Lamb v. D.S. Duggins Welding, Inc.

729 S.E.2d 724, 222 N.C. App. 52, 2012 WL 3174068, 2012 N.C. App. LEXIS 932
CourtCourt of Appeals of North Carolina
DecidedAugust 7, 2012
DocketNo. COA12-129
StatusPublished
Cited by1 cases

This text of 729 S.E.2d 724 (Lamb v. D.S. Duggins Welding, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamb v. D.S. Duggins Welding, Inc., 729 S.E.2d 724, 222 N.C. App. 52, 2012 WL 3174068, 2012 N.C. App. LEXIS 932 (N.C. Ct. App. 2012).

Opinion

BRYANT, Judge.

Where a sub-subcontractor completed its work on a construction project and the work was accepted by the general contractor, and where the condition of the work as completed by the sub-subcontractor was changed by the general contractor after the work had been accepted, the completed and accepted work doctrine applies to bar the recovery of damages in a negligence action by an employee of the general contractor against the sub-subcontractor.

Facts and Procedural History

This case arises out of an accident at a construction site that occurred on 18 December 2008. Evidence gathered during discovery reveals that plaintiff Jason B. Lamb (“Lamb”) has been employed by Lomax Construction, Inc. (“Lomax”) since 1999. In 2008, Lomax [53]*53assigned Lamb to be site superintendent on a construction project to put an addition on the High Point Public Library in High Point, North Carolina. Lomax subcontracted with D.S. Duggins Welding, Inc. (“Duggins”) to install the steel decking on the project. In turn, Duggins subcontracted the installation of the steel decking to Mabe Steel, Inc. (“Mabe”).

During the installation of the steel decking, Duggins requested that Mabe also install a perimeter safety cable, as required by OSHA regulations. OSHA regulations require a safety cable to be installed at a height of forty-two (42) inches above the walking level and that the cable is able to withstand a force of at least 200 pounds in any outward or downward direction without deflecting more than three (3) inches. When Mabe installed the perimeter safety cable on the third floor, Mabe terminated the end of the cable by wrapping it around a vertical column near the wall of the existing structure and secured it with clamps and a turnbuckle. On the columns between the termination points, Mabe threaded the cable through pre-existing holes in the columns or, where there were no pre-existing holes, field welded nuts to the columns and threaded the cable through the holes in the nuts. The purpose of threading the cable through columns and nuts was to maintain the cable at the required height of forty-two (42) inches above the walking level. Mabe completed the installation of the steel decking and perimeter safety cable by 13 October 2008.

At some point after Mabe left the construction project, the column to which Mabe terminated the third floor safety cable was removed. As a result, Lomax employees moved the termination point of the third floor safety cable to an adjacent column at the direction of Lamb. However, instead of wrapping the cable around the column and securing it, as it was previously terminated by Mabe, the Lomax employees terminated the safety cable to a nut Mabe had welded onto the column.

As site superintendent of the construction project, one of Lamb’s duties was to inspect the perimeter safety cables. Lamb performed this duty everyday. On 18 December 2008, Lamb was testing the deflection of the third floor safety cable by applying weight to it when the weld attaching the nut to the column broke and the cable fell slack. As a result, Lamb lost his balance and fell over the edge of the third floor to the ground below, sustaining severe injuries.

Lamb and his wife, Andrea Lamb, filed suit against Duggins and Mabe on 30 August 2010 in Randolph County Superior Court alleging [54]*54negligence and loss of consortium. Mabe timely answered plaintiffs’ complaint on 10 November 2010. Duggins failed to answer plaintiffs’ complaint and upon plaintiffs’ filing of a motion and affidavit for entry of default on 5 November 2010, entry of default was entered against Duggins. Following a period of discovery, Mabe filed a motion for summary judgment on 8 September 2011 on the grounds that plaintiffs’ claims against Mabe “are barred by the principles surrounding the completed and accepted work doctrine, by the applicable case precedent concerning the legal responsibility of a contractor to the employees of another contractor, and by principles of proximate cause as a matter of law.” Following a 31 October 2011 hearing, Judge Long granted Mabe’s motion for summary judgment on 8 November 2011. The order was filed 10 November 2011. Plaintiffs appeal.

On appeal, plaintiffs raise the issue of whether the trial court erred in granting Mabe’s Motion for Summary Judgment.

“Summary judgment is a device whereby judgment is rendered if the pleadings, depositions, interrogatories, and admissions on file, together with any affidavits, show that there is no genuine issue as to any material fact and that any party is entitled to judgment as a matter of law.” Dalton v. Camp, 353 N.C. 647, 650, 548 S.E.2d 704, 707 (2001) (citation omitted). The purpose of summary judgment is to “eliminate the necessity of a formal trial where only questions of law are involved and a fatal weakness in the claim of a party is exposed.” Id. (citation omitted).

“Our standard of review of an appeal from summary judgment is de novo; such judgment is appropriate only when the record shows that ‘there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.’ ” In re Will of Jones, 362 N.C. 569, 573, 669 S.E.2d 572, 576 (2008) (quoting Forbis v. Neal, 361 N.C. 519, 523-24, 649 S.E.2d 382, 385 (2007)). “On appeal from summary judgment, we review the evidence in the light most favorable to the nonmoving party.” Griggs v. Shamrock Bldg. Services, Inc., 179 N.C. App. 543, 546, 634 S.E.2d 635, 637 (2006) (citation omitted). “If the trial court grants summary judgment, the decision should be affirmed on appeal if there is any ground to support the decision.” Nifong v. C.C. Mangum, Inc., 121 N.C. App. 767, 768, 468 S.E.2d 463, 465 (1996) (citing Shore v. Brown, 324 N.C. 427, 428, 378 S.E.2d 778, 779 (1989)).

[55]*55“In a negligence action, summary judgment for defendant is proper where the evidence fails to establish negligence on the part of defendant, establishes contributory negligence on the part of plaintiff, or establishes that the alleged negligent conduct was not the proximate cause of the injury.” Hahne v. Hanzel, 161 N.C. App. 494, 497-98, 588 S.E.2d 915, 917 (2003) (emphasis and citation omitted). However, “[a]s a general proposition, issues of negligence are ordinarily not susceptible of summary adjudication either for or against the claimant but should be resolved by trial in the ordinary manner.” Vassey v. Burch, 301 N.C. 68, 73, 269 S.E.2d 137, 140 (1980) (internal quotation and citation omitted). But, “where the facts are undisputed, ‘[t]he issue of whether a duty exists is a question of law for the court.’ ” Finley Forest Condominium Ass’n v. Perry, 163 N.C. App. 735, 739, 594 S.E.2d 227, 230 (2004) (citation omitted).

In the case sub judice, the material facts are undisputed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
729 S.E.2d 724, 222 N.C. App. 52, 2012 WL 3174068, 2012 N.C. App. LEXIS 932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamb-v-ds-duggins-welding-inc-ncctapp-2012.