Korman v. Cumberland
Opinion
USCA1 Opinion
United States Court of Appeals
For the First Circuit
No. 97-2180
THE KORMAN COMPANY, AGENT FOR HYMAN KORMAN, INC.,
Appellant,
v.
CUMBERLAND FARMS, INC.,
Appellee.
____________________
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MASSACHUSETTS
[Hon. Nathaniel M. Gorton, U.S. District Judge]
____________________
Before
Selya, Boudin and Lynch,
Circuit Judges.
____________________
Michael H. Landis with whom Smolow & Landis and Bertin C.
Emmons were on brief for appellant.
Barbara D. Gilmore with whom Kathleen Provost, Sullivan &
Worcester LLP, and Mark G. Howard were on brief for appellee.
April 6, 1998
BOUDIN, Circuit Judge. The parties to this case sought
to settle a dispute between them, but the settlement agreement they
reached has now given rise to a new dispute. Our own reading of
the settlement agreement falls somewhere between the conflicting
positions of the parties, but it is impossible to state the issue
without some background and a description of the pertinent terms of
the agreement. Most, although not all, of the facts are
undisputed.
The appellant, the Korman Company, leased a parcel of
land to Chevron U.S.A., Inc., in Bensalem, Bucks County,
Pennsylvania. Cumberland Farms, Inc., acquired the lease from
Chevron in 1986 and used it to operate a gas station and
convenience store. In 1992, Cumberland filed for bankruptcy in
Massachusetts under Chapter 11.
The following year, Korman filed an adversary proceeding
in the bankruptcy court, see Fed. R. Bankr. P. 7001, to eject
Cumberland from the property, alleging that Cumberland had violated
a provision of the lease. Cumberland then closed the gas station
and reached a settlement with Korman, which the bankruptcy court
approved. The dispute now before us arises out of the
implementation of this settlement agreement.
In the settlement agreement, Korman agreed to buy out the
remainder of Cumberland's lease for $90,000, provided that
Cumberland cleared the property of all structures and eliminated
any unlawful contamination of the soil and groundwater. Anxious to
regain the property swiftly, Korman agreed to pay $90,000 into an
escrow account with the understanding that 75 percent of the
account's value would be released to Cumberland when it completed
certain specified tasks. If Cumberland failed to complete these
tasks by December 31, 1994, the escrow account would be reduced by
$10,000 for each month of delay, so the 75 percent payment--due
when the specified tasks were completed--would be a declining
amount. The remaining 25 percent of the escrow account is to be
paid only when Cumberland's "closure report" is approved by the
Pennsylvania Department of Environmental Resources ("DER") at the
conclusion of the cleanup.
On February 7, 1995, Cumberland informed Korman that it
would satisfy the requirements specified for release of 75 percent
of the escrow account by February 8, 1995. This occurred somewhat
more than a month after the December 31, 1994, deadline so the
total amount of the escrow was already reduced by somewhat more
than $10,000. However, Korman refused to agree that any payment
was due to Cumberland from the escrow, and Cumberland then filed a
motion in the bankruptcy court to compel performance under the
settlement agreement.
Paragraphs 2 and 4(a) of the agreement outline various
tasks that Cumberland must perform to be entitled to the 75 percent
payment. Korman admits that a number of the requirements were
satisfied (e.g., removal of underground storage tanks and
demolition of buildings). But Korman denies that Cumberland has
satisfied requirements in paragraph 4(a)(iii) and (iv) relating to
removal of contaminated soil, remediation of contaminated
groundwater and installation of equipment required for long-term
remediation. Paragraph 4(a) describes Cumberland's pertinent
obligations as follows:
iii) removal and replacement of
contaminated soil, if any, and the
commencement of remediation of any
contaminated groundwater to the extent such
removal and/or remediation is deemed necessary
by the appropriate federal or state
authorities;
iv) to the extent deemed necessary by
the appropriate federal or state authorities,
installation of any equipment and/or systems
required for a long-term remediation system;
and
v) delivery to Korman of written
certification by a reputable licensed
environmental consulting engineer that the
work required in Paragraphs 2(a) through 2(d)
and Paragraph 4(a)(i)-(iv) hereof has been
completed.
In the bankruptcy court, Cumberland argued that, without
any direction from any federal or state agency, it had removed
approximately 440 tons of contaminated soil and had installed
underground piping that would enable future remediation if
required. To show that it had satisfied the requirements of
subparagraphs (iii) and (iv), Cumberland relied upon a letter from
a firm of licensed geologists and engineers purporting to certify
that Cumberland had satisfied all the requirements of paragraphs 2
and 4 of the agreement, a certification previously furnished to
Korman. Cumberland also provided a letter from DER acknowledging
that Cumberland had filed a closure report.
In response, Korman urged that subparagraphs (iii) and
(iv) required Cumberland to follow procedures set out in DER's
environmental regulations, and it offered an affidavit of a
consulting engineer, experienced in environmental projects, stating
that Cumberland was required to receive DER approval prior to
commencing remediation, and that filing a closure report did not
amount to such approval. The same affidavit asserted that
contaminants in excess of DER's cleanup standards were still
present in the soil on the property.
The bankruptcy court held a telephone hearing on June 28,
1995, and issued an order on November 29, 1995, directing that 75
percent of the escrow account (as reduced by the delay penalty) be
paid to Cumberland. The court reasoned that government approvals
were required only for the second stage's 25 percent payment and
that Cumberland had satisfied its obligations at the first stage by
providing the written certification of its retained engineer as
provided in subparagraph (v) that all work required under
paragraphs 2 and 4 had been completed. The district court affirmed
the order summarily, and Korman now appeals to us.
Interpretation of the settlement agreement presents a
legal issue which we resolve de novo. See Blackie v. State of Me.,
75 F.3d 716, 721 (1st Cir. 1996). Neither side suggests that there
Free access — add to your briefcase to read the full text and ask questions with AI
Korman v. Cumberland, (1st Cir. 1998).
Korman v. Cumberland (Korman v. Cumberland) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Dana Blackie v. State of Maine
75 F.3d 716 (First Circuit, 1996)