This text of Lake Conroe Medical Center, Ltd. A/K/A Lake Area Medical Center, L.P. A/K/A Lake Conroe Medical Center Management, Inc. v. KMT Building Company and Douglas Joslyn (Lake Conroe Medical Center, Ltd. A/K/A Lake Area Medical Center, L.P. A/K/A Lake Conroe Medical Center Management, Inc. v. KMT Building Company and Douglas Joslyn) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Conroe Medical Center, Ltd. A/K/A Lake Area Medical Center, L.P. A/K/A Lake Conroe Medical Center Management, Inc. v. KMT Building Company and Douglas Joslyn, (Tex. Ct. App. 2009).

Opinion

In The



Court of Appeals



Ninth District of Texas at Beaumont

____________________



NO. 09-07-00520-CV



LAKE CONROE MEDICAL CENTER, LTD. a/k/a LAKE AREA MEDICAL

CENTER, L.P. a/k/a LAKE CONROE MEDICAL CENTER

MANAGEMENT, INC., Appellant



V.



KMT BUILDING COMPANY AND DOUGLAS JOSLYN, Appellees

On Appeal from the 221st District Court

Montgomery County, Texas

Trial Cause No. 05-11-10479-CV



OPINION


Appellant Lake Conroe Medical Center, Ltd. a/k/a Lake Area Medical Center, L.P. a/k/a Lake Conroe Medical Center Management, Inc. ("LCMC") sued appellees KMT Building Company ("KMT") and Douglas Joslyn ("Joslyn") for allegedly breaching a contract for construction of a medical building. KMT and Joslyn filed a counterclaim, in which they asserted that LCMC had breached the agreement and sought to recover damages for LCMC's alleged breach of contract, and also sought foreclosure on KMT's mechanic's lien. After a jury trial, the trial court signed a judgment that awarded KMT actual damages of $460,057, foreclosed on the mechanic's lien, and ordered that LCMC take nothing against KMT and Joslyn. LCMC then filed this appeal, in which it raises seven issues for our consideration. We reverse and remand.

Background

Joslyn and his wife Kathy owned KMT. LCMC entered into a contract with KMT for the construction by KMT of two 15,000 square foot "office buildings" in Montgomery County. Joslyn and his wife had previously owned the land where the project was to be built, but they sold the land to LCMC before construction began. Joslyn testified that he and his wife agreed to discount the price of the property by $100,000 in consideration for LCMC's promise to contract with KMT for the construction of two office buildings.

Under the terms of the construction contract, LCMC was to pay KMT $2,796,000 for the two buildings, and the contract price could "be increased or decreased only in accordance with written change orders indicating the changes to be made and the cost for such change." The contract price was to be paid in accordance with a standard draw schedule, which was attached to the contract. The contract provided that KMT "hereby contracts and agrees to build, construct and complete in a good and workmanlike manner, according to the plans and specifications agreed upon by the parties hereto and attached hereto as Exhibit "A", and to furnish and provide all labor and material to be used in the construction. . . ." The specifications attached to the contract indicated, among other things, that KMT was to construct two 15,000-square-foot buildings, "12 ADA Restrooms," (1) and the work was to include "[a]rchitectural plans and engineering[.]" The specifications did not state what material KMT was to use to frame the building. The draw schedule attached to the contract mentioned exterior frame construction and interior wall construction, but did not specify what materials were to be used.

The contract further provided as follows: "all additions or extras shall be paid for by Owner on the basis of [the] prior agreement. All such orders, adjustments and the charge therefor shall be in writing. Claims by the Contractor for extra costs must be approved by Owner in writing before executing the work involved. Additions shall be charged at cost + 20%." In addition, the contract stated, "[i]n the event that the Owner wishes to upgrade any items on the Specification Outline the increase in the cost of the upgrade above the allowance shall be added to the contract sum and the amount of such difference shall be paid to Contractor, and the draw next following installation of the item shall be increase[d] accordingly." Furthermore, the contract provided as follows:

The Contractor shall re-execute any work that fails to conform to the requirements of the Contract, the plans, specifications and drawing [sic] that appear or become evident during the progress of the work, and shall remedy any defects due to faulty materials or workmanship which appear within a period of one (1) year f[ro]m the date of completion of the Contract, all at Contractor's expense.



The contract also contained a merger clause, which provided:

This Contract and the contract documents represent the full and final agreement as to work to be performed by Contractor, and no verbal agreements not specifically covered by the Contract and/or Contract documents shall be of any force and effect and anything that has been understood by Owner not clearly stated herein must be agreed to mutually by the parties and reduced to writing.[ (2)]



At trial, Dr. Dimitrious Mantzoros, the general partner of LCMC, testified that the first building had to be made of steel because one of the tenants in the building was a hospital, and the hospital intended to have an emergency-room-type facility and an imaging facility. Mantzoros testified that the contract does not specify whether the building was to be constructed of wood or steel, but that he and his partners met with Joslyn before executing the contract, and they only discussed steel buildings with Joslyn. Mantzoros explained that having the building framed with steel was important because it allowed for "tremendous flexibility in moving walls around." According to Mantzoros, one of the intended purposes of the building was to serve disabled and injured people, and the contract required that all improvements shall be suitable for the purposes intended.

Mantzoros explained that after the plans had been completed, Joslyn informed him that it would take four months to have steel delivered, but that Joslyn could begin construction immediately if he used wood instead. Mantzoros testified that he "had concerns because I didn't want the wood building[,]" but because tenants had already signed leases, "I was between a rock and a hard spot. I had to make a decision, so I made the decision to at least proceed with Building 1." Mantzoros explained that he agreed to "just do Building Number 1 out of wood because it's a medical office." Mantzoros admitted that the contract did not indicate whether the building was to be framed with wood or steel. Mantzoros testified that the first building has not been certified as compliant with the requirements of the ADA, and LCMC was "going to have to do all the repairs that are necessary in order to get certified." Joslyn attempted to repair some of the ADA issues.

Mantzoros testified that the only change order he signed with respect to the building pertained to issues related to the foundation and the number of bathrooms the building was to contain. According to Mantzoros, some other change orders were "directly between Mr. Joslyn and [a tenant]. They were negotiating on their own.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Steak & Ale of Texas, Inc. v. Borneman
62 S.W.3d 898 (Court of Appeals of Texas, 2002)
Glover v. Texas General Indemnity Co.
619 S.W.2d 400 (Texas Supreme Court, 1981)
Union Pacific Railroad v. Williams
85 S.W.3d 162 (Texas Supreme Court, 2002)
Winchek v. American Exp. Travel Related Services Co., Inc.
232 S.W.3d 197 (Court of Appeals of Texas, 2007)
Greater Houston Transportation Co. v. Zrubeck
850 S.W.2d 579 (Court of Appeals of Texas, 1993)
State Department of Highways & Public Transportation v. Payne
838 S.W.2d 235 (Texas Supreme Court, 1992)
Triplex Communications, Inc. v. Riley
900 S.W.2d 716 (Texas Supreme Court, 1995)
Price v. Short
931 S.W.2d 677 (Court of Appeals of Texas, 1996)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Elbaor v. Smith
845 S.W.2d 240 (Texas Supreme Court, 1993)
Bel-Ton Electric Service, Inc. v. Pickle
915 S.W.2d 480 (Texas Supreme Court, 1996)
Skaggs v. Guerra
704 S.W.2d 51 (Court of Appeals of Texas, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
Lake Conroe Medical Center, Ltd. A/K/A Lake Area Medical Center, L.P. A/K/A Lake Conroe Medical Center Management, Inc. v. KMT Building Company and Douglas Joslyn, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-conroe-medical-center-ltd-aka-lake-area-medical-center-lp-aka-texapp-2009.