Koerper v. Royal Investment Co.

77 S.W. 307, 102 Mo. App. 543, 1903 Mo. App. LEXIS 618
CourtMissouri Court of Appeals
DecidedNovember 17, 1903
StatusPublished
Cited by5 cases

This text of 77 S.W. 307 (Koerper v. Royal Investment Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koerper v. Royal Investment Co., 77 S.W. 307, 102 Mo. App. 543, 1903 Mo. App. LEXIS 618 (Mo. Ct. App. 1903).

Opinion

GOODE, J.

This is an action to enforce a mechanic’s lien for work done on the dwelling house No. 4623 Berlin avenue in St. Louis. What we are concerned with is a counterclaim set up by the defendant wherein it claims a forfeiture of five dollars a day for twenty-nine days, or one hundred and forty-five dollars. Plaintiff Koerper, who did business under the style of the American Stair Company, agreed to put in the stairways of said dwelling and some others then being constructed by the defendant. The contract was made by the following proposal, which was accepted by the defendant :

[546]*546“St. Louis, Mo., Feb. 18, 1902.
“Royal Investment Co.:
“We propose and agree to furnish and build the following stairs called for under the heading of stairs in and according to the plans and specifications prepared by............, architect, for the building to be erected for one house owner, located at 4623 Berlin avenue, unless otherwise specified below:
1 main flight of stairs, quarter white oak;
1 rear flight of stairs, yellow pine.
1 attic flight of stairs, yellow pine, for the sum of two hundred and eight dollars, $208.00.
“Terms: One-half cash when stairs are roughed up; balance due when same are completed.
“Respectfully,
“American Stair Co.,
(Accepted.) By L. J. Koerper.”

Koerper was slow about finishing the stairs — unreasonably slow the defendant asserts; and was several times notified by the latter to expedite the work on the stairs of this and the other houses. Those notices failed to hasten the work rapidly enough to satisfy the defendant; so on June 20, 1902, a letter was addressed to the plaintiff notifying him of the cancellation of his contracts/ Said letter was as follows:

“June 20, 1902.
“American Stair Company, City:
“Gentlemen: — You are hereby notified that we this date cancel your contracts for 4623-33 Berlin avenue and 5053 Westminster Place owing to the fact that you have failed to do anything you have agreed to do.
“We do this after sending a representative to your office to find out whether you are in a position to complete the work and whether you have the material on hand, which we find you have not; besides there is nobody there to attend to business.
[547]*547“We will have the work finished and charge the same to your contract account. We will have it finished at once.
“Yours truly,
“Royal Investment Co.,
“C. R. H. Davis, Pres.”

This letter was received on the day it was written and plaintiff thereupon called the president of the defendant company hy telephone and protested against the attempted cancellation, as he had almost finished the work. Davis told Koerper to come to the former’s office and they would talk the matter over. Koerper went and the result of the interview was the submission of the following proposal by the plaintiff and its acceptance by the defendant:

‘ ‘ St. Louis, June 23,1902.
“Royal Investment Company, City.
“Gentlemen: — We agree to finish complete 4623 Berlin avenue by the first day of July or forfeit $5.00 a day for every day after July 1st, that expires until the stairs are completed.
“We also agree to finish 4633 Berlin avenue by July 5th or forfeit $5.00 per day.
“We also agree to finish 5053 Westminster Place complete by July 6th or forfeit $5.00 per day.
“If in the event over five days should elapse between the date we agree to complete the stairs, we hereby authorize the Royal Investment Company to have the stairs completed at our expense.
“It is agreed and understood that the payment is to be spot cash upon the completion of each house, providing the other work is progressing according to this agreement.
“Yours truly,
“American Stair Company,
“Per J. L. Koerper.”

[548]*548After the execution of that agreement the work still proceeded slowly, notwithstanding hurry notices from the defendant, and was not finished until the latter part of July; plaintiff says the 26th and defendant the 29th.

The counterclaim is based on the provision of the last contract for a forfeiture of five dollars a day unless the stairs were completed by July 1st. Koerper asserts that the sole cause of the delay prior to June 23d, when the contract for a forfeiture was signed, as well as subsequent to that date, was the failure of the defendant to pay him one-half the contract price when the stairs were done in the rough, as, by the original contract, the defendant was bound to do so; that on account of not being paid he was unable to get material or hands to finish the work. Pie further contends that the sole consideration for his signing the contract providing, for a forfeiture, was the agreement of the defendant to pay what was due him on account.

The circuit court held the provision for a forfeiture of five dollars a day should be treated as penalty instead' of liquidated damages, and that in no event was the defendant entitled to recover more than nominal damages on its counterclaim, as it made no proof of actual damages. t The defendant insists that this ruling was erroneous ; and that is the main proposition discussed by its counsel But for the question of penalty or agreed damages to become material, it is indispensable that the contract providing for forfeiture should be supported by a consideration; otherwise whatever its meaning is, it is a nude pact.

One theory of consideration presented by the defendant is that in making the second contract it waived any claim for loss theretofore entailed by plaintiff’s failure to complete the stairs in a reasonable time. Suffice to say as to this proposition, that there is nothing in the contract of June 23d referring to a claim by defendant [549]*549for damages for previous delay or undertaking to waive such, a claim.

Another proposition relied on in this connection is that if the plaintiff had broken his agreement prior to June 23d, by failing to finish the stairs in a reasonable time and remained in default after repeated demands for performance, those facts gave the defendant a right to cancel the original contract, as it undertook to do on June 23d; and that the original contract being then at an end, the parties made a new one, giving the plaintiff until July first to finish the stairs and binding defendant to pay him the price originally stipulated.

The first agreement contains no clause providing for its annulment or rescission by one party for the other’s breach. The defendant’s right to rescind it for non-performance by plaintiff depends therefore on the rules of contract law which define the limits of the right to rescind for a breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koslosky v. Bloch
177 S.W. 1060 (Missouri Court of Appeals, 1915)
Shriner v. Craft
51 So. 884 (Supreme Court of Alabama, 1910)
Laswell v. National Handle Co.
126 S.W. 969 (Missouri Court of Appeals, 1910)
Hanson v. Crawford
109 S.W. 98 (Missouri Court of Appeals, 1908)
Lavin v. Grand Lodge of the Ancient Order of United Workmen
86 S.W. 600 (Missouri Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
77 S.W. 307, 102 Mo. App. 543, 1903 Mo. App. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koerper-v-royal-investment-co-moctapp-1903.