Lake Ridge Apartments, LLC v. BIR Lakeridge, LLC

335 F. App'x 278
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 1, 2009
Docket08-1307
StatusUnpublished
Cited by2 cases

This text of 335 F. App'x 278 (Lake Ridge Apartments, LLC v. BIR Lakeridge, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Ridge Apartments, LLC v. BIR Lakeridge, LLC, 335 F. App'x 278 (4th Cir. 2009).

Opinion

Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

Lake Ridge Apartments, LLC (“Lake Ridge”) sued Berkshire Income Realty-OP, L.P. and BIR Lakeridge, LLC (collectively, “BIR”) for breach of a contract for the purchase and development of a parcel of land. The district court granted Lake Ridge’s summary judgment motion. After holding a bench trial on the issue of damages, the district court entered a judgment of $774,292 in favor of Lake Ridge. BIR now appeals the district court’s grant of summary judgment and the award of damages. For the reasons that follow, we affirm.

I.

This case arises out of a contract between BIR and Lake Ridge for the sale of property, as well as an amendment to that contract known as the “Sixth Amendment.” Under the contract, BIR would purchase an apartment complex from Lake Ridge, and Lake Ridge would build garages on the property for BIR. Under the Sixth Amendment, BIR agreed to purchase an additional parcel of land (“Parcel A-l”) for $234,000. Lake Ridge would “use its best efforts to construct on Parcel A-l an apartment building” of eighteen units. J.A. 24.

BIR agreed to pay $144,000 of the total cost for Parcel A-l at the closing of the parties’ general purchase and sale agreement on July 1, 2005. The Sixth Amendment set out several factual scenarios governing BIR’s obligation to pay the remaining $90,000 owed on the parcel. Each scenario was conditioned upon the further action of at least one of the parties. First, BIR could decide within 30 days of the parties’ closing — that is, by August 1, 2005 — to develop Parcel A-l itself. If it gave written notice to Lake Ridge before August 1, 2005, BIR could pay Lake Ridge the remaining $90,000 and Lake Ridge would “have no further rights or obligations with respect to Parcel A-l.” J.A. 25. Second, if BIR did not opt to develop Parcel A-l itself, Lake Ridge had one year to obtain the necessary building permits and approvals for the new eighteen-unit building to be con *281 structed on the parcel. If Lake Ridge delivered the necessary permits before June 30, 2006, BIR would pay the remaining $90,000. 1 Third, if BIR did not develop the property itself and Lake Ridge could not deliver the necessary permits and approvals by June 30, 2006, BIR had two options: BIR could choose to require Lake Ridge to buy back Parcel A-l for the original down-payment price of $144,000; or, BIR could choose to pay Lake Ridge $90,000 for Parcel A-l. If BIR did not provide notice of its decision between these two options by July 31, 2006, under the Sixth Amendment BIR would be “deemed to have elected” to pay Lake Ridge $90,000 for Parcel A-l. Id.

Lake Ridge contacted BIR several times in July and August 2005 to ascertain BIR’s plans for Parcel A-l, and the parties exchanged e-mails on possibly altering the architectural plans for the new building to be constructed on it. BIR did not exercise its option to develop Parcel A-l itself by the August 1, 2005 deadline. To the contrary, on October 13, 2005, BIR informed Lake Ridge that it “would like to proceed with the process of building the additional 18 units [on Parcel A-l].” J.A. 174.

In December, BIR decided that it would prefer for Lake Ridge to accept the $90,000 balance on Parcel A-l but cancel construction of both the new apartment building and the garages. BIR informed Lake Ridge on December 23, 2005 that it was “considering holding off’ the Parcel A-l development and “considering delaying construction of the garages” — both “until some undetermined point in the future.” J.A. 211. As to the Parcel A-l building, BIR asked, “[W]e will owe you a payout of +/- 90K if we elect not to build, correct?” Id.

Lake Ridge responded on January 5, 2006, confirming that $90,000 was due as to Parcel A-l, but stating that it would also request expenses and lost profits as to the garages. Lake Ridge asked BIR to “let us know as soon as possible which way Berkshire will be proceeding on these two items.” J.A. 211. On the same day, BIR informed Lake Ridge that it had decided to “hold[ ] off on proceeding” with both the Parcel A-l project and the garage project “until some undetermined point in the future.” Id. BIR promised to “initiate payment for the 90K” owed on Parcel A-l and requested an itemization of Lake Ridge’s costs for the garages. Id.

BIR began drafting a side letter agreement to memorialize its new intentions as to Parcel A-l and the garages. On March I, 2006, BIR sent Lake Ridge a proposed agreement under which BIR would pay Lake Ridge $90,000 and Lake Ridge “shall have no further rights or obligations with respect to Parcel A-l.” J.A. 50. Three weeks later, Lake Ridge declined to sign the agreement. It also indicated that it had been mistaken about the $90,000 payment owed for the Parcel A-l project. In addition to the $90,000 balance, Lake Ridge stated that it intended to seek out-of-pocket expenses and lost profits approximating $1.5 million because BIR had “committed to” the construction project. J.A. 225. BIR was unwilling to pay this amount, and the parties’ communications subsequently deteriorated.

By the June 30, 2006 deadline, Lake Ridge had neither applied for nor delivered the specified building permits. Consequently, BIR attempted to exercise its option of paying Lake Ridge $90,000 for *282 Parcel A-l. Lake Ridge returned the check and sued for breach of contract.

The district court granted summary judgment in favor of Lake Ridge, finding that BIR had anticipatorily breached the contract when it informed Lake Ridge in December 2005 and January 2006 that it wished to delay both construction projects for an undetermined period of time. The district court further found that Lake Ridge had been willing and able to perform its obligations under the contract and was entitled to damages. After holding a hearing, the district court awarded Lake Ridge $774,292 based on testimony from Lake Ridge corporate officers as to the construction costs associated with the projects and estimated lost profits.

BIR now appeals the district court’s grant of summary judgment, certain evi-dentiary decisions, and the grant of damages. We address these claims in turn.

II.

We review a district court’s grant of summary judgment de novo. Jennings v. Univ. of N.C., 482 F.3d 686, 694 (4th Cir.2007) (en banc) (citing Hill v. Lockheed Martin Logistics Mgmt., Inc., 354 F.3d 277, 283 (4th Cir.2004) (en banc)). We review a district court’s evidentiary decisions for abuse of discretion. Robinson v. Equifax Info. Servs., LLC, 560 F.3d 235, 240 n. 1 (4th Cir.2009). We review a district court’s factual findings at a bench trial for clear error. PCS Phosphate Co., Inc. v. Norfolk S. Corp., 559 F.3d 212, 217 (4th Cir.2009).

III.

BIR first argues that the district court erred in granting summary judgment in favor of Lake Ridge based on BIR’s alleged anticipatory breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
335 F. App'x 278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-ridge-apartments-llc-v-bir-lakeridge-llc-ca4-2009.