d 267 (California Court of Appeal, 1945)
Panos v. Great Western Packing Co.
134 P.2d 242 (California Supreme Court, 1943)
MacDonnell v. Capital Co.
130 F.2d 311 (Ninth Circuit, 1942)
Shannon v. General Petroleum Corp.
118 P.2d 881 (California Court of Appeal, 1941)
Rahming v. MacKey
187 So. 579 (Supreme Court of Florida, 1939)
Security Investment Co. v. Bieg-Hoffine Co.
83 P.2d 297 (California Court of Appeal, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
77 P. 765, 144 Cal. 91, 1904 Cal. LEXIS 658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamb-v-wahlenmaier-cal-1904.