Lamar Contractors, Inc. v. Kacco, Inc.

189 So. 3d 394, 2016 WL 2337957, 2016 La. LEXIS 1064
CourtSupreme Court of Louisiana
DecidedMay 3, 2016
Docket2015-C -1430
StatusPublished
Cited by11 cases

This text of 189 So. 3d 394 (Lamar Contractors, Inc. v. Kacco, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamar Contractors, Inc. v. Kacco, Inc., 189 So. 3d 394, 2016 WL 2337957, 2016 La. LEXIS 1064 (La. 2016).

Opinions

PER CURIAM,

Bin this case, we are called upon to decide whether the district court erred in reducing plaintiffs damage ’ award based on a finding that plaintiffs actions contributed to defendant’s breach of contract. For the reasons that follow, we vacate the judgment insofar as it reduced plaintiffs award.

UNDERLYING FACTS AND PROCEDURAL HISTORY

For purposes of the issue before us, the facts are largely undisputed. Lamar Contractors,' Inc. (“Lamar”) was general contractor on a construction project. Lamar entered into a subcontract with Kacco, Inc. (“Kacco”) to provide metal framing and drywall work on a construction project. The subcontract included a “pay-if-paid” payment provision, which afforded Lamar teái days to remit payment to its subcontractors after receipt of payment from the owner.

Kacco began work on the project in October 2010 but experienced recurring problems with providing manpower and paying for supplies.1 Kacco worked [396]*396through |2November and December. Toward the end of November, Kacco submitted an invoice for work performed that month. The invoice submitted at the end of December reflected that forty-five percent of the work had been performed. Lamar issued a check to Kacco on December 30, 2010.2 Notably, Lamar made this payment prior to receiving payment from the owner.3

On January 13, 2011, Lamar sent another email to Kacco addressing continuing concerns with Kacco’s ability to perform its work under the contract. Kacco responded to Lamar’s concerns regarding manpower and materials and asked to be aliowed to finish the job. Kacco then continued working on site, completing the metal framing and stud work. Lamar inspected the work and found some deficiencies, which were noted on a punch list.

On January 31, 2011, Kacco notified Lamar that Kacco was waiting on the payment of its December invoice to pay the supplier and order the necessary supplies to complete the punch list. Lamar had received payment from the owner on January 26, 2011; however, pursuant to the subcontract, Lamar was not required to make payment to Kacco until February 9, 2011, ten business days later.

On February 3, 2011, Lamar sent notice to Kacco stating that Kacco’s subcontract would be terminated if Kacco did not provide sufficient manpower and materials within forty-eight hours. Kacco did not respond to Lamar or return to the job site. Lamar officially terminated Kacco’s subcontract in a letter dated February |a5, 2011. After termination of the subcontract with Kacco, Lamar hired another contractor to complete the work.

Subsequently, Lamar filed a breach of contract suit against Kacco. It alleged that Kacco breached the contract between the parties and that this breach caused damages. Lamar also sought attorney’s fees and costs.

Kacco filed a reconventional demand against Lamar, alleging Lamar failed to pay Kacco for work performed under the contract. Kacco also alleged Lamar’s failure to pay Kacco as needed caused Kacco to breach. Kacco also sought attorney’s fees and costs.

After a bench trial, the district court entered judgment on the main demand for Lamar in the amount of $24,116.67 with interest from demand, plus attorney’s fees in the amount of $7,681.75 and costs in the amount of $3,105.81. Additionally, the dis[397]*397trict court entered a judgment in the amount of $60,020.00 plus interest from demand in favor of Kacco on the reconven-tional demand.4

In written reasons for judgment, the district court made a finding of fact that Kacco breached the contract between the parties by failing to provide sufficient materials to complete the job. However, citing La. Civ.Code art.2003, the district court found Lamar negligently withheld payments for completed work performed by Kacco, which contributed to Kacco’s breach. As a result, the district court concluded that Lamar’s negligence contributed to Kacco’s failure to perform and reduced Lamar’s damages in proportion to this negligence.

Lamar appealed the judgment. The court of appeal affirmed the judgment in its entirety. Lamar Contractors, Inc. v. Kacco, Inc., 14-1360 (La.App. 4 Cir. 7/1/15), 174 So.3d 82.

|4Upon Lamar’s application, we granted certiorari to review the correctness of this decision. Lamar Contractors, Inc. v. Kacco, Inc., 15-1430 (La.11/20/15), 180 So.3d 312. The sole issue presented for our consideration is whether the district court erred in reducing Lamar’s, damages for breach of contract based on a finding that Lamar’s negligence' contributed to Kacco’s bréaeh of the contract.5

DISCUSSION

At the outset, we find no manifest error in the district court’s findings that Kacco breached its subcontract with Lamar and that Lamar was entitled to damages as a result of that breach. Rather, our sole focus is on whether Lamar’s actions during the relevant time frame contributed to that breach for purposes of La. Civ.Code art. 2003. That article provides:

An obligee may not recover damages when his own bad faith has caused the obligor’s failure to perform or when, at the time of the contract, he has concealed from the obligor facts that he knew or should have known would cause a failure.
If the obligee’s negligence contributes to the obligor’s failure to perform, the damages are reduced in proportion to that negligence, [emphasis added].

LThis obligation is correlative .to the general duty imposed by La. Civ.Code art. 1983, which requires “[contracts must be performed in good’faith.” Professor Litvi-noff discussed the meaning of good faith in a contractual context as follows:

[398]*398Another attempt to explain the meaning of good faith focuses on the benefits or advantages parties expect to derive from their contracts. In that approach, besides abstention from malice, good faith demands from' each party abstention from any action or inaction that may prevent the other from obtaining the benefit that the latter warrantedly expected to obtain. That view is carried a step forward when the assertion is added that the duty of good faith may not only proscribe undesirable conduct, but may also require each party to take affirmative action to cooperate in the attainment of his goals by the other.... In sum, a promisee must not only, not hinder the rendering of performance by his promisor, but also do whatever is necessary to enable the promisor to perform.
In civil-law terminology that view could be expressed by saying that an obligee, especially one who is also an obligor of a reciprocal obligation, should not only abstain from contributing to the failure of the cause of his obligor’s obligation, but must do'as much as he can to allow that cause to remain, if possible, intact during the life of the .contract.
Saul Litvinoff, Good Faith, 71 TUL. L.REV. 1645 (1997).

Nonetheless, this general duty of good faith cannot be considered in isolation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
189 So. 3d 394, 2016 WL 2337957, 2016 La. LEXIS 1064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamar-contractors-inc-v-kacco-inc-la-2016.