Lake City Apartments v. Lund-Martin Co.

417 N.W.2d 704, 1988 WL 108
CourtCourt of Appeals of Minnesota
DecidedMarch 21, 1988
DocketC9-87-1462
StatusPublished
Cited by4 cases

This text of 417 N.W.2d 704 (Lake City Apartments v. Lund-Martin Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake City Apartments v. Lund-Martin Co., 417 N.W.2d 704, 1988 WL 108 (Mich. Ct. App. 1988).

Opinion

OPINION

A. PAUL LOMMEN, Judge.

Lake City Apartments (Lake City) brought suit against Lund-Martin Company (Lund-Martin) and St. Paul Fire and Marine Insurance Company (St. Paul Fire) for damages due to defective construction of a fire lane for an apartment complex. Lake City later amended its complaint to include plumbing, insulation, concrete and site drainage defects in the construction of the complex. Lund-Martin and St. Paul Fire then brought a third party action against Swanson Plumbing and Heating, Inc. (Swanson) and Orv Bakke Insulation, Inc. (Bakke) for contribution and indemnity. After motions for summary judgment, the trial court struck the amended claims because the claims fell outside the two-year statute of limitations of Minn.Stat. § 541.051. The trial court granted partial summary judgment to Lund-Martin and St. Paul Fire and dismissed the claims against Swanson and Bakke.

Lake City appeals the partial summary judgment granted to Lund-Martin and St. Paul Fire. Lund-Martin and St. Paul Fire filed notice for review of the claims against Swanson and Bakke.

*706 We affirm in part, reverse in part and remand.

FACTS

In November 1977, Lake City contracted with Lund-Martin to construct a four-building apartment complex. St. Paul Fire issued a performance bond for Lund-Mar-tin’s work. Lund-Martin then subcontracted with Bakke to install insulation and with Swanson to install the plumbing for the project.

The apartment complex was substantially completed sometime in 1979. In May 1979 and again in August 1980, Lake City contacted Lund-Martin about several problems including cracked or broken up sidewalks, a defective fire lane, standing water in the parking lot and defective insulation causing food to freeze during cold weather.

In January 1981, Lake City sought damages from Lund-Martin for breach of its warranties of workmanship and materials in constructing a fire access road because the road was not capable of supporting a fire truck. Lake City also sought damages from St. Paul Fire for its refusal to pay its surety obligation for Lund-Martin’s breach of warranties.

In February 1982, Lake City filed notice of a motion to amend the complaint to include damages for inadequate insulation. The motion was postponed indefinitely.

From July 1981 through May 1982, occasional water pipe leaks occurred. After independent testing of the water and water pipe, Lake City installed a pressure-reducing valve. The valve seemed to solve the problem and there were no more leaks until February 1984. An inspection by the Minnesota Housing and Finance Agency revealed that despite the reduction of pressure, the copper tubing seemed to be damaged throughout the building and might need total replacement.

In October 1984, Lake City filed an amended complaint to include damages for defective workmanship and materials in the plumbing, insulation, site drainage and concrete walkways and patios. Fourteen months after service of the amended complaint, Lund-Martin and St. Paul Fire served Swanson and Bakke with a third party action for contribution or indemnity.

Swanson and Bakke moved for summary judgment and Lund-Martin and St. Paul Fire moved for partial summary judgment. The trial court struck the amended claims because of the expiration of the statute of limitations, granted all motions for summary judgment and dismissed the claims against Swanson and Bakke. Lake City appeals and Lund-Martin and St. Paul Fire noticed review of their third party action.

ISSUE

Did the trial court err in ruling that the Minn.Stat. § 541.051 two-year statute of limitations had expired and prohibited suit on the amended claims?

ANALYSIS

On appeal from a summary judgment, the appellate court determines (1) whether any genuine issues of material fact exist and (2) whether the trial court erred in its application of the law. Betlach v. Wayzata Condominium, 281 N.W.2d 328, 330 (Minn.1979); See Minn.R.Civ.P. 56.03. The trial court found that “all of the damages set forth in the amended complaint * * * involve damages discovered prior to October 18, 1982, [and] said claims are outside the two-year statute of limitations” in Minn.Stat. § 541.051 (1980).

Minn.Stat. § 541.051 subd. 1 states:

Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, * * * arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution or indemnity for damages sustained on account of the injury, shall be brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property * * * more than two years after discovery thereof, nor, in any event shall such a cause of action accrue more than *707 ten years after substantial completion of the construction.

The two year statute of limitations applies to claims of defective workmanship and “begins to run when the plaintiff discovers, or in the exercise of reasonable diligence should have discovered, an injury sufficient to entitle him to maintain a cause of action.” Greenbrier Village Condominium Two Association, Inc. v. Keller Investment, Inc., 409 N.W.2d 519, 524 (Minn.Ct.App.1987).

Lake City provides two theories to bring their amended complaint within the two year statute of limitations. First, Lake City argues that the amended complaint relates back to the original complaint under Minn.R.Civ.P. 15.03 and therefore, it is timely. Second, if the amended complaint does not relate back, Lake City argues that the amended complaint was timely because it was brought within two years of the “discovery” of the defects. The facts do not appear to be in dispute. Lake City had known of the problems with water ponding, inadequate insulation, and concrete cracking since 1979.

a.Site drainage

Minn.R.Civ.P. 15.03 states:

Whenever the claim or defense asserted in the amended pleading arose out of the conduct, transaction, or occurrence set forth or attempted to be set forth in the original pleading, the amendment relates back to the date of the original pleading.

“Under this rule an amendment to a complaint or petition setting up no new cause of action will relate back to the commencement of the action.” Nelson v. Glenwood Hills Hospitals, Inc., 240 Minn. 505, 514, 62 N.W.2d 73, 78 (1953).

The policy of statutes of limitation is to “compel the exercise of a right of action within a reasonable time so that a defendant will have a fair opportunity to prepare an adequate defense.” Note,

Related

Cite This Page — Counsel Stack

Bluebook (online)
417 N.W.2d 704, 1988 WL 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-city-apartments-v-lund-martin-co-minnctapp-1988.