Koviack Irrigation and Farm Services v. Maple Row Farms LLC

CourtMichigan Court of Appeals
DecidedSeptember 21, 2017
Docket331327
StatusUnpublished

This text of Koviack Irrigation and Farm Services v. Maple Row Farms LLC (Koviack Irrigation and Farm Services v. Maple Row Farms LLC) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koviack Irrigation and Farm Services v. Maple Row Farms LLC, (Mich. Ct. App. 2017).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

KOVIACK IRRIGATION AND FARM UNPUBLISHED SERVICES, INC., September 21, 2017

Plaintiff/Counter-Defendant- Appellant,

v Nos. 331327; 331445 Lenawee Circuit Court MAPLE ROW FARMS, LLC, LC No. 14-005177-CK

Defendant/Counter-Plaintiff- Appellee.

Before: BECKERING, P.J., and MARKEY and RIORDAN, JJ.

PER CURIAM.

Plaintiff appeals by right the trial court’s judgment in favor of defendant, following a bench trial. The court determined that defendant was not liable to plaintiff for the cost of equipment that plaintiff supplied for defendant’s irrigation system because defendant properly rejected the equipment under the Uniform Commercial Code (UCC), MCL 440.1101 et seq. The court ordered defendant to return the equipment to plaintiff at defendant’s own expense. Plaintiff also appeals the trial court’s award of case evaluation sanctions of $11,362.50. We affirm in both appeals.

Plaintiff sold defendant component parts for an irrigation system for defendant’s farm, which included a pump for distributing water from a retention pond. Plaintiff also helped design and install the system. Because the pump was delivered late in the harvest season, defendant waited until the following spring to install it. At that time, plaintiff was unwilling to assist in installing the pump because defendant had not paid for it or its operating panel. Defendant was unwilling to pay for the pump and panel until they were installed, and defendant could confirm that they would work as intended with the irrigation system. Defendant therefore hired another irrigation specialist to install the pump; he was then advised that the pump would not work with defendant’s retention pond. Defendant then purchased another type of pump that was compatible with its retention pond and irrigation system. Plaintiff sued defendant for breach of contract, account stated, and unjust enrichment. Defendant filed a counterclaim, alleging that plaintiff had not provided a proper pump for the irrigation system, and that plaintiff refused to correct the problem. Following a two-day bench trial, the trial court found that defendant properly rejected

-1- the pump and its panel; consequently, plaintiff was not entitled to recover the costs of those items under the parties’ agreement. The court ordered defendant to return the goods at its own expense.

I. REJECTION OF GOODS

Plaintiff argues that the trial court erred in ruling that defendant properly rejected the pump and operating panel under the UCC.

This Court reviews a trial court’s findings of fact for clear error, MCR 2.613(C), and its conclusions of law are reviewed de novo. Trahey v City of Inkster, 311 Mich App 582, 593; 876 NW2d 582 (2015). A finding of fact is clearly erroneous if there is no evidentiary support for it or this Court is left with a definite and firm conviction that a mistake has been made. Id. Regard is given to the trial court’s special opportunity to judge the credibility of the witnesses who appeared before it. MCR 2.613(C).

Preliminarily, we disagree with plaintiff’s argument that defendant should not have been permitted to rely on a rejection of goods theory because defendant never raised that defense as an affirmative defense. Plaintiff is correct that defendant did not raise this issue as an affirmative defense to plaintiff’s claims. Defendant, however, filed a counter complaint that alleged that plaintiff had not provided the proper equipment, which plaintiff refused to correct, so defendant obtained another pump. Because defendant raised its rejection-of-goods arguments in its countercomplaint, which the trial court was required to address, there is no merit to plaintiff’s suggestion that the trial court erred by considering that theory at trial.

The trial court ruled that defendant properly rejected the pump and its operating panel in the spring of 2014 and, therefore, was not liable for the cost of that equipment under the parties’ contract. MCL 440.2602(1) provides, in relevant part:

(1) Rejection of goods must be within a reasonable time after their delivery or tender. It is ineffective unless the buyer seasonably notifies the seller.

(2) Subject to the provisions of the 2 following sections on rejected goods (sections 2603 and 2604),

(a) after rejection any exercise of ownership by the buyer with respect to any commercial unit is wrongful as against the seller; and

(b) if the buyer has before rejection taken physical possession of goods in which he does not have a security interest under the provisions of this article (subsection (3) of section 2711), he is under a duty after rejection to hold them with reasonable care at the seller’s disposition for a time sufficient to permit the seller to remove them; but

(c) the buyer has no further obligations with regard to goods rightfully rejected.

-2- Plaintiff first argues that defendant did not timely reject the pump. Where goods are rejected, what constitutes a reasonable time to act depends on the nature, purpose, and circumstances of the case. See MCL 440.1205(1); Kelynack v Yamaha Motor Corp, USA, 152 Mich App 105, 113; 394 NW2d 17 (1986). Where the product at issue involves goods of a complex nature and the buyer depends on the seller’s expertise that the goods will perform properly for the intended use, a buyer has an opportunity to put those goods to use or to test the goods before determining whether the goods conform to the contract. See Capitol Dodge Sales, Inc v Northern Concrete Pipe, Inc, 131 Mich App 149, 157-158; 346 NW2d 535 (1983).

In this case, the pump was delivered late in the harvest season, so it could not be put to use right away. Also, some installation work still needed to be performed, such as hooking it up to the electrical system to see if it would work. Under the circumstances, it was reasonable for defendant to wait until the pump was actually installed to see if it would work before deciding whether to reject it, particularly considering that defendant relied on plaintiff’s expertise in selecting a pump appropriate for its intended use. The trial court did not clearly err in finding that defendant rejected the goods within a reasonable time when it determined the following spring that the pump was not appropriate for defendant’s irrigation system. During the interim period, the pump sat in its original packaging until it could be installed to determine if it would work as intended for defendant’s purposes.

Plaintiff also argues that defendant did not actually reject the pump because it did not formally give notice that it was rejecting the pump. We disagree. Again, the reasonableness of defendant’s action depends on the nature, purpose, and circumstances of the case. See MCL 440.1205(1).

Plaintiff’s salesman, Anthony Belcher, met with defendant’s owner, Dean McClenathen, in April 2014 to inquire about defendant’s intention to pay for the pump. Belcher agreed that McClenathen told him that he did not intend to pay for anything more until he saw that the irrigation system would work as planned. Belcher admitted that the pump and panel were still in their original packaging at that time; however, plaintiff’s owner, Terry Koviack, refused to do any more work on the project until defendant paid for the equipment. At that point, plaintiff was on notice that defendant intended to reject the pump if it would not work as planned. When Koviack refused to do any further work to assist in installing the pump, defendant reasonably took steps to follow through with the parties’ agreement by hiring another irrigation specialist, Mark Ackerman, to install the pump. Ackerman informed defendant that because the pump was not appropriate for defendant’s retention pond and irrigation system, it would not work as intended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Khouri
751 N.W.2d 472 (Michigan Supreme Court, 2008)
Wood v. Detroit Automobile Inter-Insurance Exchange
321 N.W.2d 653 (Michigan Supreme Court, 1982)
Kelynack v. Yamaha Motor Corp.
394 N.W.2d 17 (Michigan Court of Appeals, 1986)
Henderson v. Chrysler Corp.
477 N.W.2d 505 (Michigan Court of Appeals, 1991)
Fargo MacHine & Tool Co. v. Kearney & Trecker Corp.
428 F. Supp. 364 (E.D. Michigan, 1977)
FOREST CITY v. Leemon Oil Co.
577 N.W.2d 150 (Michigan Court of Appeals, 1998)
Capitol Dodge Sales, Inc v. Northern Concrete Pipe, Inc
346 N.W.2d 535 (Michigan Court of Appeals, 1983)
Davis v. Forest River, Inc
748 N.W.2d 887 (Michigan Court of Appeals, 2008)
Trahey v. City of Inkster
876 N.W.2d 582 (Michigan Court of Appeals, 2015)
Forest City Enterprises, Inc. v. Leemon Oil Co.
228 Mich. App. 57 (Michigan Court of Appeals, 1998)
Van Elslander v. Thomas Sebold & Associates, Inc.
823 N.W.2d 843 (Michigan Court of Appeals, 2012)
AFT Michigan v. Michigan
303 Mich. App. 651 (Michigan Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Koviack Irrigation and Farm Services v. Maple Row Farms LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koviack-irrigation-and-farm-services-v-maple-row-farms-llc-michctapp-2017.