Korman Co. v. Cumberland Farms, Inc.

140 F.3d 331, 1998 WL 148820
CourtCourt of Appeals for the First Circuit
DecidedApril 7, 1998
Docket97-2180
StatusPublished
Cited by2 cases

This text of 140 F.3d 331 (Korman Co. v. Cumberland Farms, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Korman Co. v. Cumberland Farms, Inc., 140 F.3d 331, 1998 WL 148820 (1st Cir. 1998).

Opinion

BOUDIN, Circuit Judge.

The parties to this ease sought to settle a dispute between them, but the settlement agreement they reached has now given rise to a new dispute. Our own reading of the settlement agreement falls somewhere between the conflicting positions of the parties, but it is impossible to state the issue without some background and a description of the *332 pertinent terms of the agreement. Most, although not all, of the facts are undisputed.

The appellant, the Korman Company, leased a parcel of land to Chevron U.S.A., Inc., in Bensalem, Bucks County, Pennsylvania. Cumberland Farms, Inc., acquired the lease from Chevron in 1986 and used it to operate a gas station and convenience store. In 1992, Cumberland filed for bankruptcy in Massachusetts under Chapter 11.

The following year, Korman filed an adversary proceeding in the bankruptcy court, see Fed. R. Bankr.P. 7001, to eject Cumberland from the property, alleging that Cumberland had violated a provision of the lease. Cumberland then closed the gas station and reached a settlement with Korman, which the bankruptcy court approved. The dispute now before us arises out of the implementation of this settlement agreement.

In the settlement agreement, Korman agreed to buy out the remainder of Cumberland’s lease for $90,000, provided that Cumberland cleared the property of all structures and eliminated any unlawful contamination of the soil and groundwater. Anxious to regain the property swiftly, Korman agreed to pay $90,000 into an escrow account with the understanding that 75 percent of the account’s value would be released to Cumberland when it completed certain specified tasks. If Cumberland failed to complete these tasks by December 31,1994, the escrow account would be reduced by $10,000 for each month of delay, so the 75 percent payment—due when the specified tasks were completed—would be a declining amount. The remaining 25 percent of the escrow account is to be paid only when Cumberland’s “closure report” is approved by the Pennsylvania Department of Environmental Resources (“DER”) at the conclusion of the cleanup. 1

On February 7, 1995, Cumberland informed Korman that it would satisfy the requirements specified for release of 75 percent of the escrow account by February 8, 1995. This occurred somewhat more than a month after the December 31, 1994, deadline so the total amount of the escrow was already reduced by somewhat more than $10,-000. However, Korman refused to agree that any payment was due to Cumberland from the escrow, and Cumberland then filed a motion in the bankruptcy court to compel performance under the settlement agreement.

Paragraphs 2 and 4(a) of the agreement outline various tasks that Cumberland must perform to be entitled to the 75 percent payment. Korman admits that a number of the requirements were satisfied (e.g., removal of underground storage tanks and demolition of buildings). But Korman denies that Cumberland has satisfied requirements in paragraph 4(a)(iii) and (iv) relating to removal of contaminated soil, remediation of contaminated groundwater and installation of equipment required for long-term remediation. Paragraph 4(a) describes Cumberland’s pertinent obligations as follows:

iii) removal and replacement of contaminated soil, if any, and the commencement of remediation of any contaminated groundwater to the extent such removal and/or remediation is deemed necessary by the appropriate federal or state authorities;
iv) to the extent deemed necessary by the appropriate federal or state authorities, installation of any equipment and/or systems required for a long-term remediation system; and
v) delivery to Korman of written certification by a reputable licensed environmental consulting engineer that the work required in Paragraphs 2(a) through 2(d) and Paragraph 4(a)(i)-(iv) hereof has been completed.

*333 In the bankruptcy court, Cumberland argued that, without any direction from any federal or state agency, it had removed approximately 440 tons of contaminated soil and had installed underground piping that would enable future remediation if required. To show that it had satisfied the requirements of subparagraphs (iii) and (iv), Cumberland relied upon a letter from a firm of licensed geologists and engineers purporting to certify that Cumberland had satisfied all the requirements of paragraphs 2 and 4 of the agreement, a certification previously furnished to Korman. Cumberland also provided a letter from DER acknowledging that Cumberland had filed a closure report.

In response, Korman urged that subparagraphs (iii) and (iv) required Cumberland to follow procedures set out in DER’s environmental regulations, and it offered an affidavit of a consulting engineer, experienced in environmental projects, stating that Cumberland was required to receive DER approval prior to commencing remediation, and that fifing a closure report did not amount to such approval. The same affidavit asserted that contaminants in excess of DER’s cleanup standards were still present in the soil on the property.

The bankruptcy court held a telephone hearing on June 28, 1995, and issued an order on November 29, 1995, directing that 75 percent of the escrow account (as reduced by the delay penalty) be paid to Cumberland. The court reasoned that government approvals were required only for the second stage’s 25 percent payment and that Cumberland had satisfied its obligations at the first stage by providing the written certification of its retained engineer as provided in subparagraph (v) that all work required under paragraphs 2 and 4 had been completed. The district court affirmed the order summarily, and Korman now appeals to us.

Interpretation of the settlement agreement presents a legal issue which we resolve de novo. See Blackie v. State of Me., 75 F.3d 716, 721 (1st Cir.1996). Neither side suggests that there is any extrinsic evidence bearing on the meaning of the agreement, so inquiry is limited to the language and context of the agreement in an effort to ascertain what reasonable parties would have understood by the use of that language under the circumstances. See E.A. Farnsworth, Contracts § 5.9, at 510-11 (2d ed.1990).

Korman’s central position is that the agreement required Cumberland, in complying with the removal, replacement, commencement of remediation and installation requirements of subparagraphs (iii) and (iv), to obtain prior governmental approval of Cumberland’s remedial actions under the procedures promulgated by the Pennsylvania DER. Korman points specifically to the phrase “to the extent deemed necessary by the appropriate federal or state authorities,” which appears in subparagraphs (iii) and (iv). We do not think that this is a sustainable reading.

The most straightforward reading of the quoted phrase, in the context in the two paragraphs, is that removal, replacement, commencement of remediation and installation must meet the substantive requirements or standards set by the government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
140 F.3d 331, 1998 WL 148820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/korman-co-v-cumberland-farms-inc-ca1-1998.