L. W. Severance & Sons, Inc. v. Angley

125 N.E.2d 415, 332 Mass. 432, 1955 Mass. LEXIS 665
CourtMassachusetts Supreme Judicial Court
DecidedApril 1, 1955
StatusPublished
Cited by14 cases

This text of 125 N.E.2d 415 (L. W. Severance & Sons, Inc. v. Angley) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. W. Severance & Sons, Inc. v. Angley, 125 N.E.2d 415, 332 Mass. 432, 1955 Mass. LEXIS 665 (Mass. 1955).

Opinion

Cotjnihan, J.

This is an action of contract to recover a balance due for labor and materials furnished the defendants by the plaintiff under an alleged written contract. The action was referred to an auditor whose findings of fact were not to be final. G. L. (Ter. Ed.) c. 221, § 56. Upon the coming in of the auditor’s report, the defendants were permitted to file a substitute answer with the understanding that it would raise no issues not previously raised before the auditor. This answer contained a general denial and inter alia claims of intentional deviation from the contract by the plaintiff and modification of the contract. After the entry of the auditor’s report the rights to trial by jury and to the introduction of evidence were seasonably claimed by the defendants. Rule 88 of the Superior Court (1932). At the close of the trial the judge on motion ordered that a verdict be returned for the plaintiff in the sum of $12,737.27 which was the balance claimed by the plaintiff with interest. The action comes here upon the exception of the defendants to this order. There was error in directing a verdict for the plaintiff.

It was agreed at the trial that the treasurer of the plaintiff who was also its general manager had authority to bind the plaintiff, and also that the statements and acts of either defendant were binding upon each of them, both as agent and as principal.

*434 At the trial the auditor’s report was in evidence and the only oral testimony came from the treasurer of the plaintiff and the defendants. The contract, 1 the specifications, a letter dated May 4, 1951, 2 from the plaintiff to the defendants, another letter dated May 20, 1950, 3 from the plaintiff to the defendants, and plans of remodeling the house were in evidence as exhibits and are properly before us.

The auditor’s report discloses the following findings. The *435 defendants on May 7, 1951, were the owners of a house in the Bryantville section of Pembroke, which was about one hundred years old. It had ten rooms and a doctor’s office which Dr. Angley used. They had occupied it for many years. They desired a modern house similar to one which they had seen in East Bridgewater. As a result in 1950 they talked with the treasurer of the plaintiff. He suggested (1) that they remove the house then on the land and build a new one, (2) that they sell that house and land and build a new house on another lot, or (3) that they remodel the present house. At that time he gave them an estimate of $26,000 as the cost of remodeling according to plans which the plaintiff had prepared. Nothing happened until a year later when they got in touch with the plaintiff and it informed them by letter of May 4, 1951, that it would do the work of remodeling for an estimated cost of $27,150.77. The increase in the estimate was due to a general increase in the cost of labor and materials. As a result the contract hereinbefore referred to was signed by all the parties. The plaintiff began work on May 29, 1951, and finished on January 5, 1952.

It would unduly prolong this opinion to recite in detail the findings of the auditor with respect to the work required to be done under the contract. The auditor found that labor and materials for certain changes in the original specifications and for certain extras were furnished by the plaintiff. The auditor also found that the plaintiff "performed its part of the written contract and that the charges made and submitted to the defendants, both for labor and materials as were furnished are reasonable and proper.” He found also that the total final claim against the defendants was $49,570.22 on which they had been credited with payments of $37,409.49 leaving a balance of $12,160.73 with interest of $425.60 due the plaintiff.

At the trial there was evidence from the defendants that the plaintiff through its treasurer recommended the remodeling job. This is borne out by the letter of May 20, 1950. The contract, the letter of May 4, 1951, and the *436 specifications were all clipped together when the contract was signed. The plans were already in their possession. They relied upon the contract, the letter of May 4, 1951, the specifications, and the plans when they signed the contract. They knew that the contract was for labor and materials and that there was no set price in the contract. The doctor testified that he did not dispute any item of labor ór materials allegedly furnished and that he had no knowledge concerning them. There was evidence that the defendants had about $13,000 in cash when the work was to begin and that the treasurer of the plaintiff assisted them in securing a mortgage of $13,500.

There was further evidence that on or about August 21, 1951, the defendants had a talk with the treasurer of the plaintiff. At that time the house was not completed and work on the office had not been started. Dr. Angley told the treasurer that he already had spent $23,000 and it was obvious that they were not going to be able to finish the job for $27,150.77, the estimated price. He said "it was absolutely imperative that he know how much it was going to cost over and above the contract.” The treasurer "blamed the plumbers as being one of the causes of the great expense and told him that it would run $6,000 over the original estimate.” The doctor “repeated the figure of $6,000 and asked him if he was sure that was going to be all that it would cost because he didn’t have to build his office that year and they could do it after the completion of the house.” The treasurer told him "that it would not cost more than $6,000 above the estimate to finish everything including the office.” Dr. Angley relied upon this statement and told the treasurer to go ahead and complete it for that amount. Dr. Angley testified that he did not have the additional $6,000, and the treasurer arranged for a mortgage of $5,000 which together with $1,000 of money of the defendants would pay for the cost of completion.

The auditor found that certain labor and materials were furnished because of changes in the specifications and extras. Without enumerating these in detail it is enough to say *437 that the auditor found that such changes and extras consisted of twenty-five items. He found that the cost of such items was $5,835. The evidence from the defendants was that only six changes and extras were furnished by the plaintiff. There was also evidence that certain work called for by the specifications was not done and that the defendants did this work themselves at a cost of over $1,000.

In Cook v. Farm Service Stores, Inc. 301 Mass. 564, the effect of a report of an auditor, whose findings of fact are not final, in a trial before a jury was discussed. At page 566 it was said, “Each and every finding of fact ... reported by an auditor, becomes ‘prima facie evidence.’ That expression has acquired a definite legal meaning in this Commonwealth. . . . An analysis of that expression shows, first of all, that prima facie evidence is ‘evidence,’ remains evidence throughout the trial, and is entitled to be weighed like any other evidence upon any question of fact to which it is relevant. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wounded Warrior Project, Inc. v. Lotsa Helping Hands, Inc.
649 F. App'x 732 (Eleventh Circuit, 2016)
Galvin v. Excel Switching Corp.
21 Mass. L. Rptr. 233 (Massachusetts Superior Court, 2006)
Stigum v. Skloff
2000 Mass. App. Div. 63 (Mass. Dist. Ct., App. Div., 2000)
Beal v. Krock
First Circuit, 1998
Emerald Excavating Co. v. Amelia
1998 Mass. App. Div. 60 (Mass. Dist. Ct., App. Div., 1998)
Troy Mining Corp. v. Itmann Coal Co.
346 S.E.2d 749 (West Virginia Supreme Court, 1986)
Adams v. Elliott
1982 Mass. App. Div. 315 (Mass. Dist. Ct., App. Div., 1982)
Chase v. Katz
3 Mass. Supp. 640 (Massachusetts District Court, 1982)
Chase v. Katz
1982 Mass. App. Div. 149 (Mass. Dist. Ct., App. Div., 1982)
A. Leo Nash Steel Corp. v. Southern New England Steel Erection Co.
402 N.E.2d 71 (Massachusetts Appeals Court, 1980)
Simons v. American Dry Ginger Ale Co. Inc.
140 N.E.2d 649 (Massachusetts Supreme Judicial Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
125 N.E.2d 415, 332 Mass. 432, 1955 Mass. LEXIS 665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-w-severance-sons-inc-v-angley-mass-1955.