Krohnke v. Lemer

300 N.W.2d 246, 1980 N.D. LEXIS 327
CourtNorth Dakota Supreme Court
DecidedDecember 19, 1980
DocketCiv. 9795
StatusPublished
Cited by10 cases

This text of 300 N.W.2d 246 (Krohnke v. Lemer) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krohnke v. Lemer, 300 N.W.2d 246, 1980 N.D. LEXIS 327 (N.D. 1980).

Opinions

ERICKSTAD, Chief Justice.

Because the trial judge died after the trial of this case, but before he was able to render a decision, this case is somewhat unique. Judge Ray R. Friederich tried this case without a jury on May 6 and 7 of 1979 in the Pierce County Courthouse at Rugby, North Dakota. At the close of the trial, he asked counsel for each side to prepare proposed findings of fact, conclusions of law [247]*247and order for judgment and submit the same to him for his consideration. Before he could render a decision, Judge Priederich came to an untimely death. This court appointed Harold L. Anderson as a temporary judge and Douglas B. Heen as the Presiding Judge of the Northeast Judicial District assigned this case to Judge Anderson. Through counsel, the parties stipulated that Judge Anderson should decide the case on the transcript of the proceedings before Judge Friederich.

Initially, Everett Krohnke, doing business as Serve and Save Lumber, sued George Lemer to recover $3,183.92 as a balance due on the purchase price of a pole barn which was constructed by Krohnke for Lemer on his ranch near Drake, North Dakota. The complaint is dated the 18th of August, 1975, and is signed by Robert A. Butz as the attorney for Krohnke. Lemer filed an answer and a counterclaim, the essence of which is that the parties agreed that Krohnke should build for Lemer a pole barn on Lemer’s premises, 40 feet by 120 feet for the total sum of $6,780, and that $3,600 had been paid on the contract, leaving $3,183.92, the balance to be paid when the building was completed to Lemer’s satisfaction. He further alleged that he had informed Krohnke that the building was not properly constructed; that Krohnke agreed to make necessary repairs to the satisfaction of Lemer, but that on the 7th of February, 1975, a large section of the roof collapsed, completely ruining the building; that Krohnke again agreed to make necessary repairs to the satisfaction of Lemer, but that he had not done so; that Lemer was willing to pay the balance due on the contract as soon as Krohnke completed the building to Lemer’s satisfaction, that if he did not do so, it would cost Lemer $5,000 to reconstruct it.

Judge Anderson rendered a memorandum decision on the 9th day of November, 1979, wherein he held that Krohnke’s complaint should be dismissed and that Lemer should recover $5,000 on his counterclaim with no interest, his costs and disbursements. Krohnke appeals from the judgment which was entered upon the findings of fact, conclusions of law and order for judgment executed subsequent to the memorandum decision.

As Judge Anderson did not see and hear the witnesses testify, but rendered his decision on the basis of the transcript, we do not apply Rule 52(a) of the North Dakota Rules of Civil Procedure in this case. See Dolajak v. State Auto. & Cas. Underwriters, 252 N.W.2d 180 (N.D.1977). Accordingly, we have reviewed the entire transcript in an attempt to determine the facts and have concluded that the judgment rendered upon Judge Anderson’s findings of fact, conclusions of law and order for judgment and his memorandum decision should be and is affirmed.

Notwithstanding that we have reached our determination of this case from an independent examination of the transcript and exhibits, we believe it is significant that Judge Anderson concluded that Krohnke was liable, both under his oral warranty of fitness and for improper construction.1

[248]*248The record shows that Krohnke testified that George Lemer wanted to use 2 by 6 lumber for the rafters and 2 by 6 lumber for the trusses, but that Krohnke told Lemer that “it didn’t need it.” In the building of the pole barn, Krohnke used 2 by 4 lumber for the lower part of the trusses.

Relative to the issue of warranty, the record shows that Krohnke testified that he assured George Lemer that the pole barn would stand a long time but that he did not assure him that it would stand against a 70-mile-an-hour wind and two feet of snow. Notwithstanding that assertion, Krohnke did concede that he told Geoge Lemer that the building would stand until Lemer’s three-year-old son was able to take over the farm.

As for the construction of the rafters, the record discloses that Krohnke testified that Adam Lemer, a brother of George Lemer, told Krohnke that the rafters were sagging and that this conversation occurred prior to the collapse of the building on the 7th day of February, 1975. Krohnke’s testimony as to his own response to Adam’s statement was that, "he was out of his tree.”

There is considerable testimony relative to the construction of the rafters. Krohnke testified that three rafters broke after they pulled apart which, he conceded, would indicate, possibly, that they were not glued too well. .The building contained 31 rafters, including the two end rafters. Apparently the end rafters could not be glued together, but of the 29 at least three, if not five, of the rafters were glued at a time different from the other rafters. At one point in his testimony, Krohnke testified that he built all of the rafters in the Drake School Ag room. At another point in his testimony, he asserted that he built the five rafters in his office at the lumber yard and said that he did not remember saying that he had built them in the school.

The issue is important because gluing, to be effective, must be done at a temperature of something like 50 0 Fahrenheit and, thus, if it were done outside in the subzero temperature, the gluing would not hold. George Lemer contended that Krohnke’s shop was so filled with supplies and so small that it would be impossible to construct the rafters inside of the shop. Kenneth Richter, a neighbor, said that Krohnke came out to his farm and borrowed a heater in January of 1974 “to glue rafters for George’s barn.” Krohnke denied that he ever used Richter’s heater for such a purpose.

Krohnke's testimony was to the effect that George Lemer had not paid the balance on the barn at the time the roof caved in in February of 1975, although the barn was substantially completed in April of 1974, for the reason assertedly given by Lemer that Lemer had no money to pay the balance.

George Lemer, on the other hand, contended that the reason he hadn’t paid the balance of the purchase price of the pole barn was that he was dissatisfied with a number of things including the sagging rafters, that the building was not square, that the doors were improperly constructed, and that the overhang varied from 13½ inches on the west end of the front of the building, to 16½ inches on the east half of the front of the building.

Krohnke testified that he guessed the level of the snow to be 22 inches deep on the 7th of February, 1975, when the roof collapsed, but that he did not measure it. As to the gluing, he further testified that the five rafters in question were supposed to be glued although he did not check them, but, in any case, whether glued or not, they would have broken from the pressure.

George Lemer testified that he agreed to the use of 2 by 6 top cord truss rafters and 2 by 4 bottom cord rafters because Krohnke said it would “stand for my lifetime.”

Krohnke apparently commenced the construction of the pole barn in December of 1973 and completed it, such as it was, in April of 1974.

[249]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanson v. Williams County
452 N.W.2d 313 (North Dakota Supreme Court, 1990)
Stracka v. Peterson
377 N.W.2d 580 (North Dakota Supreme Court, 1985)
Varnson v. Satran
368 N.W.2d 533 (North Dakota Supreme Court, 1985)
McCroskey v. Fettes
336 N.W.2d 645 (North Dakota Supreme Court, 1983)
Sturdevant v. Sturdevant
315 N.W.2d 263 (North Dakota Supreme Court, 1982)
Steckler v. Miller & Holmes, Inc.
303 N.W.2d 560 (North Dakota Supreme Court, 1981)
Hager v. Devils Lake Public School District
301 N.W.2d 630 (North Dakota Supreme Court, 1981)
Krohnke v. Lemer
300 N.W.2d 246 (North Dakota Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
300 N.W.2d 246, 1980 N.D. LEXIS 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krohnke-v-lemer-nd-1980.