Finley Forest Condominium Ass'n v. Perry

594 S.E.2d 227, 163 N.C. App. 735, 2004 N.C. App. LEXIS 570
CourtCourt of Appeals of North Carolina
DecidedApril 20, 2004
DocketCOA03-155
StatusPublished
Cited by19 cases

This text of 594 S.E.2d 227 (Finley Forest Condominium Ass'n v. Perry) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Finley Forest Condominium Ass'n v. Perry, 594 S.E.2d 227, 163 N.C. App. 735, 2004 N.C. App. LEXIS 570 (N.C. Ct. App. 2004).

Opinion

McGEE, Judge.

Finley Forest Condominium Association, Inc. (plaintiff} appeals from summary judgment entered in favor of DHC Construction, Inc. (defendant).

*736 Pursuant to plaintiff’s Declaration of Condominium, filed in Orange and Durham counties, plaintiff is responsible for the maintenance and repair of common property of the condominium. Plaintiff contracted in the fall of 2000 with James Kramer (Kramer), an engineer, to draft plans and specifications for the replacement of roofs on five buildings, numbered 26, 27, 28, 47, and 52. Each building contained several individual condominium units. Plaintiff wished to replace the flat style roof of the buildings with a pitched roof in order to prevent future water damage. Once the plans were completed and approved by plaintiff’s board of directors, the speci-. fications were submitted for bid to general contractors licensed in North Carolina.

Plaintiff contracted on 20 August 2001 with Bill Perry and Wayne Denton, doing business as Neuse River Construction (Neuse River), to replace the roofs in accordance with the specifications drawn up by Kramer. Unbeknownst to plaintiff, Neuse River hired DHC Construction, Inc. (DHC) as a subcontractor to install pre-manufactured trusses and to lay plywood over the trusses on the roofs of buildings 47 and 52. Neuse River informed DHC that another party would lay tarpaper over the plywood and install the roof shingles. According to the agreement, DHC was to complete the framing by 2 September 2001 and DHC would be penalized for any delay thereafter. All construction materials were supplied by Neuse River. The record on appeal does not include a copy of the contract between Neuse River and DHC.

DHC arrived at the job site on 30 August 2001 to begin work on buildings 47 and 52. At that time, several Neuse River employees had already begun to remove a significant portion of the rubber membrane that served to weatherproof the flat roof of building 52. In addition, some plywood had been cut away. DHC assisted Neuse River in removing the remaining plywood on building 52 in order that plaintiff could begin installation of the support system necessary for the new trusses.

Meanwhile, on building 47, Neuse River employees had removed two feet of the rubber membrane from around the roof’s perimeter. DHC employees assisted Neuse River employees in laying two-by-eight lumber around the sides of the roof. In addition, DHC employees were engaged in modifying the pre-manufactured trusses provided by Neuse River because the trusses were not the correct size for the project.

*737 In the early afternoon, a heavy rain storm caused substantial water damage to buildings 47 and 52, damaging the eight units in each building. At the time of the storm, portions of buildings 47 and 52 were covered by tarps supplied by Neuse River. Bill Perry, a foreman with Neuse River attempted to purchase additional tarps at the time of the storm. At the request of Neuse River, DHC employees assisted in laying the tarps.

Following the rain storm, DHC employees left the job site and did not return until the next day, 31 August 2001. At that time, DHC employees completed laying the plywood on building 52 and agreed with Neuse River to lay the tarpaper over the plywood. Over the course of the next two days, DHC agreed to Neuse River’s additional requests that DHC remove the remaining rubber membrane and plywood on building 47, prepare the roof for the new trusses, and lay the tarpaper. DHC completed all the work initially covered by the original contract and all the work negotiated thereafter by Neuse River.

Neuse River eventually abandoned the project and plaintiff hired another contractor to complete the work detailed in plaintiffs contract with Neuse River. The contractor also repaired the damage resulting from the water intrusion to the common areas and individual units of buildings 47 and 52.

According to the testimony of Kramer and others, the weather forecast on 30 August 2001 had called for thunderstorms. A light rain preceded the heavy storm that day. Kramer, who was unaware of DHC’s involvement, raised his concern to individuals on the job site that the roofs were not adequately protected in the event of rain.

The specifications for the project, as incorporated in the contract between plaintiff and Neuse River, explicitly required that all work be left weathertight each night. According to the written agreement, the general contractor was responsible for all weather damage when the building was left exposed to the elements. The possibility of thunderstorms in the summer months was noted in the contract.

Plaintiff filed a complaint on 22 October 2001 asserting numerous claims against Neuse River and DHC. Neuse River failed to file an answer and an entry of default was made against Neuse River. Neuse River is not a party to this appeal. Both plaintiff and DHC filed motions for summary judgment. The trial court granted summary judgment in favor of DHC and taxed costs against plaintiff. Plaintiff appeals.

*738 Plaintiff first assigns error to the trial court’s alleged admission and consideration of DHC’s expert affidavits in determining summary judgment. DHC submitted the affidavits at issue in opposition to plaintiff’s motion for partial summary judgment and in support of DHC’s own motion for summary judgment.

Plaintiff filed an objection and a motion to strike the affidavits on the grounds that the affidavits failed to comply with the requirements of Rule 56 of the North Carolina Rules of Civil Procedure. According to the record, the trial court never ruled on plaintiff’s objection and motion to strike the affidavits. This Court is unable to review the issue concerning the trial court’s admission and consideration of the affidavits since there is nothing before this Court indicating the trial court’s ruling on the question. N.C.R. App. P. 10(b)(1) provides that in order to preserve a question for appellate review, it is “necessary for the complaining party to obtain a ruling upon the party’s request, objection or motion.” Because plaintiff failed to obtain such a ruling, plaintiff’s assignment of error number one is overruled.

Plaintiff next contends the trial court erred in denying plaintiff’s motion for partial summary judgment and in granting DHC’s motion for summary judgment as to the issue of liability.

N.C. Gen. Stat. § 1A-1, Rule 56(c) (2003) proscribes that summary judgment is appropriate only “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue of material fact and that any party is entitled to a judgment as a matter of law.” An issue is deemed genuine “if it is supported by substantial evidence,” DeWitt v. Eveready Battery Co., 355 N.C. 672, 681, 565 S.E.2d 140, 146 (2002), and “a fact is material if it would constitute or would irrevocably establish any material element of a claim or a defense.” Bone International, Inc. v. Brooks, 304 N.C. 371, 375, 283 S.E.2d 518, 520 (1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Long v. Fowler
Court of Appeals of North Carolina, 2024
Fearrington v. City of Greenville
Court of Appeals of North Carolina, 2022
Glenn v. Johnson
787 S.E.2d 65 (Court of Appeals of North Carolina, 2016)
Sims v. Graystone Ophthalmology Associates, P.A.
757 S.E.2d 925 (Court of Appeals of North Carolina, 2014)
Henslee v. N.C. Dep't of Pub. Safety
Court of Appeals of North Carolina, 2014
Lamb v. D.S. Duggins Welding, Inc.
729 S.E.2d 724 (Court of Appeals of North Carolina, 2012)
Baltzell v. Dowdy
690 S.E.2d 558 (Court of Appeals of North Carolina, 2010)
Mason v. Dwinnell
660 S.E.2d 58 (Court of Appeals of North Carolina, 2008)
In re Z.J.T.B.
645 S.E.2d 206 (Court of Appeals of North Carolina, 2007)
In Re Me. B.
640 S.E.2d 407 (Court of Appeals of North Carolina, 2007)
State v. McDougald
638 S.E.2d 546 (Court of Appeals of North Carolina, 2007)
Walden v. Morgan
635 S.E.2d 616 (Court of Appeals of North Carolina, 2006)
Gilreath v. North Carolina Department of Health & Human Services
629 S.E.2d 293 (Court of Appeals of North Carolina, 2006)
In Re Estate of Redding v. Welborn
612 S.E.2d 664 (Court of Appeals of North Carolina, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
594 S.E.2d 227, 163 N.C. App. 735, 2004 N.C. App. LEXIS 570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/finley-forest-condominium-assn-v-perry-ncctapp-2004.