Kvaerner ASA v. Bank of Tokyo-Mitsubishi, Ltd.

210 F.3d 262
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 17, 2000
Docket99-1368
StatusPublished
Cited by17 cases

This text of 210 F.3d 262 (Kvaerner ASA v. Bank of Tokyo-Mitsubishi, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kvaerner ASA v. Bank of Tokyo-Mitsubishi, Ltd., 210 F.3d 262 (4th Cir. 2000).

Opinion

Affirmed by published opinion. Judge LUTTIG wrote the opinion, in which Judge WIDENER and Judge ANDERSON joined.

OPINION

LUTTIG, Circuit Judge:

Kvaerner and Jones filed a petition to compel the Bank of Tokyo to arbitrate disputes related to the performance of a construction contract, which performance Kvaerner and Jones had guaranteed to the Bank through formal Guaranties. The dis *264 trict court held that under the Guaranties, read in conjunction with the underlying construction contract, the Bank was required to arbitrate its disputes with Kvaer-ner and Jones. For the reasons below, we affirm.

I.

On April 8, 1993, BCH Energy, L.P. (“BCH” or the “Owner”) entered into a Turnkey Design and Construction Agreement (“Construction Agreement” or “Agreement”) with general contractor Metric/Kvaerner Fayetteville, a joint venture, for the purpose of constructing a waste-to-energy plant in Fayetteville, North Carolina. The joint venture was formed by Kvaerner Environmental Technologies, Inc. (“Kvaerner”), an indirect subsidiary of Kvaerner, and Metric Contractors, Inc. (“Jones”), a subsidiary of Jones. A syndicate of New York branch banks, with the Bank of Tokyo (the “Bank”) acting as lead agent, financed the project, providing over $70 million in credit support to the joint venture.

On November 16, 1993, Kvaerner and Jones executed Guaranty Agreements to “irrevocably and unconditionally guarantee[] the punctual performance of each and every obligation offthe joint venture] under the [Construction] Agreement.” J.A. 18 (Kvaerner Guaranty, at ¶ 2); J.A. 26 (Jones Guaranty, at ¶ 2). 1 In the event the joint venture did not perform its duties under the Construction Agreement, the Guaranties could be enforced against Kvaerner and Jones. The Bank of Tokyo signed the Guaranties on behalf of the banks. Kvaerner and Jones also provided the Guaranties to BCH, the owner of the project.

Construction and acceptance testing on the project were completed in 1996. BCH and the joint venture had a dispute about the project, and BCH then took possession of it. In September 1996, BCH sent the joint venture a notice of default under the Construction Agreement. Pursuant to an arbitration clause in the Construction Agreement, BCH and the joint venture began arbitration proceedings in October 1996.

In December 1996, BCH shut down the operation of the project, and the project was unable to make payments on the banks’ financing. On January 14, 1997, the Bank filed an action for breach of the Guaranties against Kvaerner and Jones in the Supreme Court of New York County in New York. The New York Appellate Division dismissed the action against Jones because it was without personal jurisdiction over Jones. As to Kvaerner, the court granted Kvaerner’s motion to stay the action pending the outcome of the BCH arbitration. The Bank subsequently refiled its breach of Guaranty action against Jones in federal court in New York.

On November 12, 1997, the Bank filed an involuntary Chapter 7 Bankruptcy Proceeding against BCH in the District of Delaware. The BCH arbitration with the joint venture was then automatically stayed, which stay continues to be in effect.

On April 13, 1998, Kvaerner and Jones filed a demand for arbitration with the American Arbitration Association, seeking to arbitrate the Bank’s claim against them for breach of the Guaranties, which is the subject of the New York state action against Kvaerner and the New York federal action against Jones. On April 14,1998, Kvaerner and Jones filed a petition to compel the bank to arbitrate in the Eastern District of North Carolina. The district court granted the petition to compel arbitration, finding that an agreement to arbitrate existed between the parties. Accordingly, the Bank has participated in *265 arbitration proceedings under a reservation of right with respect to this appeal. 2

II.

The Construction Agreement, to which the owner BCH and the joint venture are parties, includes a broad arbitration clause requiring that disputes “arising out of or relating to” the Agreement be submitted to arbitration in North Carolina. 3 The Guaranties, to which BCH, Kvaerner and Jones, and the Bank are parties, however, do not specifically address the question whether arbitration is required for disputes among the parties to the Guaranties. The question in this case is whether the Guaranties executed by Kvaerner and Jones to secure the loans for the project require the Bank to submit to arbitration.

The district court concluded that the arbitration clause of the Construction Agreement was incorporated into the Guaranties, and that the Bank was required to submit to arbitration in the present case because the dispute related to the Construction Agreement. 4 We agree. Although the Guaranties do not specifically reference arbitration, they do include a provision that gives Kvaerner and Jones the same “rights and remedies” as are available to the joint venture under the Construction Agreement:

Each and every default or failure by [the joint venture] in making payment or otherwise discharging or performing any of the Guaranteed Obligations shall give rise to a separate liability of [the joint venture] to [the Bank] and a separate cause of action hereunder and a .separate suit may be brought hereunder as each liability or cause of action arises. Upon receipt of notice of default, [Kvaerner and Jones] shall have the same rights and remedies of [the joint venture] under the [Construction] Agreement, including’ without limitation the benefit of any remaining cure periods granted to [the joint venture] pursuant to the[Construction] Agreement.

J.A. 20 (Kvaerner Guaranty, at ¶ 4) (emphasis added); J.A. 28 (Jones Guaranty, at ¶ 4) (emphasis added). This provision of the Guaranties operates to incorporate into the Guaranties the rights and remedies available to the joint venture under the Construction Agreement. One of the rights available to the joint venture under the Agreement is the right to arbitrate disputes “arising out of or relating to” the Construction Agreement. Under paragraph 4 of the Guaranties, Kvaerner and Jones have the same right — the right to *266 arbitrate disputes — as the joint venture has under the Agreement. Thus, paragraph 4’s rights and remedies clause grants Kvaerner and Jones the right to arbitrate disputes that arise out of or relate to the Construction Agreement. Cf. Maxum Foundations, Inc. v. Salus Corp., 779 F.2d 974, 978 (4th Cir.1985) (“It is well settled that, under the Federal Arbitration Act, an agreement to arbitrate may be validly incorporated into a subcontract by reference to an arbitration provision in a general contract.”).

The disputes between the Bank and Kvaerner and Jones arise out of and relate to the Construction Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
210 F.3d 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kvaerner-asa-v-bank-of-tokyo-mitsubishi-ltd-ca4-2000.