Kobyluck Bros., LLC v. Planning & Zoning Comm'n of Waterford

142 A.3d 1236, 167 Conn. App. 383, 2016 Conn. App. LEXIS 308
CourtConnecticut Appellate Court
DecidedAugust 2, 2016
DocketAC37732
StatusPublished
Cited by34 cases

This text of 142 A.3d 1236 (Kobyluck Bros., LLC v. Planning & Zoning Comm'n of Waterford) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kobyluck Bros., LLC v. Planning & Zoning Comm'n of Waterford, 142 A.3d 1236, 167 Conn. App. 383, 2016 Conn. App. LEXIS 308 (Colo. Ct. App. 2016).

Opinion

DiPENTIMA, C.J.

*385 The plaintiffs, Kobyluck Brothers, LLC (Kobyluck Brothers), and Kobyluck Construction, Inc. (Kobyluck Construction), appeal from the judgment of the trial court affirming the decision of the defendant, the Planning and Zoning Commission of the Town of Waterford (commission), denying the plaintiffs' special permit and site plan application. 1 The plaintiffs claim that the court incorrectly interpreted the term "manufacturing" as used in the Waterford Zoning Regulations (regulations) to preclude the production of construction aggregate. 2 We agree, and, accordingly, reverse the judgment of the trial court.

The record reveals the following relevant undisputed facts and procedural history. Kobyluck Brothers owns 28 Industrial Drive (property), the parcel at the center *386 of the dispute, in Waterford. The property is a thirty-seven acre parcel of land in an industrial park at the eastern end of a cul-de-sac street. Adjacent to the property, Kobyluck Brothers also owns 24 Industrial Drive, which contains a concrete manufacturing plant operated by Kobyluck Construction.

On December 5, 2011, the plaintiffs applied to the commission for a special permit and site plan approval seeking permission to construct a "building materials manufacturing facility" on the property. According to the plaintiffs, because the property was located in a general industrial *1239 district (I-G district), the proposed development was consistent with the town's land use plan and permitted under § 11.2 of the regulations. Relevant to this appeal, § 11.2.11 of the regulations provided, in relevant part, that the following was a permitted use in an I-G district: "Manufacture of asphalt, cement, cinder block, or other building materials...."

The plaintiffs' principal purpose in applying for a special permit and site plan approval was to build a permanent facility to "manufactur[e] ... earth products used in the construction industry," i.e., "crushed stone, septic gravel, and aggregate...." 3 To accomplish this, the plaintiffs first needed to excavate and remove from the property approximately 350,000 cubic yards of earth products, which included bedrock. The *387 extracted earth products would be crushed and sorted by industrial machinery; afterward, the finished product would be removed from the property. Once the permanent facility was completed, the plaintiffs would no longer extract materials from the property. Rather, the plaintiffs intended to bring raw materials from off-site to their permanent facility and then transport the finished products off-site. In short, the plaintiffs sought to crush extracted bedrock into a product suitable for use in the construction industry.

Public hearings on this application began on April 9, 2012, and continued to various dates thereafter, concluding on June 25, 2012. Subsequently, the commission unanimously denied the plaintiffs' application on July 9, 2012. Relevant to this appeal, the commission found that the plaintiffs' proposed use was not permitted under § 11.2.11 of the regulations. Specifically, it determined that the plaintiffs' proposed use was "processing" and not "manufacturing." The plaintiffs filed a timely appeal with the Superior Court on July 26, 2012.

On April 10, 2014, the court held a hearing on the threshold issue of whether the plaintiffs' applications were for a permitted use in an I-G district. See footnote 1 of this opinion. On July 31, 2014, the court issued a memorandum of decision. After determining that the "rock crushing facility proposed by the plaintiff [did] not constitute 'manufacturing,' " the court concluded that the plaintiffs' proposed use of the property was not a specially permitted use under the regulations when the plaintiffs filed their application.

Preliminarily, the court described the plaintiffs' proposed use: "[T]here can be no question that what the plaintiffs intend to do on th[e] property is crush rocks-that is, either from materials on-site or materials brought from off-site. The plaintiffs intend to process rocks and crush them into smaller rocks, which would *388 be used for various construction projects." The court then set forth the parties' arguments: "The plaintiffs argue that a rock crushing facility would fall within the scope of § 11.2.11 of the zoning regulations because that proposed use constitutes the *1240 manufacture of building materials. The [commission] counters that rock crushing does not qualify as 'manufacturing,' but rather is classified as 'processing' rock through a rock crushing facility, and such processing of rock is not a permitted use under § 11.2.11." Accordingly, the court proceeded to construe the term "manufacturing" as used in § 11.2.11 of the regulations.

The court found § 11.2.11 of the regulations ambiguous for two reasons. First, neither "manufacture" nor "building materials" was defined in the regulations. Second, the court determined that the plaintiffs' proposed use of "crush[ing] large rocks into smaller rocks" that "would subsequently be sold for use in construction projects" was distinct from the manufacturing of asphalt, cement, or cinder blocks, which was expressly enumerated in § 11.2.11, because the latter products required "various ingredients [to be] mixed to form a new product...." Having found that the regulation was ambiguous, the court appropriately sought interpretative guidance. See, e.g., Anatra v. Zoning Board of Appeals, 307 Conn. 728 , 739, 59 A.3d 772 (2013).

Specifically, the court looked at "(1) internal clues in the regulations themselves, (2) dictionary definitions of the word 'manufacture,' and (3) the manner in which other cases have construed 'manufacture' in its common usage, both generally and specifically to rock crushing." Its interpretative analysis led the court to conclude that the plaintiffs' "excavation and crushing of rock to create aggregate [did] not constitute 'manufacturing' of other building materials under the regulations, and is more properly classified solely as 'processing' of the materials." Accordingly, the court *389 found that the plaintiffs' proposed use of the property was not a specially permitted use. On October 16, 2014, the court issued an order expressly affirming the commission's denial of the plaintiffs' special permit and site plan approval application. This appeal followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McHenry Solar, LLC v. Hampton
Connecticut Appellate Court, 2025
Commission on Human Rights & Opportunities v. Cantillon
207 Conn. App. 668 (Connecticut Appellate Court, 2021)
Ash Grove Cement Co. v. Nebraska Dept. of Rev.
306 Neb. 947 (Nebraska Supreme Court, 2020)
Putnam Park Apartments, Inc. v. Planning & Zoning Commission
193 Conn. App. 42 (Connecticut Appellate Court, 2019)
Town of Wethersfield v. PR Arrow, LLC
203 A.3d 645 (Connecticut Appellate Court, 2019)
Arlin George Hatfield, III v. Madison County Board of Supervisors
235 So. 3d 18 (Mississippi Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
142 A.3d 1236, 167 Conn. App. 383, 2016 Conn. App. LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kobyluck-bros-llc-v-planning-zoning-commn-of-waterford-connappct-2016.